Cities Index.
Approve an increase of $385,000 to the cost contingency and 329 calendar days to the duration

CleanPowerSF Sfpuc Commission
October 22, 2024

Document
Approve an increase of $385,000 to the cost contingency and 329 calendar days to the duration
Meeting
October 22, 2024
Body
CleanPowerSF Sfpuc Commission
Pages
2
Original file
346 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

DEPARTMENT

Infrastructure

AGENDA NO.

14 MEETING DATE

October 22, 2024

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Calendar: Regular Calendar
Project Manager: Carman Luk

Approve Increase to Cost and Duration Contingency for Contract No . WW-739, As - Needed Large Diameter Sewer Cleaning

Summary of
Proposed
Commission
Action:

Approve an increase of $385,000 to the cost contingency and 329 calendar days to the duration contingency for Contract No. WW-739, As -Needed Large Diameter Sewer Cleaning , with Pipe and Plant Solutions, Inc ., to perform additional large diameter (greater than 36-inches in diameter) sewer cleaning, for a revised cost limit of up to$1,433,439, and a revised duration limit of up to730 consecutive calendar days.

Background: The scope of work for this contract is performing as-needed cleaning of existing large diameter sewers, which are sewers that are greater than 36 -inches in diameter or hydraulically equivalent sizes. The cleaning of sewers is an integral part of the San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise’s comprehensive asset management program and helps maintain hydraulic capacity in the wastewater collection and conveyance system.

Wastewater Enterprise’s Collection System management has identified critical needs for cleaning services of existing sewers to supplement Wastewater Enterprise’s Collection System staff’s ongoing cleaning and inspection work.

Work under this Contract will assist with the ongoing maintenance for Wastewater Enterprise and ensure the sewer s ystem continues to operate efficiently. Wastewater Enterprise Collection System staff will determine the locations and extent of large -diameter sewer cleaning work on an as -needed basis throughout the duration of this Contract.

On September 20, 2023, by Resolution No. 23-0161, this Commission awarded Contract No. WW- 739, As-Needed Large Diameter Sewer Cleaning , to Pipe and Plant Solutions, Inc., in the amount of $953,127 and with a contract duration of 365 consecutive calendar days.

Scope of
Contract:

The contract work is at various locations * within the City and County of San Francisco, and at locations to be determined by Wastewater Enterprise.

The contract work consists of:
• Mobilization and demobilization at each location;
• Traffic Control;
• High-velocity, hydraulically-propelled cleaning;
Agenda Title: WW-739, As-Needed Large Diameter Sewer Cleaning Commission Meeting Date: October 22, 2024

Page 2 ends

• Debris removal: including handling, testing, transportation and disposal of collected debris to approximate disposal site; and • Camera inspection of cleaned sewers.

Modifications to
the Contract:

Recommended Increase to Contract Contingency: Staff recommends the Commission approve an increase of $385,000 to the existing cost contingency and an increase of 329 calendar days to the existing duration contingency, to provide additional time and funding for the contractor to perform additional large diameter sewer cleaning, for a revised total cost limit of up to$1,433,439, and a revised total duration limit of up to730 consecutive calendar days.

In 2024, Wastewater Enterprise staff identified an urgent need to use this contract for cleaning at the Oceanside wastewater treatment facility, which Staff managing this contract had not anticipated. The recommended increase in cost and duration contingency replen ishes the contract capacity to permit the contractor to perform planned as -needed large diameter sewer cleaning in the next dry weather season.

Funding & Costs: Funding: Wastewater Enterprise, Renewal and Replacement Program, Project No. 10038749, Sewer Cleaning – Large Diameter
Original Contract Amount: $953,127
Original 10% Cost Contingency: $95,312
Recommended Additional Cost Contingency: $385,000
Total Revised Contract Cost Limit: $1,433,439

Schedule: Notice-to-Proceed Date: January 8, 2024
Original Contract Duration: 365 consecutive calendar days Original 10% Duration Contingency: 36 calendar days
Recommended Additional Duration Contingency: 329 calendar days Total Revised Contract Duration Limit: 730 consecutive calendar days

Environmental
Review:

This action does not constitute a “project” under the California Environmental Quality Act Guidelines section 15378 (a) because there would be no physical change in the environment.

Local Business
Enterprise
Utilization and
Non-
Discrimination in
Contracting:

The Contract Monitoring Division established a 10% Local Business Enterprise (LBE) subcontracting requirement for this contract. The contractor committed to 13.61% LBE participation in its bid submittal.

*Due to the nature of this As-Needed contract, there is no accompanying Location Map.

PUBLIC UTILITIES COMMISSION

City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise Collection System management has identified critical needs for cleaning of existing large -diameter sewers to supplement Wastewater Enterprise Collection System staff’s ongoing cleaning of the sewer system under SFPUC Wastewater Enterprise’s Collection System Asset Management Program, to maintain design hydraulic capacity, and to assist with the ongoing maintenance; and

WHEREAS, On September 20, 2023, by R esolution No. 23- 0161, the Commission awarded Contract No. WW-739, As-Needed Large Diameter Sewer Cleaning , to Pipe and Plant Solutions, Inc.; and

WHEREAS, The original contract amount was for $953,127 and the original contract duration was 365 consecutive calendar days; and

WHEREAS, The contract Notice-to-Proceed date was January 8, 2024; and

WHEREAS, Staff recommends an increase of $385,000 to the cost contingency, and an increase of 329 calendar days to the duration contingency , to provide additional time and funding to perform additional large diameter sewer cleaning; and

WHEREAS, The Contract Monitoring Division established a 10% Local Business Enterprise (LBE) subcontracting requirement for this contract , and the contractor committed to 13.61% LBE participation in its bid submittal; and

WHEREAS, This action does not constitute a “project” under the California Environmental Quality Act Guidelines section 15378(a) because there would be no physical change in the environment; and

WHEREAS, Funds are available from Project No. 10038749, Sewer Cleaning – Large Diameter; now, therefore, be it

RESOLVED, That this Commission hereby approves an increase of $385,000 to the existing cost contingency and increase of 329 consecutive calendar days to the existing duration contingency, for Contract No. WW-739, As-Needed Large Diameter Sewer Cleaning, with Pipe and Plant Solutions, Inc., for a total cost contingency of $480,312 and a total duration contingency of 365 calendar days, and for a revised total amount limit of up to $1,433,439, and a total duration limit of up to 730 consecutive calendar days.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of October 22, 2024.

Director of Commission Affairs
San Francisco Public Utilities Commission

← All documents from this meeting