DEPARTMENT Infrastructure Division AGENDA NO. 12
MEETING DATE December 10, 2024

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
Calendar: Regular Calendar
Project Manager: Aileen Caylao
Approve Increase to Construction Duration Contingency for Contract No. WW-697, As- Needed Main Sewer Replacement No. 8
Summary of
Proposed
Commission Action:

Approve an increase of 316 calendar days to the duration contingency for Contract No. WW-697, As-Needed Main Sewer Replacement No. 8, with JDB & Sons Construction, Inc., for a revised duration limit of up to 1,811 consecutive calendar days (approximately five years), with no change to contract amount, to allow the contractor additional time to complete contract service orders previously issued.

Background: The San Francisco Public Utilities Commission ( SFPUC) requires contract work to perform as -needed manhole -to-manhole segment main sewer replacements on short notice at locations throughout the City and County of San Francisco, to be determined by SFPUC Wastewater Enterprise staff. The locations of work to be performed and the replacement work itself is determined on an as-needed basis during the contract duration to address any urgently needed main sewer replacement work.

Under San Francisco Administrative Code section 6.64, an as -needed construction contract may be modified up to a five-year total duration and up to 150% of the original contract amount ; no contract service orders may be issued after four years from the date of Controller certification; and no individual contract service order may exceed the Threshold Amount as set by the Controller.

For Contract No. WW -697, the recommended increase to the construction duration contingency would allow for an extension of the contract time to five years, as allowed under Administrative Code section 6.64. The additional time is required to complete work under contract service orders already issued, including time required for coordination with Pacific Gas & Electric in one work location. As four years has passed from the date of Controller certification, no new contract service orders will be issued.

On
August 25, 2020, by Resolution No. 20- 0179, this Commission awarded Contract No. WW-697, As-Needed Main Sewer Replacement No. 8, to JDB & Sons Construction, Inc. The original contract amount was $7,373,000 and the original contract duration was 400 consecutive calendar days.

Agenda Title: WW-697, As-Needed Main Sewer Replacement No. 8 Commission Meeting Date: December 10, 2024

Page 2 ends

On January 11, 2022, by Resolution No. 22-0009, this Commission approved an increase of 325 calendar days to the duration contingency for a total duration limit of up to 765 consecutive calendar days, with no change to the contract amount.

On January 24, 2023, by Resolution No. 23-0020, this Commission approved an increase of 365 calendar days to the duration contingency for a total duration limit of up to 1,130 consecutive calendar days, with no change to the contract amount.

On November 28, 2023, by Resolution No. 23-0209, this Commission approved an increase of 365 calendar days to the duration contingency for a total duration limit of up to 1,495 consecutive calendar days, with no change to the contract amount.

Scope of Contract: The contract work locations are within the City and County of San Francisco.

SPFUC staff issued contract service orders to replace existing sewers with approximately 3,750 linear feet of vitreous clay pipe, ranging in size from 12- inch diameter, 15-inch diameter, 18-inch diameter and 24-inch diameter; and slip line existing sewers with approximately 300 li near feet of high -density polyethylene pipe and cured-in-place lining of approximately 1,250 linear feet of existing 12-inch diameter and 15-inch diameter sewers.

Modifications to the
Contract:

Modification Nos. 1 -3: Staff issued Modification Nos. 1 -3, in accordance with Resolution Nos. 22-0009, 23-0020, and 23-0209, increasing the contract duration by 1,095 calendar days, to allow staff to issue contract service orders and provide time for the contractor to perform work, for a total contract duration of 1,495 consecutive calendar days, with no change to contract amount. Modification Nos. 1- 3 exhausted the approved contract duration contingency.

Recommended Increase to Duration Contingency: Staff recommends the Commission approve a new duration contingency of up to 316 calendar days, for a revised duration limit of up to 1,811 consecutive calendar days, with no change to the contract amount, to allow the c ontractor additional time to complete contract service orders previously issued.

Funding and Costs: Funding Source: Wastewater Enterprise, Renewal and Replacement Program, Project No. 10034813, As-Needed Main Sewer Replacement No. 8 Original Contract Amount: $7,373,000
Original 10% Cost Contingency: $737,300
Requested Additional Cost Contingency: $0
Total Contract Cost Limit: $8,110,300

Schedule: Notice-to-Proceed Date: November 30, 2020
Original Contract Duration: 400 consecutive calendar days Agenda Title: WW-697, As-Needed Main Sewer Replacement No. 8 Commission Meeting Date: December 10, 2024

Page 3 ends

Original 10% Duration Contingency: 40 calendar days
Approved Increase to Duration Contingency: 1,055 calendar days Modification Nos. 1-3: Contract duration of 1,495 calendar days Recommended New Duration Contingency: 316 calendar days Total Revised Duration Limit: 1,811 consecutive calendar days

Environmental
Review:

Increasing the duration of this as -needed contract does not constitute a “project” under the California Environmental Quality Act (CEQA) Guidelines Section 15378
because it does not involve any commitment to any specific project that may result in a physical change in the environment. The SFPUC will not issue any task orders for work to be performed under this contract until the proposed work is reviewed and any appropriate environmental review under the CEQA, if required, has been completed.

Local Business
Enterprise
Utilization and Non-
Discrimination in
Contracting:

The Contract Monitoring Division established a 14% Local Business Enterprise (LBE) subcontracting requirement for this contract. The contractor committed to a 21.47% LBE subcontractor participation with its bid submittal, and this amount remains unchanged.

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) must address manhole-to-manhole segment main sewer replacements on an as -needed basis on short notice in locations to be determined throughout the City and County of San Francisco; and

WHEREAS, On August 25, 2020, by Resolution No. 20-0179, the Commission awarded Contract No. WW-697, As-Needed Main Sewer Replacement No. 8 to JDB & Sons Construction, Inc.; and

WHEREAS, The original contract amount was for $7,373,000 and the original contract duration was 400 consecutive calendar days; and

WHEREAS, The contract Notice-to-Proceed date was November 30, 2020; and

WHEREAS, On January 11, 2022, by Resolution No. 22-0009, the Commission approved an increase of 325 calendar days to the existing duration contingency, for a revised total duration limit of up to 765 consecutive calendar days, with no change in contract amount; and

WHEREAS, On January 24, 2023, by Resolution No. 23-0020, the Commission approved an increase of 365 calendar days to the existing duration contingency, for a revised total duration limit of up to 1,130 consecutive calendar days, with no change in contract amount; and

WHEREAS, On November 28, 2023, by Resolution No. 23- 0209, the Commission approved an increase of 365 calendar days to the existing duration contingency, for a revised total duration limit of up to 1,495 consecutive calendar days, with no change in contract amount; and

WHEREAS, Modification Nos. 1 through 3, increased the contract duration by 1,095 consecutive calendar days, with no change to the contract amount, for a total contract duration of 1,495 consecutive calendar days, to allow staff to issue contract service orders and provide time for the Contractor to continue performing work; and

WHEREAS, Staff recommends approval of a 316-calendar day increase to the duration contingency, for a revised duration limit of up to 1,811 consecutive calendar days, to allow the contractor additional time to complete contract service orders previously issued, with no change to the contract amount; and

WHEREAS, Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting participation of 14% for this contract, and the contractor committed 21.47% LBE subcontractor participation with its bid submittal, and this amount remains unchanged; and

WHEREAS, Increasing th e duration of this as -needed contract does not constitute a “project” under the California Environmental Quality Act (CEQA) Guidelines Section 15378 because it does not involve any commitment to any specific project that may result in a physical change in the environment and the SFPUC will not issue any task orders for work to be performed under this contract until the proposed work is reviewed and any appropriate environmental review under the CEQA, if required, has been completed; and

WHEREAS, Funds are available from Project No. 10034813, As-Needed Main Sewer Replacement No. 8; now, therefore, be it

RESOLVED, That this Commission hereby approves a new duration contingency of 316 calendar days for Contract No. WW- 697, As-Needed Main Sewer Replacement No. 8, for a new duration limit of up to 1,811 consecutive calendar days, with no change to the contract amount.

I hereby certify that the foregoing resolution was adopted by the Public Utilities C ommission at its meeting of December 10, 2024.