Cities Index.
Contract Advertisement Report

CleanPowerSF Sfpuc Commission
August 22, 2023

Document
Contract Advertisement Report
Meeting
August 22, 2023
Body
CleanPowerSF Sfpuc Commission
Original file
227 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.

Project Administration Bureau
525 Golden Gate Avenue, 8th Floor
San Francisco, CA 94102
T 415.551.4603
F 415.554.3225
TTY 415.554.3488
TO: Commissioner Newsha K. Ajami, President
Commissioner Sophie Maxwell, Vice President
Commissioner Tim Paulson
Commissioner Anthony Rivera
Commissioner Kate H. Stacy
THRU: Dennis J. Herrera, General Manager
FROM: Ivy Fine, Deputy Assistant General Manager,
Project Administration Bureau, Infrastructure Division
Stephen Robinson, Assistant General Manager, Infrastructure Division
DATE: August 10, 2023
SUBJECT: Contract Advertisement Report: August 22, 2023 CONSTRUCTION:

Contract Number and Title:

HH-1009, San Joaquin Pipeline Valve and Safe Entry Improvements:

Phase 3 – Tesla Surge Tower
Contract Estimate:
$16,500,000
Program:

Hetchy Capital Improvement Program
Estimated Date of Advertisement:

August 2023
Description of Contract Work:

This contract is for Phase 3 of Project #10035575 San Joaquin Pipeline (SJPL) Valve and Safe Entry Improvements. It is to build a new surge tower to control the surge pressure in the SJPL system. The scope of work includes building new facilities such as 1) approximately 900 ft long 60- inch diameter steel pipe, 2) an approximately 65-ft tall surge tower, 3) a water recirculation system, 4) a gravel access road; and revamping the existing spillway and drainage culverts.

Project Manager:

Jimmy Leong
for DJH