NEW CDD CAMPUS
AT 2000 MARIN STREET:

PROJECT APPROVAL
Shelby Campbell, Senior Project Manager
August 13, 2024

APPROVE PROJECT
2 APPROVE City
Distribution Division
(CDD) Campus at 2000
Project;
and
ADOPT Final Mitigated
Negative Declaration
(FMND and Mitigation
Monitoring and
Reporting Program
(MMRP).

NEW CDD CAMPUS
• Potable, recycled, groundwater,a uxiliary
• 1250 m iles of water mains
• 15 m iles of pipe replaced per year
• 12 re servoirs
• 9 pump st ations
• 176,000 w ater meters
SFWD HEADQUARTERS AT 2000 MARIN STREET | 2024.05.20
WHO is CDD?
San Francisco Water Department
Existing site mixes pedestrian and vehicular paths across the sprawlingcampus.

Large vehicles do not fit inside Auto Shop due to door and ceiling heights. Repairs are madeoutside.

Fabrication Shop workers cut pipe at exterior of shop. Hazardous debris is notcontained.

Old B-Blasters in most shops in confined space with inadaquate ventilation. No containment of debris.

Overcrowded work areas are non-compliant for accessibility and areunsafe.

SFWD HEADQUARTERS AT 2000 MARIN STREET| 2024.05.20
WHY - NEW FACILITIES?
VICINITY | NEIGHBORHOOD OF MUNICIPAL OPERATIONS YARDS ALONG CESAR CHAVEZ SFWD HEADQUARTERS AT 2000 MARIN STREET | 2024.05.20CAMPUSLOCATION WHERE? 2000 Marin Street
6 2000 Marin Street
WHAT = NEW CAMPUS
7 8
Key Design Objectives = Community-
building + Sustainability + Safety
• Pedestrian-Safe Pathway
• Central Green Hub
• Stormwater Garden
• Solar Energy
• Recycling Existing Building

DESIGN:

FINAL PHASE - CONSTRUCTION

DOCUMENTS UNDERWAY
TRADE PROCUREMENT:

COMMENCED JULY 2024
CONSTRUCTION START:

SEPTEMBER 2024
CONSTRUCTION FINISH:

DECEMBER 2028
TOTAL PROJECT BUDGET:
$393.4 Million
When = Project Milestones

ARCHITECT
Mark Cavagnero Associates

SHOP ARCHITECT
William Duff Architects

STRUCTURAL ENGINEER
Miyamoto International

CIVIL ENGINEER
BKF Engineers

MECHANICAL / ELECTRICAL / INDUSTRIAL
Stantec

PLUMBING ENGINEER
SJ Engineers

GARAGE DESIGNER
Watry Design

TELECOM / SECURITY
HRA Consulting Engineers

ACOUSTICS / AV
Salter

SUSTAINABILITY
Stok

STORMWATER MANAGEMENT
Lotus Water

LIGHTING DESIGN
Banks Landl Lighting Design

ENVELOPE AND WATERPROOFING
RDH Building Science

SIGNAGE / WAYFINDING
Clearstory

LANDSCAPE
PW Bureau of Landscape
Architecture

VERTICAL TRANSPORTATION
Syska Hennessey Group

SPECIFICATIONS
Emily Borland Specifications

JOINT TRENCH UTILITIES
Urban Design Consulting
Engineers

CODE / LIFE SAFETY
Reax Engineering

TRASH MANAGEMENT
American Trash Management

GEOTECHNICAL ENGINEER
Engeo

GENERAL CONTRACTOR
Clark Construction
TAKES A VILLAGE:

Design/Construction Team
Preliminary Mitigated
Negative Declaration
Issued June 19, 2024
for 30-Day Public
Review Period. No
Comments.

Final Mitigated
Negative Declaration
Issued July 31, 2024
TEAM: SFPUC Env Mgmt
Group (EMG), Planning
Dept, Panorama
Environmental

ENVIRONMENTAL REVIEW

12 GROUND BREAKING = OCTOBER

THE FUTURE

DEPARTMENT Infrastructure

AGENDA NO. 9

MEETING DATE

August 13, 2024

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Calendar: Regular Calendar
Project Manager: Shelby Campbell

Adopt CEQA Final Mitigated Negative Declaration, Approve City Distribution Division Campus at 2000 Marin Project, and Authorize Staff to Proceed with Actions Necessary to Implement the Project.

Summary of
Proposed
Commission Action:

Adopt the Final Mitigated Negative Declaration and a Mitigation Monitoring and Reporting Program pursuant to the California Environmental Quality Act (CEQA); approve Project No. 10037249, City Distribution Division ( CDD) Campus at 2000 Marin, to replace facilities at 1990 Newcomb Avenue; and authorize staff to proceed w ith actions necessary to implement the Project, including issuance of the Notice -to-Proceed for
the Construction Phase
pursuant to the Construction Manager/General Contractor (CM/GC) Contract No. WD-2879R. This action constitutes the Approval Action for the Project for the purposes of CEQA, pursuant to San Francisco Administrative Code section 31.04(h).

Background: San Francisco Public Utilities Commission (SFPUC) Water Enterprise City Distribution Division (CDD) oversees water distribution within the City and County of San Francisco. CDD is responsible for the City’s water system infrastructure, operating and maintaining its reservoirs, pump stations , and approximately 1,250 miles of water pipes ; managing the City’s meter program; and maintaining CDD facilities, equipment, and fleet of vehicles.

The current CDD campus, located at 1990 Newcomb Avenue, has served as CDD’s main facility for almost six decades.

Due to significant growth in service demands and challenges with maintaining operations at a facility that has exceeded its useful life, the SFPUC needs to design and
construct new CDD headquarters facilities to alleviate
overcrowding, address building code and safety issues, eliminate inefficiencies, and accommodate CDD’s current and future operational needs.

On June 28, 2022, by Resolution No. 22-0125, this Commissi on awarded Contract No. WD-2879R, City Distribution Division Campus at 2000 Marin, to Clark Construction Group with an original contract amount of $260,450,682 and an original contract duration of 2,464 consecutive calendar days and authorized the contract or to proceed only with pre -construction services, in the contract amount of $1,250,000 with a contract duration of 913 consecutive calendar days.

Agenda Title: WD-2879R, CDD Campus at 2000 Marin
Commission Meeting Date: August 13, 2024

Page 2 ends

Contract No. WD-2879R, City Distribution Division Campus at 2000 Marin is for construction management (CM) and general contractor (GC) services in constructing this proposed new CDD headquarters. The contractor awarded this contract is referred to as the CM/GC.

Scope of Contract: Under Contract No. WD-2879R, the SFPUC is constructing new facilities at 2000 Marin Street in San Francisco to relocate the CDD headquarters from its current location at 1990 Newcomb Avenue to alleviate overcrowding, address building code and safety issues, eliminate inefficiencies, and accommodate CDD’s current and future operational needs.

The contract work includes:
• Demolition of existing building and parking lot;
• Site work, including grading, utilities, paving; and
• Construction of five new structures, including administrative offices, shops, warehouse, and parking, for a total of approximately 370,000 gross square feet.

Funding and Costs: Funding Source: Water Capital Improvement Program, Project No. 10037249, New CDD Campus at 2000 Marin.

Original Contract Amount: $260,450,682
• Pre-construction: $1,250,000
• Construction: $259,200,682

Schedule: Original Contract Duration: 2,464 consecutive calendar days

Pre-Construction Phase:

Notice-to-Proceed Date: March 1, 2023
Duration: 913 consecutive calendar days
Completion: August 25, 2025

Construction Phase:

Estimated Start of Construction: September 2, 2024
Duration: 1,551 consecutive calendar days ( 1,276 days to Substantial Completion and 275 additional days to Final Completion).

Estimated Completion: December 1, 2028

Environmental
Review:

On June 19, 2024, the Planning Department published a Preliminary Mitigated Negative Declaration for the City Water Distribution Division Campus Project at 2000 Marin Street Project (Case Number 2022-000702ENV ), which was available for public comment until July 19, 2024. No public comments or appeals on the Preliminary Mitigated Negative Declaration were received.

On July 29, 2024, the Planning Department approved the Final Mitigated Negative Declaration for the Project.

The Final Mitigated Negative Declaration and the Mitigation Monitoring and Reporting Program can be found here: link.

Agenda Title: WD-2879R, CDD Campus at 2000 Marin
Commission Meeting Date: August 13, 2024

Page 3 ends

This action constitutes the Approval Action for the Project for the purposes of the CEQA, pursuant to San Francisco Administrative Code section 31.04(h).

Agenda Title: WD-2879R, CDD Campus at 2000 Marin
Commission Meeting Date: August 13, 2024

Page 4 ends

WD-2879R, City Distribution Division Campus at 2000 Marin

PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO.

WH
EREAS, The San Francisco Public Utilities Commission (SFPUC) is constructing new facilities at 2000 Marin Street to relocate the Water Enterprise City Distribution Division (CDD) from its current location at 1990 Newcomb Avenue to alleviate overcrowding, address building code and safety issues, eliminate inefficiencies, and accommodate CDD’s current and future operational needs; and
WHEREAS, On June 28, 2022, by Resolution No. 22-0125, the Commission awarded Contract No. WD-2879R, CDD Campus at 2000 Marin to Clark Construction Group as a Construction Manager/General Contractor (CM/GC) in the amount of $260,450,682 and with a duration of 2,464 consecutive calendar days; and
WHEREAS, On June 28, 2022, by Resolution No. 22- 0125, the Commission authorized commencement of pre-construction services for the Project in the amount of $1,250,000 with a duration of 913 consecutive calendar days; and
WHEREAS, On June 28, 2022, by Resolution No. 22-0125, the Commission requested staff, upon completion of environmental review under the California Environmental Quality Act (CEQA), to return to seek approval of the Project and request that this Commission authorizes the remaining contract funding in the amount up to $259,200,682 and authorize s the staff to proceed with the construction phase.; and
WHEREAS, March 1, 2023, was the Notice-to-Proceed date for Pre-Construction; and WHEREAS, On June 19, 2024, the Planning Department published a Preliminary Mitigated Negative Declaration for the City Water Distribution Division Campus Project at 2000 Marin Street Project (Case Number 2022-000702ENV), which was available for public comment until July 19, 2024, and no public comments or appeals on the Preliminary Mitiga ted Negative Declaration were received; and
WHEREAS, On July 29, 2024, the Planning Department reviewed and considered the Final Mitigated Negative Declaration and found that the contents are adequate, accurate and objective, reflected the independent analysis and judgment of the Planning Department, and the procedures through which it was prepared, publicized, and reviewed, complied with California Environmental Quality Act (CEQA), 14 California Code of Regulations section 15000 et seq. (the CEQA Guidelines), and Chapter 31 of the San Francisco Administrative Code; and WHEREAS, The Planning Department is the custodian of records, located in Case Number 2022-000702ENV, at 49 South Van Ness Avenue, Suite 1400, San Francisco, California; and WHEREAS, Staff ha s made the Final Mitigated Negative Declaration and Mitigation Monitoring and Reporting Program available to the public and this Commission for this Commission’s review, consideration, and action; and
WHEREAS, Subject to Commission approval of the Project, staff recommends authorizing the Project to proceed to the Construction Phase, consistent with this Commission Resolution No. 22-0125, and for Clark Construction Group to provide construction services in the amount up to $259,200,682, consistent with the terms and conditions of Contract No. WD-2879R; and WHEREAS, Funds are available from Project No. 10037249, City Distribution Division Campus at 2000 Marin; now, therefore, be it
RESOLVED, That the SFPUC has reviewed and considered the Final Mitigated Negative Declaration and the record as a whole, and finds the Final Mitigated Negative Declaration is adequate for its use as the decision making body for the Project, and there is no substantial evidence that the Project will have a significant effect on the environment with the adoption of the mitigation measures contained in the Mitigation Monitoring and Reporting Program and that the Final Mitigated Negative Declaration reflects the City’s independent judgment and analysis, and hereby adopts the Final Mitigated Negative Declaration ; and be it FURTHER RESOLVED, That the SFPUC hereby adopts the Mitigation Monitoring and Reporting Program incorporated herein as part of this Resolution by this reference thereto and commits to all required mitigation measures identified in the Final Mitigated Negative Declaration and contained in the Mitigation Monitoring and Reporting Program; and be it FURTHER RESOLVED, That this Commission hereby approves the CDD Campus at 2000 Marin project, and authorizes SFPUC staff to proceed with actions necessary to implement the Project; and be it
FURTHER RESOLVED, That this Commission hereby authorizes SFPUC staff to proceed to the Construction Phase under Contract No. WD-2879R for Clark Construction Group to deliver a new CDD Campus at 2000 Marin in the amount up to $259,200,682 and a duration of 1,551 consecutive calendar days, in accordance with the terms and conditions of such contract, subject to appropriation and certification of funds.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of August 13, 2024.

Director of Commission Affairs,
San Francisco Public Utilities Commission

← All documents from this meeting