1 WD-2868R
SF Local Water As-Needed Paving
(FY21-24)
November 12, 2024
Steve Ritchie AGM, Water Enterprise
Services of the San Francisco Public Utilities Commission 2 Background: Contract Information
• WD-2868 As-Needed Paving Contract
• Award Date: May 11, 2021
• Contractor: A. Ruiz Construction
• Contract Amount: $13.9 Million
• Contract Duration: 1095 days
• Contract Scope: Pavement & Sidewalk Restoration
3 Water Main Break Event

4 Paving Contract Restoration Work

5 Water Service Line Repair Work &
Restoration
301 Eugenia 2332 Vicente
2331 Vicente St Service Line Replacement
6 Contract Expenditures
Leaks and Main
Breaks
$5 Million (31%)
Service Line
Replacements
$3.9 Million (24%)
New Service
Line Installations
$5 Million (31%)
Total Expenditures: $16.3 Million as of 7-2024
Other Repair Work
$2.4 Million (14%)
7 Unforeseen Paving Restoration Work
• WD-2868 exceeded existing capacity due to
variability of unforeseen water main break work
• Examples (Paving Costs Only):
• Oct 2022: 29th Ave and Fulton St $117,000
• Jun 2023: Duboce St and Castro St $265,000
• Sep 2023: Fillmore St and Green St $1.8 Million
Contract Change Order History
Previous Change Orders
• Total Modified Contract amount: $19.2 Million
• Total Modified Contract Duration: 1,283 days
8 CO # Increase Approved By Commission
1 $1.1 Million N/A: under 10% Contract Capacity
2 $0.25 Million
Extended to 10-13-24 N/A: under 10% Contract Capacity
3 $3,963,881
Extended to 12-31-24 Approved June 25, 2024
9 Proposed CO#4 and New Paving
Contract
• New: Change Order #4
• Increase capacity to $20.8 Million
• Increase duration to 1,825 calendar days
• New: As-Needed Paving Contract WD-2927
• Estimated Bid & Award Date: March 2025
• Estimated NTP Date: December 2025
• Estimated Cost: $17.1 Million

DEPARTMENT Water Enterprise
AGENDA NO.

9 MEETING DATE November 12, 2024

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Calendar: Regular Calendar
Project Manager: Bill Teahan

Approve Increase to Construction Cost and Duration Contingencies for Contract No.

WD-2868R, San Francisco Local Water As-Needed Paving (FY 21-24)

Summary of
Proposed
Commission Action:

Approve increases of $1,578,919 to the cost contingency and 542 days to the duration contingency for Contract No. WD -2868R, San Francisco Local Water As-Needed Paving (FY 21-24), with A. Ruiz Construction Company & Associates, Inc., for a revised cost limit of $20,785,500 and a revised duration of 1,825 consecutive calendar days , due to an ongoing need for as -needed paving services until SFPUC issues a replacement (new) contract.

Background: The work performed through this contract is necessary to restore roadways and sidewalks after installation of water infrastructure, repair of main breaks, and replacement of meter boxes.

Due to delays in procuring a new as -needed paving contract to replace this contract, Staff recommends an extension of the duration of this existing contract and an increase in contract amount to provide capacity for critical street repair services following unanticipated main breaks and leaks and to support new water service installations and meter maintenance. Staff anticipates that SFPUC will be able to obtain a new as-needed paving contract by January 2026.

Scope of Contract: The contract work locations are located primarily within the City and County of San Francisco, including Y erba Buena Island, Treasure Island and occasionally in San Francisco Public Utilities Commission ( SFPUC) easements or properties on the Peninsula and in the East Bay.

The contract work consists of as-needed street and pavement restoration on short notice at locations to be determined within the City and County of San Francisco, and occasionally on easements or properties on the Peninsula or East Bay, including as-needed pavement restoration for excavations in the public right-of way and replacement of existing pavement adjacent to excavations performed under DPW Order No. 18005. Excavations in the public right-of-way include those associated with water service installation, meter and meter box installation/adjustment, curb ramp construction, pipe leaks, and main breaks.

Modifications to the
Contract:

Original Contract: On May 11, 2021 , by Resolution No. 21-0079, this Commission awarded Contract No. WD -2868R, San Francisco Local Water Agenda Title: No. WD-2868R, San Francisco Local Water As-Needed Paving (FY 21-24) Commission Meeting Date: November 12, 2024

Page 2 ends

As-Needed Paving (FY 21-24), to A. Ruiz Construction Co. & Assoc., Inc., in the amount of $13,857,000 and with a contract duration of 1,095 consecutive calendar days.

Modification Nos. 1- 2: Staff issued Modification Nos. 1- 2 increasing the contract amount by $1,385,700 and increasing the contract duration by 109 calendar days, within the original 10% contract cost and duration contingencies, for work exceeding the original projected estimated quantities for a total revised contract amount of $15,242,700 and a revised contract duration of 1,204 consecutive calendar days.

Modification No. 3: On June 25, 2024, by Resolution No. 24- 0145, this Commission approved an increase of $3,963,881 to the existing cost contingency and an increase of 79 calendar days to duration contingency, for a total revised cost limit of $19,206,581 and a total revised duration limit of 1,283 calendar days, and staff issued Modification No. 3 increasing the contract consistent with the contingency limits.

Recommended Increase to Cost and Duration Contingency: Staff recommends the Commission approve an increase of $1,578,919 to the existing cost contingency and an increase of 542 calendar days to the existing duration contingency, for a revised contract cost limit of $20,785,500 and a revised duration contingency of 1,825 calendar days.

Funding and Costs: Funding Source: Water Enterprise Local Conveyance/Distribution System Program-funded Project No. 10035726, San Francisco Local Water As - needed Paving (FY 21-24)

Original Contract Amount: $13,857,000
Original 10% Cost Contingency: $1,385,700
Approved Increase in Cost Contingency: $3,963,881
Recommended Additional Cost Contingency: $1,578,919
Total Revised Contract Cost Limit: $20,785,500

Schedule: Notice-to-Proceed Date: June 28, 2021
Original Contract Duration: 1,095 consecutive calendar days Original 10% Duration Contingency: 109 calendar days
Approved Increase to Duration Contingency: 79 days
Recommended Additional Duration Contingency: 542 calendar days Total Revised Contract Duration Limit: 1,825 consecutive calendar days

Local Business
Enterprise U and
Non-Discrimination
in Contracting:

The Contract Monitoring Division established a 5% Local Business Enterprise (LBE) subcontracting requirement for this contract. The contractor ’s bid committed to 15.86% LBE participation and this amount remains unchanged.

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, On May 11, 2021, by Resolution No. 21- 0079, this Commission awarded Contract No. WD-2868R, San Francisco Local Water As -Needed Paving (FY 21- 24) to A. Ruiz Construction Company & Associates, Inc.; and

WHEREAS, The original contract amount was for $13,857,000 and the original contract duration was 1,095 consecutive calendar days with a Notice-to-Proceed date of June 22, 2021; and

WHEREAS, Staff issued Modification Nos. 1 and 2, increasing the contract amount by $1,385,700 and increasing the contract duration by 109 calendar days, within the original 10% contract cost and duration contingencies, for a total revised contract amount of $15,242,700 and a revised contract duration of 1,204 consecutive calendar days; and

WHEREAS, On June 25, 2024, by Resolution No. 24-0145, this Commission approved an increase of $3,963,881 to the existing cost contingency and an increase of 79 calendar days to duration contingency, for a total revised cost limit of $19,206,581 and a total revised duration limit of 1,283 calendar days; and

WHEREAS; The contract is essential to repairing streets and sidewalks following main breaks, leaks and ongoing maintenance work; and

WHEREAS, Staff recommends an increase of $1,578,919 to the contract cost contingency and an increase of 542 calendar days to the contract duration contingency to allow the as-needed paving work to continue for the San Francisco Water Department until the SFPUC procures a new as-needed paving contract; and

WHEREAS, Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting participation of 5% for this contract, and the contractor’s bid committed to 15.86% LBE participation, and this remains unchanged; and

WHEREAS, Funds are available from Project No. 10035726, San Francisco Local Water As-needed Paving (FY 21-24); now, therefore, be it

RESOLVED, That this Commission hereby approves an increase of $1,578,919 to the existing contract cost contingency and an increase of 542 calendar days to the existing contract duration contingency, for Contract No. WD-2868R, San Francisco Local Water As-Needed Paving (FY 21-24), with A. Ruiz Construction Company & Associates, Inc., for a total contract cost limit of $20,785,500 and a total contract duration limit of 1,825 calendar days.

I hereby certify that the foregoing resolution was adopted by the Public Utilities Commission at its meeting of November 12, 2024.