OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.
Project Administration Bureau
525 Golden Gate Avenue, 8th Floor
San Francisco, CA 94102
T 415.551.4603
F 415.554.3225
TTY 415.554.3488
TO: Commissioner Newsha K. Ajami, President
Commissioner Sophie Maxwell, Vice President
Commissioner Tim Paulson
Commissioner Anthony Rivera
Commissioner Kate H. Stacy
THRU: Dennis J. Herrera, General Manager
FROM: Ivy Fine, Deputy Assistant General Manager,
Project Administration Bureau, Infrastructure Division
Stephen Robinson, Assistant General Manager, Infrastructure Division
DATE: June 1, 2023
SUBJECT: Contract Advertisement Report: June 13, 2023
CONSTRUCTION:
Contract Number and Title:
WW-750 Southeast Water Pollution Control
Plant SEP7 Operations, Engineering, &
Maintenance and Maintenance Mechanical
Buildings
Contract Estimate:
$55,400,000
Program:
WWE-CIP
Estimated Date of Advertisement:
June 2023
Description of Contract Work:
Contract work consists of construction manager/general construction services for construction of two new buildings Operations, Engineering, and Maintenance and Maintenance Mechanical buildings at the Southeast Water Pollution Control Plant. The scope of work includes demolition of existing structure and parking lot; and construction of two buildings with industrial shops, showers and locker rooms, and offices. The project will include relocating existing facilities and utilities, and two chemical tanks.
Project Manager:
Janelle Plummer
for
PROFESSIONAL SERVICES:
Contract Number and Title:
PRO.0227(R), As-Needed Power Operations
Support (Re-bid)
Contract Estimate:
8,000,000 cumulative
(Up to four (4)
agreements;
$2,000,000 per
agreement)
Program:
Power Enterprise
Estimated Date of Advertisement:
July 2023
Description of Contract Work:
The SFPUC seeks to retain services to assist with power-operations support including assisting in power supply management, grid expansion, customer growth, Integrated Resource Plan related support, risk management, settlements, power scheduling, and trading. The SFPUC would also like to utilize the contractor’s expertise in business and strategic planning to support both its publicly owned utility and Community Choice Aggregation business lines.
Project Manager:
Randi H. Cheuk
Contract Number and Title:
PRO.0234 CleanPowerSF In-City Solar
Contract Estimate:
$76,000,000
Program:
Power Enterprise
Estimated Date of Advertisement:
June 2023
Description of Contract Work:
The City seeks to retain the services of a qualified Proposer to assist with renewable energy projects to be built on San Francisco Public Utilities Commission owned property (1st phase: Stanford Heights Reservoir, Summit Reservoir, Sutro Reservoir, University Mound Reservoir - North Basin).
Project Manager:
Michael Foley
Contract Number and Title:
PRO.0262, Technical Services - Renewable &
Advanced Energy Generation
Contract Estimate:
$12,000,000
cumulative (Up to
three (3)
agreements;
$4,000,000 per
agreement)
Program:
Power Enterprise
Estimated Date of Advertisement:
July 2023
Description of Contract Work:
The SFPUC seeks to retain services to assist with renewable energy technical evaluation, project development, implementation, permitting, and design support during construction of renewable and advanced energy technologies. The SFPUC would also like to utilize the contractor’s expertise to provide other related evaluation engineering support and data analysis services, as well as support for energy program and policy development and implementation.
Project Manager:
Jamie Seidel