DEPARTMENT

Infrastructure

AGENDA NO.

7e

MEETING DATE

May 14, 2024

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Construction Modification: Consent Calendar
Contract Manager: Mary Tienken

Approve Increase to Duration and Cost Contingencies for Contract No. WW-736, Castro and Mission Districts Sewer Improvements

Summary of Proposed
Commission Action:

Approve an increase in the amount of $2,500,000 to the cost contingency and an increase of 100 calendar days to the duration contingency for Contract No. WW- 736, Castro and Mission Districts Sewer Improvements, with Precision Engineering, Inc ., increasing the c ontract amount limit up to $10,499,552 and increasing the contract duration limit up to 567 consecutive calendar days (approximately one year and seven months), to rehabilitate an additional 1,440 linear feet of large diameter high- risk sewers on 18th Street between Eureka and Danvers Streets . Implementation of all the 18 th Street sewer rehabilitation under a single construction contract will reduce disruption to the Castro District residents and businesses. This actio n constitutes the Approval Action for the 18th Street sewer rehabilitation work for the purposes of the Cali fornia Environmental Quality Act ( CEQA), pursuant to San Francisco Administrative Code section 31.04(h). The Planning Department has determined that the Project is exempt from the CEQA. The Commission will rely on that determination to make its decision on this action.

Background: The purpose of this project is to rehabilitate existing sewers that are over 100 years old and identified to be at a high- risk of failure based on data in the San Francisco Public Utilities Commission (SFPUC) c ondition assessment management program.

On May 9, 2023, by Resolution 23- 0097, the Commission awarded Contract No. WW-736, Castro and Mission Districts Sewer Improvements to Precision Engineering, Inc. The original contract amount was $7,272,320 and original contract duration was 425 consecutive calendar days.

After the Commission awarded WW -736, Castro and Mission Districts Sewer Improvements, City staff completed condition assessment s of additional brick sewers on 18 th Street between Eureka Street and Danvers Street, directly west of the current Contract limit, observed missing mortar and fallen bricks in televised videos of these sewers , and confirmed the need for structural rehabilitation. In the interest of time and to minimize additional disruption to the community with a future construction contract, staff recommends performing this work under Contract No. WW-736.

Contract: WW-736, Castro and Mission Districts Sewer Improvements Commission Meeting Date: May 14, 2024

Page 2 ends

Scope of Contract: The additional contract work location is on 18th Street between Eureka Street and Danvers Street in San Francisco and directly west of WW -736 contract work at the intersection of 18 th and Eureka Streets. The original contract work included the rehabilitation of 3,900 linear of feet of brick sewer at six locations in the Mission and Castro Districts.

The additional contract work proposed includes:
• Rehabilitation of approximately 1,440 linear feet of existing sewers using cured-in-place-liners or spray mortaring construction methods; • Rehabilitation or installation of seven sewer manholes; • Replacement and rehabilitation of laterals and associated appurtenances;
• Restoration of roadway and other restoration- in-kind work associated with the sewer work; and
• Traffic control.

Modifications to the
Contract:

Recommended Increase to Contract Cost and Duration Contingency:

Staff recommends Commission approval of a $2,500,000 increase to the existing contract cost contingency and an increase of 100 calendar days to the existing contract duration contingency to rehabilitate an additional 1,440 linear feet of brick sewers on 18th Street between Eureka Street and Danvers Street, directly west of the current Contract limits, for a total contract amount limit of $10,499,552 and a total contract duration limit of 567 consecutive calendar days (approximately one year and seven months). Implementation of all of the 18 th Street sewer rehabilitation under a single construction contract will reduce disruption to the Castro district residents and businesses.

Funding and Costs: Funding: Project No. 10034718, Castro and Mission Districts Sewer Improvements
Original Contract Amount: $7,272,320
Original 10% Cost Contingency Amount: $727,232
Requested Additional Cost Contingency: $2,500,000
Total Revised Contract Cost Limit: $10,499,552

Schedule: Notice-to-Proceed Date: August 28, 2023
Original Contract Duration: 425 consecutive calendar days Original 10% Duration Contingency: 42 calendar days
Requested Additional Duration Contingency: 100 calendar days Total Revised Contract Duration Limit: 567 consecutive calendar days

Environmental
Review:

On June 29, 2022 , the San Francisco Planning Department determined the Castro and Mission Districts Sewer Improvements project to be statutorily exempt from environmental review under t he CEQA section 21080.21 and CEQA Guidelines section 15282(k) (Case No. 2022- 005580ENV), because the proposed pipeline replacement will be in the public right of way and does not exceed one mile in length.

On April 8, 2024, the San Francisco Planning Department determined the Contract: WW-736, Castro and Mission Districts Sewer Improvements Commission Meeting Date: May 14, 2024

Page 3 ends

18th Street sewer rehabilitation work to be statutorily exempt from environmental review under the CEQA s ection 21080.21 and CEQA Guidelines section 15282(k) (Case No. 2024- 003063ENV) because the proposed pipeline replacement will be in the public right -of-way and does not exceed one mile in length.

The 18th Street sewer rehabilitation work was added to this contract for contracting convenience, and has independent utility from the Castro and Mission Districts Sewer Improvements project under the CEQA.

The exemption determination s can be found here :
https://sfpuc.sharefile.com/public/share/web-
s8e45a48742304941bdf0398ee3a83bb6

This action constitutes the Approval Action for the 18th Street sewer rehabilitation work for the purposes of the CEQA, pursuant to San Francisco Administrative Code section 31.04(h).

Local Business
Enterprise
Participation and Non-
Discrimination in
Contracting:

Set: The Contract Monitoring Division (CMD) established a 6% Local Business Enterprise (LBE) subcontracting requirement for this contract.

Submitted: The contractor committed to 6.18% LBE participation with its bid submittal.

LOCATION MAP

18th Street, Additional
Sewer Rehabilitation

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) c ollection system assessment management program identified sewers that are over 100 years old and pose a high- risk of failure; and
WHEREAS, Staff confirmed the need for rehabilitation of existing brick sewers based on missing mortar and bricks observed from televised videos. The program has identified sewers in need of rehabilitation lo cated on 18th Street, 17th Street, Guerrero Street, Folsom Street and South Van Ness Avenue; and
WHEREAS, On May 9, 2023, by Resolution No. 23- 0097, this Commission awarded Contract No. WW -736, Castro and Mission Districts Sewer Improvements to Precision Engineering, Inc.; and
WHEREAS, The contract Notice-To-Proceed date was August 28, 2023; and WHEREAS, The original contact amount was $7,272,320 and the original contract duration was 425 consecutive calendar days to rehabilitate 3,900 linear feet of brick sewer; and WHEREAS, Staff re commends approval of an increase of $2,500,000 to the cost contingency and an increase of 100 calendar days to the duration contingency to rehabilitate the brick sewers on 18
th Street between Eureka and Danvers Street, directly west of the original area specified in the contract scope, , for a total contract amount limit of $ 10,499,552 and a total contract duration limit of 567 consecutive calendar days; and WHEREAS, CMD established a Local Business Enterprise ( LBE) subcontracting participation of 6% for this contract , and the contractor committed to 6.18% LBE participation with its bid submittal; and
WHEREAS, On June 29, 2022, the San Francisco Planning Department determined the Castro and Mission Districts Sewer Improvements project to be statutorily exempt from environmental review under the CEQA section 21080.21 and CEQA Gui delines section 15282(k) (Case No. 2022-005580ENV), because the proposed pipeline replacement will be in the public right of way and does not exceed one mile in length; and

WHEREAS, On April 8, 2024, the San Francisco Planning Department determined the 18th Street sewer rehabilitation work to be statutorily exempt from environmental review under the CEQA s ection 21080.21 and CEQA Guidelines s ection 15282(k) (Case No. 2024- 003063ENV) because the proposed pipeline replacement will be in the public right -of-way and does not exceed one mile in length; and

WHEREAS, The 18th Street sewer rehabilitation work was added to this contract for contracting convenience, and has independent utility from the Castro and Mission Districts Sewer Improvements project under the CEQA; and
WHEREAS, Funds are available from Project No. 10034718; now, therefore be it

5 RESOLVED, That this Commission hereby a pproves an increase of $2,500,000 to the cost contingency and an increase of 100 calendar days to the duration contingency for Contract No. WW-736, Castro and Mission Districts Sewer Improvements , for a new contract amount limit of up to $ 10,499,552 and a new contract duration limit of up to 567 consecutive calendar days.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of May 14, 2024.

Secretary, Public Utilities Commission