WW-628 Southeast Plant New Headworks Facility
Project
Jignesh Desai, P.E., Senior Project Manager
Presentation to: SFPUC
3/26/2024
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 2 • Remove Grit to protect
downstream processes
• Improve odor, noise, and
visual quality
• Provide reliability and
operational flexibility
• Improve seismic reliability
• Meet the permitted capacity
of 250 million gallons per day
(MGD)
SEP New Headworks Facility Project
Objectives
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.
SEP New Headworks Facility Project
Scope of Work
3 N
Main Headworks
Evans Avenue
Rankin St.
Quint Street
Bruce
Flynn
PS
Bruce
Flynn
PS
Odor Control
Scope III
Scope I
Scope II.A
Lift
Station
Scope I – Site Preparation (Complete)
Scope II.A – BFS Upgrades (Complete)
Scope III – Main Headworks (Construction)
Odor Control Facility (Construction)
Lift Station Rehabilitation (Construction)
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.
Scope III (Headworks) Progress & Status:
• The new Headworks building is complete. Contractor is in the process of installing roofing, windows, elevators, doors, and other architectural finishes. • Majority of the project equipment (grit pumps, odor control, grit removal, screenings removal, hoppers, process piping, ventilation ducts/fans, etc.) has been delivered and installed. • The electrical installations (conduit, wiring, panels, enclosures) and wire testing are on-going. • Work on the art wall is complete.
• SFPUC has awarded sixty-six of the expected seventy bid packages. • Limited Start-up/testing with generators on-going
SEP New Headworks Facility Project
Current Status
4 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. • Increase to Contract Amount
• An additional ~$7.2M is needed to primarily account for increased General Conditions & Requirements
• Increase to Cost and Duration Contingency
• An additional ~$7.8M and 257 days to the contract cost and duration contingencies is needed to account for the remaining (4) bid packages, as well as, pending change orders.
• Reasons for Amendment
• Unforeseen conditions and required structural strengthening of the 43 years old existing influent channels,
• Shutdown constraints due to process needs and unprecedented wet weather in recent years • Supply chain challenges with odor control systems and major electrical and process equipment
• Impacts related to electrical service delays
• The proposed amendment is aligned with the Commission adopted SFPUC 10-Year Capital Plan
SEP New Headworks Facility Project
Proposed Amendment No. 6
5 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean. 6 Questions
DEPARTMENT
Infrastructure Division
AGENDA NO. 10
MEETING DATE
March 26, 2024
AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
Construction Modification: Regular Calendar
Contract Manager: Jignesh Desai
Approve Amendment No. 6 and Approve Increases in Construction Cost and Duration Contingencies for Contract No. WW-628 Southeast Water Pollution Control Plant New Headworks Facility
Summary of Proposed
Commission Action:
Approve Amendment No. 6 to Contract No. WW-628 Southeast Water Pollution Control Plant New Headworks Facility with Sundt-Walsh Joint Venture (Construction Manager/General Contractor or CM/GC) , increasing the contract amount by $7,158,234 for a total contract amount not to exceed $555,982,050; and approve increasing the contract cost contingency by $7,841,766, and increasing the contract duration contingency by 257 calendar days, resulting in a contract cost limit of $570,380,175 and a revised contract duration limit of 3,304 consecutive calendar days (approximately nine years and one month) due to unforeseen conditions associated with structural strengthening required for existing influent channel, additional shutdown constraints, supply chain challenges with odor control systems and major electrical and process equipment, as well as impacts related to electrical service delays.
Background: The San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise Headworks facility is one of the most odorous treatment processes in the wastewater stream . It contains critical solids remo val equipment, such as fine screens, grit removal, and odor control systems.
The existing fine screening and grit removal processes are inefficient and significantly impact the performance of downstream processes at Southeast Water Pollution Control Plant (SEP). Upgrading these systems with a new Headworks facility will improve the downstream treatment processes and protect the existing and new equipment from damaging debris such as rags, sand, and abrasive grit.
On May 24, 2016 , by Resolution No. 16-0099 , this Commission awarded Contract No. WW- 628 Southeast Water Pollution Control Plant New Headworks Facility . The original contract amount was $244,562,224, and the original contract duration was 2,658 consecutive calendar days.
On February 28, 2017, by Resolution No. 17-0043, this Commission adopted the CEQA Findings, including the Final Mitigated Negative Contract: WW-628 Southeast Water Pollution Control Plant New Headworks Facility Commission Meeting Date: March 26, 2024
Declaration (FMND) , and the Mitigation Monitoring and Reporting Program, and approved the Headworks Project and authorized the General Manager to proceed with construction of the project under Contract No. WW-628.
In November of 2017, c onstruction began, and the CM/GC has accomplished the following milestones:
• Scope I – Site Preparation (100% complete)
• Scope II – Bruce Flynn Pu mp Station Improvements (100% complete)
• Scope III – Main Headworks (81% complete)
o The new Headworks building is complete. CM/GC is
in the process of installing roofing, windows, elevators, doors, and other architectural finishes.
o Majority of the project equipment (grit pumps, odor
control, grit removal, screenings removal, hoppers,
process piping, HVAC, etc.) has been delivered and
installed.
o The electrical installations (conduit, wiring, panels, enclosures) and wire testing are on-going.
o Work on the art wall and campus fence is underway.
o SFPUC has approved 66 of the expected 70 bid
packages.
Description of Scope of
Work:
The contract work location is in the City and County of San Francisco.
The work under this contract consists of the following:
Detail of Work under this Contract:
• Scope I – Site Preparation
o Construction of a new work- around pipe to bypass the old wet weather Headworks facility.
o Demolition of wet weather Headworks (SEP 011).
• Scope II – Bruce Flynn Pump Station Improvements
o New bar screens, new lift pumps and upgrades to the
electrical system.
o New odor control units to minimize impacts to surrounding communities.
• Scope III – Main Headworks
o New Influent Junction Structure and Influent Monitoring. o New screening and grit removal facilities.
o Construction of the new Odor Control Facility.
o Rehabilitation of the existing Southeast Lift Station. o Installation of art wall and aesthetic improvements.
Contract: WW-628 Southeast Water Pollution Control Plant New Headworks Facility Commission Meeting Date: March 26, 2024
Amendments to the
Contract:
Contract No. WW -628, as a CM/GC contract, uses an integrated project delivery method that allows the contractor to review design documents and provide construction cost estimates and constructability reviews at various milestones. This project delivery method also allows the design of certain scopes of work to be performed concurrently with construction. The CM/GC bids out the subcontractor trade packages as the project progresses. As such, the project team has implemented the following design developments related to constructability and value engineering, as well as changes to market conditions, escalation, and field condition changes:
Amendment No. 1: On February 28, 2017, by Resolution No. 17-0043, this Commission approved Amendment No. 1, increasing the contract amount by $11,600,000 for a total contract amount of $256,162,224 , with no change to the contract duration.
Amendment N o. 2: On December 11, 2018, by Resolution No. 18- 0208, this Commission approved Amendment No. 2, increasing the contract amount by $36,017,960 for a total contract amount of $292,180,184, with no change to contract duration , and increasing the contract cost contingency by $18,630,619 for a contract cost limit of up to $335,267,025 and increasing the contract duration contingency by 75 calendar days, for a total contract duration limit of up to 2,936 consecutive calendar days.
Amendment No. 3: On December 22, 2020, by Resolution 20-0249, this Commission approved Amendment No. 3, increasing the contract amount by $106,321,923, for a total contract amount of $398,502,107, and increasing the contract duration by 111 consecutive calendar days, for a total contract duration limit of up to 2769 consecutive calendar days.
Amendment N o. 4: On March 9, 2021, by Resolution 21- 0041, this Commission approved Amendment No. 4, increasing the contract amount by $91,749,642, for a total c ontract amount of $490,251,749 , with no change to the contract duration.
Amendment N o. 5: On October 24, 2022, by Resolution 22-0184, this Commission approved Amendment No. 5, increasing the contract amount by $58,572,067, for a total contract amount of $548,823,816 and reducing the contract cost contingency by $40,530,482, for a total contract cost limit up to $555,380,175, with no change to the contract duration.
Proposed Amendment No. 6: Staff recommends the Commission authorize an increase to the contract amount of $7,158,234, for a total contract amount not to exceed $555,982,050 due to unforeseen conditions associated with required structural strengthening of the existing influent channel, additional shutdown constraints, supply chain challenges with odor control s ystems and major electrical and process equipment.
Requested Contingency Changes : Staff requests Commission Contract: WW-628 Southeast Water Pollution Control Plant New Headworks Facility Commission Meeting Date: March 26, 2024
authorization to increase the contract cost contingency by $7,841,766 , and an increas e to the contract duration contingency by 257 calendar days, for a total contract cost limit up to $570,380,175 and a total contract duration limit of up to 3,304 consecutive calendar days to address impacts related to electrical service delays and remaining work to complete the project.
Funding, Budget &
Costs:
Funding: Project No. 10015807, SEP New Headworks (Grit) Removal and within the following projects:
• Project No. CWWSIPSE07 – SEP Facility-wide Distributed Control System Upgrades
• Project No. CWWSIPSE08 – SEP Seismic Reliability and
Condition Assessment Improvements
• Project No. CWWSIPSE10 – SEP Power Feed and Primary
Switchgear Upgrades
Original Contract Amount: $244,562,224
Approved Amendment Nos. 1-5 Amount: 304,261,592
Proposed Amendment No. 6 Amount: $7,158,234
Total Proposed Contract Amount: $555,982,050
Original Cost Contingency: $28,456,222 (including CM/GC Contingency)
Approved Modifications to Cost Contingency:
Amendment 2 - $18,630,619
Scope Approved
Contract Amount
Proposed
Amendment No. 6
Revised Contract
Amount
Pre-Construction $4,879,866 $585,287 $5,465,153
Scope I - Si te Preparati on
Includes SE08 & SE10 Scopes of
work (Mod No. 1)
$48,238,055 $48,238,055
Scope II - BFS / Includes Scope D
& SE07 Scope of Work (Mod No.
1)
$19,073,194 $19,073,194
Scope III - Main Headworks $414,284,646 $576,602 $414,861,248 Scope I - General Conditions $7,493,237 $7,493,237
Scope II - General Conditions $2,569,801 $2,569,801
Scope III - General Conditions $42,715,052 $5,000,000 $47,715,052 General Requi rements $3,203,654 $1,996,346 $5,200,000 Bonds $4,366,311 $4,366,311
Reimbursable Expenses $2,000,000 -$1,000,000 $1,000,000 WW-628 Contract Amount $548,823,816 $7,158,235 $555,982,050 Contract Change Contingency* $2,556,359 $10,341,766 $12,898,125 CM/GC Contingency** $4,000,000 -$2,500,000 $1,500,000
Total Contingencies $6,556,359 $7,841,766 $14,398,125
Total WW-628 Contract Limit $555,380,175 $15,000,000 $570,380,175 WW-628 Proposed Contract Amendment No. 6
* Contract Change Contingency addresses changes to construction scope and schedule ** CM/GC Contingency addresses work coordination and/or scope gaps between bid packages and trade subcontractors
Contract: WW-628 Southeast Water Pollution Control Plant New Headworks Facility Commission Meeting Date: March 26, 2024
Amendment 5 – ($40,530,482)
Total Modifications to Cost Contingency– ($21,899,863)
Requested Increase to Cost Contingency: $7,841,766
Total Cost Contingency: $14,398,125
Total Not-to-exceed Contract Amount: $570,380,175
Schedule: Notice-To-Proceed Dates:
• Pre-Construction: August 15, 2016
• Construction: November 15, 2017
Original Contract Duration: 2,658 consecutive calendar days Approved Increase to Contract Duration: 111 calendar days Total Contract Duration: 2,769 consecutive calendar days
Original Duration Contingency: 203 consecutive calendar days Approved Additional Duration Contingency: 75 calendar days Recommended Increase to Duration Contingency: 257 calendar days
Total Duration Contingency: 535 consecutive calendar days
Total Revised Contract Duration Limit: 3,304 consecutive calendar days
Environmental Review: On December 19, 2016 , t he Planning Department approved a Final Mitigated Negative Declaration for Project No. CWWSIPSE02, Southeast Plant Headworks Replacement Project (Case Number 2015- 006224ENV).
On February 28, 2017, by Resolution No. 17- 0043, this Commission approved the SEP New Headworks Facility Project and adopted findings (California Environmental Quality Act (CEQA) Findings) and a Mitigation Monitoring and Reporting Program required by the CEQA.
On March 7, 2019, the Planning Department issued an A ddendum to the Final Mitigated Negative Declaration to upgrade the Bruce Flynn Pump Station, construct a new Southeast Lift Station, and other associated changes. On October 8, 2019, by Resolution No. 19- 0195, this Commission reviewed and considered the Addendum to the Final Mitigated Negative Declaration and a revised Mitigation Monitoring and Reporting Program to approve the modification.
The work under the proposed Amendment No. 6 is within the scope of the project authorized under the Final Mitigated Negative Declaration and Addendum.
The Final Mitigated Negative Declaration , Addendum, CEQA Findings, Resolution Numbers 17- 0043 and 19-0195, and the revised Mitigation Monitoring and Reporting Program can be found here:
Contract: WW-628 Southeast Water Pollution Control Plant New Headworks Facility Commission Meeting Date: March 26, 2024
https://sfpuc.sharefile.com/public/share/web-
sb96f1d1444a74fc2bd6f710664c1bf5e
Compliance with
Chapter 14B: Local
Business Enterprise
Utilization and Non-
Discrimination in
Contracting Ordinance:
The Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting requirement of 15% for this contract.
The contractor committed to 15% LBE subcontractor participation in its bid submittal.
Contract: WW-628 Southeast Water Pollution Control Plant New Headworks Facility Commission Meeting Date: March 26, 2024
Southeast Water Pollution Control Plant
PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO.
WHEREAS, The San Francisco Public Utilities Commission (SFPUC) has undertaken improvements to the existing antiquated Wastewater Enterprise Headworks facility inefficient fine screening and grit removal processes , which is significantly impacting the performance of downstream processes at the Southeast Plant; and
WHEREAS, On May 24, 2016, by Resolution No. 16- 0099, this Commission awarded Contract No. WW-628 Southeast Water Pollution Control Plant New Headworks Facility to Sundt- Walsh Joint Venture (Construction Manager/General Contractor or CM/GC); and WHEREAS, The original contract amount was for $244,562,224 and the original contract duration was 2,658 consecutive calendar days; and
WHEREAS, August 15, 2016, was t he pre -construction Notice -To-Proceed date, and November 15, 2017, was the construction Notice-To-Proceed date; and WHEREAS, On February 28, 2017, by Resolution No. 17- 0043, this Commission approved Amendment No. 1 increasing to the contract amount by $11,600,000 for a total contract amount of $256,162,224, with no change to the contract duration; and WHEREAS, On December 11, 2018, by Resolution No. 18- 0208, this Commission approved Amendment No. 2 increasing the contract amount by $36,017,960 for a total contract amount of $292,180,184, with no change to contract duration, and increasing the contract cost contingency by $18,630,619, for a total contract cost limit of up to $335,267,025 and increasing the contract duration contingency by 75 calendar days, for a total contract duration limit of up to 2,936 consecutive calendar days; and
WHEREAS, On December 22, 2020, by Resolution 20- 0249, this Commission approved Amendment No. 3 increasing the contract amount by $106,321,923, for a total contract amount of $398,502,107, and increasing the contract duration by 111 consecutive calendar days, for a total contract duration of 2,769 consecutive calendar days; and WHEREAS, On March 9, 2021, by Resolution 21- 0041, this Commission approved Amendment No. 4 increasing the contract amount by $91,749,642, for a total contract amount of $490,251,749, with no change to the contract duration; and WHEREAS, On October 24, 2022, by Resolution 22- 0184, this Commission approved Amendment No. 5 increasing the contract amount by $58,572,067, for a total contract amount of $548,823,816, with no change to the contract duration; and WHEREAS, Staff recommends approval of proposed Amendment No. 6 to Contract No.
WW-628 Southeast Water Pollution Control Plant New Headworks Facility, increasing the contract amount by $7,158,234, for a total contract amount not to exceed $555,982,050, due to unforeseen conditions associated with required structural strengthening of the existing influent channel, additional shutdown constraints, supply chain challenges with odor control systems and major electrical and process equipment; and
WHEREAS, Staff also recommends increasing the contract cost contingency by $7,841,766, and increasing the contract duration contingency by 257 calendar days, resulting in a total contract cost limit of up to $570,380,175 and a revised contract duration limit of up to 3,304 consecutive calendar days to address impacts related to electrical service delays and remaining work to complete the Project; and
WHEREAS, Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting participation of 15% for this contract, and the contractor committed 15% LBE participation with its bid submittal; and
WHEREAS, On December 19, 2016, the Planning Department approved a Final Mitigated Negative Declaration for Project No. CWWSIPSE02, Southeast Plant Headworks Replacement Project (Case Number 2015-006224ENV); and
WHEREAS, On February 28, 2017, by Resolution No. 17- 0043, this Commission approved the SEP New Headworks Facility Project and adopted findings (California Environmental Quality Act (CEQA ) Findings) and a Mitigation Monitoring and Reporting Program required by the CEQA; and
WHEREAS, On March 7, 2019, the Planning Department issued an Addendum to the Final Mitigated Negative Declaration to upgrade the Bruce Flynn Pump Station, construct a new Southeast Lift Station, and other associated changes; and
WHEREAS, On October 8, 2019, by Resolution No. 19-0195, this Commission reviewed and considered the Addendum and a revised Mitigation Monitoring and Reporting Program to approve the modification; and
WHEREAS, The work under the proposed Amendment No. 6 is within the scope of the project authorized under the Final Mitigated Negative Declaration and Addendum; and
WHEREAS, On March 7, 2019, the Planning Department issued an Addendum to the Final Mitigated Negative Declaration for the Modified Project and determined that no supplemental environmental review was needed beyond the Addendum; and
WHEREAS, On October 8, 2019 , by Resolution No. 19- 0195, this Commission adopted the Addendum; and
WHEREAS, The San Francisco Planning Department is the custodian of records, located in the files for Case Number 2015-006224ENV, at 49 South Van Ness Avenue, Suite 1400, San Francisco, California; and
WHEREAS, The Project files, including the Final Mitigated Negative Declaration , Addendum, SFPUC Resolution Numbers 17- 0043 and 19-0195, CEQA Findings, and the Mitigation and Monitori ng Reporting Program have been made available for review by this Commission and the public, and those files are part of the record before this Commission; and
WHEREAS, This Commission has reviewed and considered the information contained in the Final Mitigated Negative Declaration , Addendum, the findings contained in SFPUC Resolution Numbers 17- 0043 and 19-0195, the Mitigation and Monitoring Reporting Program , and all written and oral information provided by the Planning Department, the public, relevant public agencies, SFPUC and other experts and the administrative files for the Project; now , therefore be it
RESOLVED, This Commission has reviewed and considered the Final Mitigated Negative Declaration and the Addendum and the record as a whole, finds that the Final Mitigated Negative Declaration is adequate for its use as the decision –making body for the Project and incorporates the CEQA findings contai ned in Resolution Numbers 17- 0043 and 19-0195 by this reference thereto as though set forth in this Resolution; and be it FURTHER RESOLVED, This Commission further finds that since the Final Mitigated Negative Declaration and Addendum were finalized, there have been no substantial Project changes and no substantial changes in Project circumstances that would require major revisions to them due to the involvement of new significant environmental effects or an increase in the severity of previously identif ied significant impacts, and there is no new information of substantial importance that would change the conclusions set forth in them; and be it FURTHER RESOLVED, That this Commission hereby a pproves Amendment No. 6 for Contract No. WW- 628 Southeast Wat er Pollution Control Plant New Headworks Facility , with Sundt-Walsh Joint Venture (Construction Manager/General Contractor or CM/GC), increasing the contract amount by $7,158,234, for a total contract amount not to exceed $555,982,050, with no change in contract duration; and be it
FURTHER RESOLVED, That this Commission hereby approves an increasing to the contract cost contingency by $7,841,766, for a total contract cost contingency of $14,398,125 and a total contract cost limit of up to $570,380,175; and, be it FURTHER RESOLVED, That this Commission hereby a pproves an increase to the contract duration contingency of 257 calendar days for a total contract duration contingency of 535 calendar days and a total contract duration limit of up to 3,304 consecutive calendar days.