DEPARTMENT
Infrastructure
AGENDA NO.
7c
MEETING DATE
January 23, 2024
AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
Calendar: Consent Calendar
Project Manager: Tracy Cael
Approve Increase to Construction Duration Contingency for Contract No. WD-2878A, Regional Groundwater Storage and Recovery Phase 2A
Summary of
Proposed
Commission
Action:
Approve a 290-calendar-day increase to the construction duration contingency for Contract No. WD -2878A, Regional Groundwater Storage and Recovery Phase 2A , with Marinship Development Interest LLC , for a new construction duration limit of up to 958 consecutive calendar days (approximately two years and eight months), with no change to the Contract amount, to allow for installation of the variable frequency drives that have been delayed, and are sti ll awaiting delivery , due to supply chain issues.
Background: The purpose of the San Francisco Public Utilities Commision (SFPUC) Regional Groundwater Storage and Recovery P roject is provide additional dry year water supply to the regional water system by constructing up to 13 groundwater well stations that will be connected to three wholesale customers on the Upper Peninsula and to the SFPUC transmission system.
Construction of the Project is being performed in two phases to to expedite installation of most of the wells in Phase 1, while allowing for later contracts in Phase 2 for work requiring long lead time to secure permits and easements . The Phase 1 work is complete, which included the installation of 13 well stations..
The Phase 2 work has been separated into two contracts. Phase 2A, under this Contract No. WD-2878A, consists of additional improvements at 10 out of the 13 well sites installed in Phase 1, including installation of cathodic protection, variable frequenc y drives, flowmeters for water accounting, valve modifications, and well rehabilitation.
Phase 2B, currently in the bid and award phase, consists of work at Antoinette Well (also known as South San Francisco Main Well ) for installation of the groundwater pump system, electrical and mechanical work, and pipeline installation.
On February 22, 2022, by Resolution No. 22-0040, this Commission awarded Contract No. WD -2878A, Regional Groundwater Storage and Recovery Phase 2A , to Marinship Development Interest LLC. The original Contract amount was $6,850,000, and the original Contract duration was 608 consecutive calendar days.
Agenda Title: WD-2878A, Regional Groundwater Storage and Recovery Phase 2A Commission Meeting Date: January 23, 2024
Scope of
Contract:
The Contract work for this Phase 2A Contract No. WD-2878A consists of installation of cathodic protection, variable frequency drives, flowmeters for water accounting, valve modifications, and well rehabilitation at 10 groundwater well facilities.
Construction under Contract No. WD -2878A is ongoing, and is approximately 60% complete as of the end of November 2023.
Modification
s to the
Contract:
Modification Nos. 1 and 2: The SFPUC modified the Contract within the approved contingency and decreased the C ontract amount by $288,605 to reduce the well rehabilitation and redevelopment scope s, add temperature s ensors for variable frequency drives, increase special inspection allowance, and replace bearings for the pumps, for a total Contract amount of $6,561,395.
Recommended Increase to Contract Duration Contingency : Staff recommends approval of an additional duration contingency in the amount of 290 calendar days, for a new C ontract duration limit of up to 958 consecutive calendar days (approximately 2 years and 8 months), with no change to the Contract amount, to allow for installation of the variable frequency drives that have been delayed, and are still awaiting delivery due, due to supply chain issues.
Funding and
Costs:
Funding Source: Water Enterprise, Project No. CUW30103, Regional Groundwater Storage and Recovery
Original Contract Amount: $6,850,000
Original 10% Cost Contingency: $685,000
Requested Additional Cost Contingency: $0
Total Contract Amount: $6,561,395
Total Contract Cost Limit: $7,535,000
Schedule: Notice-to-Proceed Date: June 23, 2022
Original Contract Duration: 608 consecutive calendar days Original 10% Duration Contingency: 60 calendar days
Requested Additional Duration Contingency: 290 calendar days Total Contract Duration Limit: 958 consecutive calendar days
Environment
al Review:
On October 30, 2008, the San Francisco Planning Commission certified the Final Program Environmental Impact Report (Program EIR) (Case Number 2005.0159E) for the Water System Improvement Program. On August 7, 2014, the Planning Commission ce rtified the Final Environmental Impact Report (F inal EIR) for the Regional Groundwater Storage and Recovery Project (Case Number 2008.1396E) , which is tiered from the 2008 Program EIR.
Since the Program EIR and the Final EIR were finalized, there have bee n no substantial project changes and no substantial changes in project circumstances that would require major revisions to the F inal EIR due to the involvement of new significant environmental effects or an increase in the severity of previously identified significant impacts, and there is no new information of substantial importance that would change the conclusions set forth in the Final EIR.
Agenda Title: WD-2878A, Regional Groundwater Storage and Recovery Phase 2A Commission Meeting Date: January 23, 2024
The 2008 Program EIR can be found here: https://sfplanning.org/environmental- review-
documents?title=Water+System&field_environmental_review_categ_target_id=212 &items_per_page=10
The 2014 Final EIR, Resolution No. 14-0127, CEQA Findings and Mitigation Monitoring and Reporting Program can be found here:
https://sfpuc.sharefile.com/d-s1a3843770374401f986f04471c8e6260
Local
Business
Enterprise
Participation
and Non-
Discriminati
on In
Contracting:
The Contract Monitoring Division established a 10% Local Business Enterprise (LBE) subcontracting requirement for this Contract. The contractor committed to 41.07 % LBE participation with its bid submittal.
Agenda Title: WD-2878A, Regional Groundwater Storage and Recovery Phase 2A Commission Meeting Date: January 23, 2024
SITE MAP
PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO.
WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Regional Groundwater Storage and Recovery P roject is necessary to provide additional dry year water supply and includes construction of up to 13 groundwater well stations that SFPUC will connect to three wholesale customers on the Upper Peninsula and to the SFPUC transmission system; and WHEREAS, On February 22, 2022, by Resolution No. 22-0040, this Commission awarded Contract No. WD-2878A, Regional Groundwater Storage and Recovery Phase 2A , to Marinship Development Interest LLC; and
WHEREAS, The original C ontract amount was for $6,850,000 and the original C ontract duration was 608 consecutive calendar days; and
WHEREAS, The Contract Notice-to-Proceed date was June 23, 2022; and WHEREAS, Modification Nos. 1 and 2 decreased the C ontract amount by $288,605 to reduce the well rehabilitation and redevelopment scopes, add temperature sensors for variable frequency drives, increase special inspection allowance, and replace bearings for the pumps, for a total Contract amount of $6,561,395; and
WHEREAS, Staff recommends an increase to the C ontract duration contingency by 290 calendar days , for a new C ontract duration limit of up to 958 consecutive calendar days (approximately two years and eight months), with no change to C ontract amount to allow for installation of the variable frequency drives that have been delayed, and are still awaiting delivery, due to supply chain issues; and
WHEREAS, Contract Monitoring Division established a 10% Local Business Enterprise (LBE) subcontracting participation requirement for this C ontract, and the C ontractor committed to 41.07% LBE subcontracting participation with its bid submittal; and WHEREAS, On October 30, 2008, the San Francisco Planning Commission certified the Final Program Environmental Impact Report (Program EIR) (Case Number 2005.0159E) for the Water System Improvement Program; and
WHEREAS, On August 7, 2014, the San Francisco Planning Commission certified the Final Environmental Impact Report (F inal EIR) for the Regional Groundwater Storage and Recovery Project (Case Number 2008.1396E); and
WHEREAS, Funds are available from Project No. CUW30103 - Regional Groundwater Storage and Recovery; now, therefore, be it
RESOLVED, This Commission finds that since the Program EIR and Final EIR were finalized, there have been no substantial project changes and no substantial changes in project circumstances that would require major revisions to the Final EIR due to the involvement of new significant environmental effects or an increase in the severity of previously identified significant impacts, and there is no new information of substa ntial importance that would change the conclusions set forth in the Final EIR; and be it
FURTHER RESOLVED, That this Commission hereby approves an increase of 290 calendar days to the existing construction duration contingency for Contract No. WD -2878A, Regional Groundwater Storage and Recovery Phase 2A , for a total construction duration contingency of up to 350 calendar days and a total Contract duration of up to 958 consecutive calendar days, with no change to the Contract amount.
I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of January 23, 2024.