DEPARTMENT
Infrastructure Division
AGENDA NO.
8b
MEETING DATE
October 22, 2024
AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
Calendar: Consent Calendar
Project Manager: Jon Cantu
Approve Increase to Construction Cost Contingency for Contract No. WD-2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street
Summary of
Proposed
Commission Action:
Approve an increase of $117,517 to the cost contingency for Contract No. WD- 2896, 12- Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street , with M. Squared Construction, Inc., to procure additional ductile iron pipe necessary to, realign the pipe after encountering an unforeseen underground storage tank, and for additional traffic controls and support, for a revised cost limit of $1,733,375, with no change to the contract duration.
Background: The water main replacement work under this contract is part of the San Francisco Public Utilities Commission (SFPUC) Water Enterprise Local Conveyance/Distribution System Program. The program includes the replacement of pipes that have either been damaged or are at the end of their useful service life to ensure reliable water delivery within the City.
This contract will replace the existing 12- inch diameter cast iron water pipes, currently located within the Buchanan Street Mall, with 12-inch diameter ductile iron pipes on Webster Street from Grove to Eddy Streets and on Eddy Street from Webster to Buchanan Streets. The City installed the existing cast iron pipes in 1936; due to their material, age of 87 years, and history of repeated main breaks in the neighborhood, they need to be replaced. Replacement of these pipelines at a new location allows for the same operational redundancy in the system while also eliminating potential conflicts with the City’s upcoming Buchanan Street Mall Renovation Project.
On January 9, 2024, by Resolution No. 24- 0009, this Commission awarded Contract No. WD -2896, 12- Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street (Project) to M. Squared Construction, Inc. The original contract a mount was $1,468,962 and the original contract duration was 286 consecutive calendar days.
Scope of Contract: The contract work location is in the Fillmore district within the City and County of San Francisco.
The contract work includes installation of:
Agenda Title: WD-2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street Commission Meeting Date: October 22, 2024
• 200 feet of 4-inch to 8-inch diameter ductile iron water conveyance pipe;
• 2,200 feet of 12-inch diameter ductile iron water conveyance pipe; and • Curb ramps, and pavement restoration.
Modification(s) to
the Contract
Modification No. 1: Staff issued Modification No. 1 increasing the contract by $146,499, within the original cost contingency, for a total contract amount of $1,615,461, and with no change to the contract duration , for the contractor to furnish the ductile iron pipe material.
Recommended Increase to Cost Contingency : Staff recommends the Commission approve an increase of $117,517 to the existing cost contingency, for a revised cost limit of $1,733,375,
and with no change to the contract
duration, to procure additional ductile iron pipe necessary to realign the pipe after encountering an unforeseen underground storage tank at the intersection of Webster and Fulton Streets, and for additional traffic controls and support needed to implement single-lane reversible traffic on a Muni bus route along Eddy Street from Webster to Buchanan Streets . Where realigned, the pipe remains within the project limits.
Funding and Costs: Funding Source: Project Number 10039033, WD-2896 Webster Street Original Contract Amount: $1,468,962
Original 10% Cost Contingency: $146,896
Recommended Additional Cost Contingency : $117,517
Total Revised Contract Cost Limit: $1,733,375
Schedule: Notice-to-Proceed Date: May 28, 2024
Original Contract Duration: 286 consecutive calendar days Original Contract Duration Contingency: 28 consecutive calendar days Recommended Additional Duration Contingency: 0 days
Total Revised Contract Duration Limit: 314 consecutive calendar days
Environmental
Review:
On May 23, 2023 , the San Francisco Planning Department determined the Project to be statutorily exempt from environmental review under the California Environmental Quality Act Guidelines section 15282(k) (Case Number 2023- 004517ENV) because the pipeline will be in the public right of way and does not exceed one mile in length.
The exemption determination can be found here:
https://sfpuc.sharefile.com/d-s81ab7ab73a9b495db7a4193d4e45bf5d
Local Business
Enterprise
Utilization and
Non-Discrimination
in Contracting:
The Contract Monitoring Division (CMD) established a 12% Local Business Enterprise (LBE) subcontracting requirement for this c ontract. The contractor committed to 11.81% LBE subcontractor participation with its bid submittal.
Despite the 11.81% LBE commitment, CMD still requires the contractor to meet the 12% LBE subcontracting requirement.
Agenda Title: WD-2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street Commission Meeting Date: October 22, 2024
WD-2896, LOCATION MAP
PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO.
WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Water Enterprise Local Conveyance/Distribution Program provides for the replacement of water pipelines that have either been damaged or are at the end of their useful service life to ensure reliable water delivery within the City; and
WHEREAS, SFPUC staff has identified cast iron water main pipes that were installed in 1936 and now require replacement due to their material age of 87 years, and history of repeated main breaks in the Fillmore district; and
WHEREAS, On January 9, 2024, by Resolution No. 24- 0009, the SFPUC awarded Contract No. WD-2896, 12- Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street (Project) to M. Squared Construction, Inc.; and
WHEREAS, The original c ontract amount was $1,468,962 and the original c ontract duration was 286 consecutive calendar days; and
WHEREAS, The contract Notice-to-Proceed date was May 28, 2024; and
WHEREAS, Modification No. 1 increased the contract amount by $146,499, within the original cost contingency, increasing the contract amount to $1,615,461 for the contractor- furnished ductile iron pipe material; and
WHEREAS, Staff recommends approval of an i ncrease of $117,517 to the cost contingency, for a revised cost limit of up to $1,733,375, and with no change to the contract duration, to procure additional ductile iron pipe necessary to realign the pipe after encountering an unforeseen underground storage tank, and for additional traffic controls and support; and
WHEREAS, The Contract Monitoring Division (CMD) established a 12% Local Business Enterprise (LBE) subcontracting requirement for this contract, and M. Squared Construction, Inc., committed to 11.81% LBE participation in its bid submittal, but CMD will require the contractor to meet the 12% LBE subcontracting requirement; and
WHEREAS, On May 23, 2023, the San Francisco Planning Department determined the Project to be statutorily exempt from environmental review under the California Environmental Quality Act Guidelines section 15282(k) (Case Number 2023-004517ENV) because the pipeline will be in the public right of way and does not exceed one mile in length; and
WHEREAS, Funds are available from Project No. 10039033, WD-2896 Webster Street ; now, therefore, be it
RESOLVED, That this Commission hereby approves an increase of $117,517 to the existing cost contingency for Contract No. WD-2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street, with M. Squared Construction, Inc., for a total cost contingency limit of $264,413, for a total allowable cost limit of up to $1,733,375, and a duration of 286 consecutive calendar days.
I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of October 22, 2024.
Director of Commission Affairs