Cities Index.
Contract Advertisement Report

CleanPowerSF Sfpuc Commission
April 11, 2023

Document
Contract Advertisement Report
Meeting
April 11, 2023
Body
CleanPowerSF Sfpuc Commission
Original file
301 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.

Project Administration Bureau
525 Golden Gate Avenue, 8th Floor
San Francisco, CA 94102
T 415.551.4603
F 415.554.3225
TTY 415.554.3488

TO: Commissioner Newsha K. Ajami, President
Commissioner Sophie Maxwell, Vice President
Commissioner Tim Paulson
Commissioner Anthony Rivera
Commissioner Kate H. Stacy

THRU: Dennis J. Herrera, General Manager

FROM: Ivy Fine, Deputy Assistant General Manager,
Project Administration Bureau, Infrastructure Division

Stephen Robinson, Assistant General Manager, Infrastructure Division

DATE: March 30, 2023

SUBJECT: Contract Advertisement Report: April 11, 2023

CONSTRUCTION:

Contract Number and Title:

DB-134 Biogas Utilization Project
Estimated Cost:
$50,000,000
Program:

San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise, Sewer System Improvement Program (SSIP)
Estimated Date of Advertisement:

April 2023 (Request for Qualifications (RFQ))
Description of Contract Work:

Design, build, finance, operate and maintain the Biogas Utilization Project through a public-private partnership agreement. The Biogas Utilization Project will include treating the biogas generated in the new digesters to natural gas quality, injection into the adjacent PG&E natural gas pipeline, and sale as a renewable fuel, which City anticipates will be eligible for environmental credit programs.

Project Manager:

Daniela Brandao
Lyman for Fine

Contract Number and Title: Estimated Cost:

JOC-95, General Engineering (A-License), with
Marine Emphasis San Francisco, San Mateo,
Alameda and Santa Clara Counties
$ 5,000,000
Program:

N/A
Estimated Date of Advertisement:

April 2023
Description of Contract Work:

Contract work locations are San Francisco, San Mateo, Alameda and Santa Clara Counties. This General Engineering (A-License) Job Order Contract may be used to perform construction maintenance, repair and/or rehabilitation work at SFPUC facilities, watershed lands and other San Francisco City and County- owned property as set forth in the contract bidding documents, and may include the following: Moving, Wrecking, Carpentry, Cathodic Protection, Concrete, Construction Traffic Control Services, Earthwork & Paving, Electrical, Hazardous Materials, Heating, Ventilation, Air Conditioning, Marine Related, Painting/Waterproofing, Pipeline, Plumbing, Reinforcing Steel, Sheet Metal, Structural Steel, Trucking & Hauling, Welding, and Well Drilling.

Project Manager:

Judy Chin

Contract Number and Title: Estimated Cost:

JOC-96, General Engineering (A-License)
Construction within San Joaquin, Stanislaus,
and Tuolumne Counties, Hetch Hetchy
$ 5,000,000
Program:

N/A
Estimated Date of Advertisement:

April 2023
Description of Contract Work:

Contract work locations are San Joaquin, Stanislaus, and Tuolumne Counties. This Job Order C ontract will be utilized to construct, maintain, repair and/or install general engineering (A – License) tasks and facilities for all SFPUC enterprise operations, bureaus and other areas as set forth in the contract bidding documents, and may include the f ollowing: Moving, Demolition, Cathodic Protection, Concrete, Construction Traffic Control Services, Earthwork & Paving, Electrical, Hazardous W aste and Remediation Service, Landscape, Masonry, Painting/Waterproofing, Pipeline, Plumbing, Reinforcing Steel, Security Integration, Tree Service, Trucking & Hauling, Welding, Well Pump Repair, and Well Drilling.

Project Manager:

Judy Chin

Contract Number and Title: Estimated Cost:

WW-738, East SOMA Sewer Improvements $ 11,200,000
Program:

SFPUC Wastewater Enterprise, SSIP
Estimated date of advertisement:

June 2023
Description of contract work:

The purpose of the project is to rehabilitate and/or replace approximately 4,900 linear feet of existing sewers, and associated manholes, laterals, culverts and other appurtenances on 7th, Mission, Howard, 3rd, Harrison, and Bryant Street. The sewers are constructed of brick materials, egg-shaped, and are generally 3-foot wide by 5-foot high in size. Rehabilitation will be via the cured-in-place liner (CIPL) method. Other work includes: traffic control, and pavement restoration work.

Project Manager:

Carman Luk

Contract Number and Title: Estimated Cost
WW-739, As-needed Large Diameter Sewer
Cleaning
$ 1,000,000
Program:

SFPUC Wastewater Enterprise, SSIP
Estimated date of advertisement:

May 2023
Description of contract work:

As-needed sewer cleaning for combined sewers, measuring 36-inch diameter or larger box sewers, within the City and County of San Francisco.

Other work will consist of mobilization; demobilization; traffic control; handing, testing, transportation, and disposal of debris.

Project Manager:

Carman Luk

PROFESSIONAL SERVICES:

Contract Number and Title: Contract Estimate:

PRO.0209 As Needed Recruitment Services $300,000 cumulative (Three (3) contracts, each for not-
to-exceed value of
$100,000)
Program:

Human Resource Services (HRS)
Estimated date of advertisement:

April 2023
Description of contract work:

The SFPUC seeks to retain services of up to three professional executive search firms to conduct nationwide executive searches that require executive recruitment services for high profile, hard-to-fill positions including those for positions that are a part of the executive team.