DEPARTMENT

Infrastructure

AGENDA NO.

6c

MEETING DATE

February 28, 2023

APPROVAL:

COMMISSION

SECRETARY

Donna Hood

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Construction Modification: Consent Calendar
Contract Manager: Carman Luk

Approve Increase to Contract Amount and Duration Contingencies for Contract No.

WW-675, 5th/18th/Upper Larkin Street Sewer Inspection

Summary of Proposed
Commission Action:

Approve an increase of $180,000 to the contract cost contingency, and an increase of 180 calendar days (approximately six months) to the contract duration contingency, for Contract No. WW-675, 5th/18th/Upper Larkin Street Sewer Inspection; and authorize the General Manager to approve future modifications to the contract for a total contract amount of up to $2,378,170 and a total contract duration of up to 345 consecutive calendar days. Staff seeks the increase in cost contingency to perform an additional half mile of sewer and lateral inspections. The increase in duration contingency is needed to perform the additional sewer and lateral inspections and to complete post- processing videos coding, quality control, and to allow time for the City’s review and approval process.

Background: The San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise (WWE) inspects sewers to identify areas needing rep air to avoid failures in the system. WWE Collection System Division (CSD) has identified the sewers in this project to be in need of inspection based on age, size, hydraulic capacity, and/or location. The purpose of this contract is to provide inspection s ervices of these existing sewers to supplement WWE CSD staff’s on-going inspection work. The cleaning and inspection work will assist with the ongoing inspection/data gathering necessary for SFPUC WWE’s Collection System Asset Management Program.

On March 22, 2022, by Resolution No. 22-0057, the Commission awarded Contract No. WW-675, 5th/18th/Upper Larkin Street Sewer Inspection. The original contract amount was $1,998,336, and the original contract duration was 150 consecutive calendar days.

Contract: WW-675, 5th/18th/Upper Larkin Street Sewer Inspection Commission Meeting Date: February 28, 2023

Description of Scope of
Work:

The contract work consists of inspection and as -needed cleaning of existing sewers and laterals using automated camera and camera inspection. Inspection work locations included:

• 5th Street, from Market to Berry Streets
• Jessie Street, from Jessie West to 5th Streets
• Minna Street, from 4th to 6th Streets
• Natoma Street, from 5th to 6th Street
• Tehama Street, from dead end east of 5th to 5th Streets • 18th Street from Danvers to Eureka Streets, and Collingsworth Street to Treat Avenue
• Douglass Street, from 18th to Caselli Streets
• Valencia Street, from 17th to 18th Streets
• Larkin Street, from Turk to Ellis Streets, and Olive to Bush Street
• Bush Street, from Larkin to Polk Street
• Polk Street, from Bush to Pine Streets, Post to Sutter Streets, and Larkin to Polk Streets

Changes and
Modifications to the
Contract:

The initial contract consist ed of inspection and cleaning of approximately 3.4 miles of existing sewers using automated camera and camera inspection. Staff determined it would be prudent to add an additional half mile of sewer locations for a total of approximately four miles of existing sewers to be inspected under this contract, which is the targeted mileage for this contract.

The additional locations are as follows:

• Bay Street, from Kearny Street to Embarcadero
• Greenwich Street, from Jones Street to Mason Street
• Lombard Street, from Powell Street to Taylor Street
• Mason Street, from Francisco Street to Chestnut Street , and at Beach Street intersection
• Taylor Street, from Greenwich Street to Filbert Street

Requested Increase to Contract Cost and Duration Contingency Staff recommends a n increase of $180,000 to the existing cost contingency and an i ncrease of 180 calendar days to the existing duration contingency to perform the additional half mile of sewers and laterals inspections at the locations listed above , for a total contract amount of up to $2,378,170, and a total contract duration of up to 345 consecutive calendar days. The recommended duration contingency increase will provide additional time to complete the additional inspection work in these high- traffic areas and also for provide additional time to complete post- processing videos coding, quality control, and allow time for the City’s review and approval process.

Contract: WW-675, 5th/18th/Upper Larkin Street Sewer Inspection Commission Meeting Date: February 28, 2023

Budget & Costs: Funding: Project No. 10036832, 5th/18th/Upper Larkin Street Sewer Inspection
Original Contract Amount: $1,998,336
Original 10% Cost Contingency: $199,834
Requested Additional Cost Contingency: $180,000
Total Revised Contract Cost Limit: $2,378,170

Schedule: Notice-to-Proceed Date: August 22, 2022
Original Contract Duration: 150 consecutive calendar days Original 10% Duration Contingency: 15 calendar days
Requested Additional Duration Contingency: 180 calendar days Total Revised Contract Duration Limit : 345 consecutive calendar days

Compliance with
Chapter 14B: Local
Business Enterprise
Utilization and Non-
Discrimination in
Contracting Ordinance:

The Contract Monitoring Division established a 10% Local Business Enterprise ( LBE) subcontracting requirement for this contract. The contractor committed to 12.71% LBE participation in its bid submittal.

Recommendation: SFPUC staff recommends that the Commission adopt the attached resolution.

Contract: WW-675, 5th/18th/Upper Larkin Street Sewer Inspection Commission Meeting Date: February 28, 2023

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) performs cleaning, debris removal, and inspection of existing sewer lines to identify locations with a high risk of potential failure bases on asset age, size, hydraulic capacity, and/or location; and WHEREAS, On March 22, 2022, by Resolution No. 22- 0057, the Commission awarded Contract No. WW-675, 5th/18th/Upper Larkin Street Sewer Inspection to Pipe and Plant Solutions, Inc.; and
WHEREAS, The construction contract Notice-to-Proceed date was August 22, 2022; and WHEREAS, The original contract amount was for $1,998,336, the original contract duration was 150 consecutive calendar days, and the contract provided for inspection and cleaning of 3.4 miles of sewers and laterals; and
WHEREAS, Staff recommends an increase of $180,000 to the contract cost contingency and an increase of 180 calendar days to the contract duration contingency in order to inspect and clean an additional have mile of sewers and laterals and to complete post-processing videos coding, quality control, and allow time for the City’s review and approval process; and WHEREAS, Contract Monitoring Division established a 10% Local Business Enterprise (LBE) subcontracting participation requirement or this contract, and the contractor committed to

12.71% LBE participation in its bid submittal; and
WHEREAS, Funds are available from Project No. 10036832, 5th/18th/Upper Larkin Street Sewer Inspection; now, therefore, be it
RESOLVED, That this Commission hereby approves an increase of $ 180,000 to the existing contract cost contingency and an increase of 180 calendar days to the existing contract duration contingency, for Contract No. WW-675, 5th/18th/Upper Larkin Street Sewer Inspection, for a total contract cost contingency amount of up to $379,834 and a total contract duration contingency of 195 calendar days; and be it
FURTHER RESOLVED, That this Commission hereby authorizes the General Manager or the General Manager’s designee to consider and, if appropriate, to approve any future modifications to the contract amount for a total contract amount of up to $2,378,170, and a total contract duration of up to 345 consecutive calendar days.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of February 28, 2023

Secretary, Public Utilities Commission