Contract Advertisement Report

CleanPowerSF Sfpuc Commission
February 14, 2023

Document
Contract Advertisement Report
Meeting
February 14, 2023
Body
CleanPowerSF Sfpuc Commission
Original file
595 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.

Project Administration Bureau
525 Golden Gate Avenue, 8th Floor
San Francisco, CA 94102
T 415.554.4306
F 415.554.3225
TTY 415.554.3488

TO: Commissioner Newsha Ajami, President
Commissioner Sophie Maxwell, Vice President
Commissioner Tim Paulson
Commissioner Tony Rivera
Commissioner Kate Stacy

THRU: Dennis J. Herrera, General Manager

FROM: Ivy Fine, Deputy Assistant General Manager,
Project Administration Bureau, Infrastructure Division

Stephen Robinson, Assistant General Manager, Infrastructure Division

DATE: February 6, 2023

SUBJECT: Contract Advertisement Report: February 14, 2023

CONSTRUCTION:

Contract Number and Title:

WW-735, Various Locations Main Sewer
Inspection No. 1
Estimated Cost of
Services:
$ 2,000,000
Program:

SFPUC Wastewater Enterprise, Renewal and Replacement (R&R) Program Estimated date of advertisement:

March 2023
Description of contract work:

Contract work consists of video camera inspection of existing main sewer, sewer lateral and culvert pipelines at various locations within the City and County of San Francisco.

Project Manager:

John Wong

Contract Number and Title:

WD-2862, San Antonio Pump Station Motor
Control Center Replacement & Seismic Retrofit
Estimated Cost of Services:
$6,500,000
Program:

Water Enterprise CIP

Estimated Date of Advertisement:

February/March 2023

Description of Contract Work:

The objective of the project is to replace the motor control centers and appurtenant equipment, and seismically upgrade the San Antonio Pump Station in Sunol, CA.

Project Manager:

Alisha Reinhardt