OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.

Contract Administration Bureau
525 Golden Gate Avenue, 8th Floor
San Francisco, CA 94102
T 415.551.4603
F 415.554.3225
TTY 415.554.3488

TO: Commissioner Tim Paulson, President
Commissioner Anthony Rivera, Vice President
Commissioner Newsha K. Ajami
Commissioner Kate H. Stacy

THRU: Dennis J. Herrera, General Manager

FROM: Ivy Fine, Deputy Assistant General Manager,
Project Administration Bureau, Infrastructure Division

Stephen Robinson, Assistant General Manager, Infrastructure Division

DATE: September 16, 2024

SUBJECT: Contract Advertisement Report and Competitive Selection Process Communications Policy Restricted Communications Period Report: September 24, 2024

CONSTRUCTION:

Contract Number and Title:

PUC-0007(I), 525 Golden Gate Ave. Fire Alarm and Life Safety Testing and Inspection Services 2025 to 2029
Contract Estimate:
$950,000
Program:
525 Golden Gate
Estimated Date of Advertisement:

September 2024
Description of Contract Work:

Perform inspection and testing for the fire protection, fire alarm, and life safety systems for the 525 Golden Gate Avenue, San Francisco, CA 94102 high rise building. In addition to the extent that any fire protection, fire alarm, life safety system, or any portion thereof, does meet regulatory requirements, the contractor will provide maintenance and repair services on an as-needed basis, including the replacement of component equipment (e.g., fire panel) as necessary.

Project Manager:

Chris Anderson

Kyndra Cox on
behalf of Ivy Fine

PROFESSIONAL SERVICES:

Contract Number and Title:

PRO.0322, SFPUC Interconnection Process Enhancements, Request for Qualifications (RFQ)
Contract Estimate:

N/A*
Program:

Power Enterprise

Estimated Date of Advertisement:

September 2024

Description of Contract Work:

The City and County of San Francisco (City), acting by and through its Public Utilities Commission (SFPUC) seeks proposals for projects in California Independent System Operator (CAISO) Queue Cluster 15 (QC15) to allocate CleanPowerSF (the City’s Community Choice Aggregation (CCA) program) and Hetch Hetchy Power (the City’s municipal electric utility) Commercial Interest points, in accordance with the CAISO’s Interconnection Process Enhancements initiative.

Project Manager:

Kiara Hermann
*There is no dollar value associated with this RFQ. The purpose is to prequalify projects in accordance California Public Utilities Code Section 399.12 and California Public Resources Code 25741, in preparation for a subsequent Request for Offers (RFO).

Competitive Selection Process Communications Policy
Restricted Communications Period Report
The following competitive solicitations are published and are within the Restricted Communications Period under the Public Utilities Commission Competitive Selection Process
Communications Policy
1:

Program Contract No. Title Publication
Date
525 Golden
Gate PUC-0007(i)
525 Golden Gate Ave. Fire Alarm
and Life Safety Testing and
Inspection Services 2025 to 2029
September 24,
2024
N/A PRO.0322 As-Needed Security Consulting and
Design Services
September 24,
2024
Sewer System
Improvement
Program
WW-719B
Folsom Area Stormwater
Improvements – Alameda Street
Wet Weather Conveyance Tunnel
September 10,
2024
N/A JOC-109
General Engineering (A-License)
Construction within San Joaquin,
Stanislaus, and Tuolumne Counties,
Hetch Hetchy
September 10,
2024
Infrastructure PRO.0282 As-Needed Security Consulting and Design Services
September 10,
2024
Business
Services PRO.312 Power Rate Study September 10,
2024
SFPUC
Wastewater
Enterprise,
Renewal and
Replacement
(R&R) Program
WW-741 Various Locations Spot Main Sewer
Replacement No. 1 August 13, 2024
Hetchy Capital
Improvement
Program
HH-1016
San Joaquin Pipeline Valve and Safe
Entry Improvements Phases 2B &
2C
August 13, 2024

1 On February 9, 2021, by Resolution No. 21-0022, the San Francisco Public Utilities Commission adopted a Competitive Selection Process Communications Policy. The policy establishes a Restricted Communications Period. The period starts immediately upon the publication of a Request for Qualifications, Request for Proposals, Request for Bids, Advertisement for Bids, or any other type of competitive solicitation for a contract or lease.

The period ends when the Commission awards the contract or lease or terminates the competitive process.

Program Contract No. Title Publication
Date
SFPUC
Wastewater
Enterprise,
Renewal and
Replacement
(R&R) Program
WW-727 WW-727 Various Locations Sewer
Replacement No. 16 August 13, 2024
SFPUC
Wastewater
Enterprise,
Renewal and
Replacement
(R&R) Program
WW-760 As-Needed Spot Sewer
Replacement No. 46 August 13, 2024
Power
Enterprise PRO.0234 CleanPowerSF In-City Solar August 13, 2024 Wastewater
Enterprise
Capital
Improvements
Program
DB-136 Wastewater Facilities Security
Enhancements August 13, 2024
SFPUC
Wastewater
Enterprise,
Renewal and
Replacement
(R&R) Program
WW-729 Various Locations Sewer
Replacement No. 17 June 25, 2024
Water
Enterprise
Capital
Improvements
Program
WD-2909 Sunol Valley Water Treatment Plant
Short Term Improvements June 25, 2024
CleanPowerSF,
the City and
County of San
Francisco's
Community
Choice
Aggregation
Program
PRO-0297
SFPUC Customer Administrative
Services Community Choice
Aggregation
June 25, 2024
Wastewater
Enterprise,
Sewer System
Improvement
Program

WW-744 Seacliff 2 Pump Station and Force
Main Upgrade June 25, 2024

Program Contract No. Title Publication
Date
SFPUC Energy
Efficiency and
Electrification
Program

PW-012 Master As-Needed HVAC and
Mechanical Services June 25, 2024
TBD DB-138 Biogas Utilization Project June 25, 2024
Engineering
Management PRO.0309 As-Needed Relocation Coordination
Services June 25, 2024
Engineering
Management PRO.0308 As-Needed Engineering Design
Services June 25, 2024
Power
Enterprise PRO.0280 2024 CleanPowerSF Renewable
Energy Supplies June 25, 2024
Water
Enterprise
Capital
Improvements
Program
WD-2909 Sunol Valley Water Treatment Plant
Short Term Improvements June 25, 2024
Water Capital
Improvement
Program
WD-2926(I)
Harry Tracy Water Treatment Plant
East Chemical Storage Structure
Seismic Retrofit
June 11, 2024
Water and
Wastewater
Retail
PRO.0300(G) Demonstration Garden
Programming and Maintenance June 11, 2024
Local Water
Main
Replacement
Program
WD-2875
8-Inch and 12-Inch Ductile Iron
Water Main and Sewer Replacement
on Grand View Avenue from Clipper
Street to Romain Street, and
Various Area
June 11, 2024
Local Water
Main
Replacement
Program
WD-2876
16-Inch Ductile Iron Water Main
Installation and 8-Inch Ductile Iron
Water Main Replacement on San
Bruno Avenue from Campbell
Avenue to Paul Street and on
Blanken Avenue from Bayshore
Boulevard to Executive Park
Boulevard
June 11, 2024
Water
Enterprise PRO.0289 River Ecosystem Science Services May 28, 2024 Power
Enterprise PRO.0234 CleanPowerSF In-City Solar May 28, 2024

Program Contract No. Title Publication
Date
Water
Enterprise PRO.0302 Meter Maintenance Diagnostics
Services May 14, 2024
Power
Enterprise PRO.0230
Bay Corridor Transmission
Distribution Phase 4 and Water
Improvements Project –
Construction Management Staff
Augmentation Services and
Construction Management Services
May 14, 2024
Water
Enterprise PRO.0205 Water Capital Plan Delivery -
Program Management Consultant April 23, 2024
San Francisco
Public Utilities
Commission
(SFPUC)
Wastewater
Enterprise,
Renewal and
Replacement
Program
WW-740 Various Large Diameter Sewer
Inspection No. 2 April 23, 2024
Capital
Improvement
Program
PRO.0176
As-Needed Corrosion Control
Engineering and Inspection
Services
April 23, 2024
Wastewater
Capital
Improvements
Program
WW-757
Laguna, Howard, and Mission
Creeks Combined Sewer Discharge
Improvements
April 09, 2024
Business
Services PRO.0265(R) Discount Program Post-Enrollment
Verification Services (Re-Bid) March 26, 2024
Water
Enterprise
Capital
Improvement
Program
PRO.0239
New City Distribution Division
Campus at 2000 Marin Construction
Management Staff Augmentation
Services
March 26, 2024
Sewer System
Improvement
Program
WW-755 Sunnydale Pump Station Safety
Improvements March 12, 2024