Approve an increase of $2,000,000 to the cost contingency and an increase of 350 calendar days

CleanPowerSF Sfpuc Commission
February 25, 2025

Document
Approve an increase of $2,000,000 to the cost contingency and an increase of 350 calendar days
Meeting
February 25, 2025
Body
CleanPowerSF Sfpuc Commission
Pages
4
Original file
610 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

DEPARTMENT

Infrastructure Division

AGENDA NO.

13 MEETING DATE

February 25, 2025

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Calendar: Regular Calendar
Project Manager: Carman Luk

Approve Increase to Construction Cost and Duration Contingencies for Contract No.

WW-723R, Channel Force Main Intertie

Summary of Proposed
Commission Action:

Approve an increase of $2,000,000 to the cost contingency and an increase of 350 calendar days to the duration contingency, for Contract No. WW - 723R, Channel Force Main Intertie, with Anvil Builders, Inc., for a revised contract amount limit of $19,375,899 and a revised contract duration limit of 1,131 consecutive calendar days (approximately three years and one month), to address extensive dewatering needed due to
unforeseen site
conditions, and extend dry weather restricted work in to 2025 to support ongoing shoring and dewatering activities.

Background: Project No. 10034718-1, the Channel Force Main Intertie Project (Project) is part of the San Francisco Public Utilities Commission (SFPUC) Sewer System Improvement Program (SSIP) and is located on Cesar Chavez Street, west of the intersection at Indiana Street.

By this Project, the SFPUC is constructing an underground pipeline connection and control -valves between two existing sewer facilities: the Channel Force Main located under Cesar Chavez Street (westbound lanes), and the Islais Creek Transport/Storage box located under Cesar Chavez Street (eastboun d lanes) and within the San Francisco Municipal Transportation Agency ’s Islais Creek Motor Coach Facility. T he new control valves w ill be installed in an underground concrete vault (new underground valve-vault) to allow for access for operation, maintenanc e, and replacement. In addition, to operate the new control valves, this project will also construct new electrical control panels in the sidewalk along Cesar Chavez Street, between Indiana and Pennsylvania Streets. Work also includes modifications to the interior of the Islais Creek Transport/Storage Box near the intersection of Cesar Chavez and Mississippi Streets, as well as replacement of existing air valves along the Channel Force Main at two locations on Indiana Street, near 20
th Street and 25th Street intersections.

When completed, this Project will allow dry weather flows to be divert ed from the existing Channel Force Main to the existing Islais Creek Transport/Storage Box, thereby increasing the operational flexibility and reliability of the sewer system. In addition, the completed Project will allow SFPUC to inspect and rehabilitate approximately 2,000 -linear feet of the Agenda Title: Contract No. WW-723R, Channel Force Main Intertie Commission Meeting Date: February 25, 2025

Page 2 ends

existing Channel Force Main located downstream of this new pipeline connection in the future.

On December 13 , 2022, by Resolution No. 22- 0215, this Commission awarded Contract No. WW -723R, Channel Force Main Intertie , to Anvil Builders, Inc. The original contract amount was $15,796,272 , and the original contract duration was 710 consecutive calendar days.

The SFPUC issued notice -to-proceed (NTP) late in the mid -dry weather period of 2023 due to various contract insurance documents delays, which left only one dry weather window available in 2024 for dry- weather restricted work. Based on actual work completed to date, which included utility relocations and long lead equipment delivery, an additional dry weather season in 2025 is needed to complete the remaining scope of work.

The dewatering rates and set-up of the dewater system are largely uncertain because the groundwater discharge permit is approved only during construction. The rates and set -up depend on the groundwater testing and the design of the shoring system, which must work within the constraints of the existing utilities. The Contractor encountered various unforeseen site conditions which contributed to the increase in dewatering needs. Based on investigations and permit approvals, the dewatering allowance within the contract was vastly underestimated, hence, additional cost contingency increase is needed to support the ongoing dewatering activities for the scope of work. This includes upkeep of tanks, pumps, generators, underground piping for moving water 24/7 for the estimated duration extension, as well as dewatering measures to support the excavation and trench. The cost contingency increase will ensure excavation activities can continue uninterrupted.

Scope of Contract: The contract work locations are on Cesar Chavez Street just west of Indiana Street, and on Indiana Street near 20 th and 25 th street intersections. The contract work consists of:

• Furnish and install one 48-inch and two 66-inch diameter valves, including ancillary piping and mechanical joints;
• Construction of a new subsurface underground valve-vault on piles;
• Installation of above-ground control panels for electrical controls and instrumentations systems;
• Replacement of air release valves;
• Associated traffic controls and street restoration; and • Testing and commission of all major mechanical, electrical, instrumentation and automation systems before turning over to SFPUC for operation.

Agenda Title: Contract No. WW-723R, Channel Force Main Intertie Commission Meeting Date: February 25, 2025

Page 3 ends

Modifications to the
Contract:

Modification No. 1-4: Staff issued Modification Nos. 1-4, increasing the contract amount by $717,031, within the original 10% contingency, for a total contract amount of $16,513,303, with no change to the contract duration, to address multiple special traffic permits and Caltrans encroachment permits and agreement fees, and dewatering measures in support of the shoring system, and ongoing dewatering activities in 2023.

There is $862,596.20 remaining from the original contingency.

Recommended Increase to Cost and Duration Contingencies: Staff recommends the Commission approve an increase of $2,000,000 to the cost contingency to address extensive dewatering needed due to unforeseen site conditions, and an increase of 350 calendar days to the duration contingency to extend dry weather allowed work into 2025 to support ongoing shoring and dewatering activities , for a revised cost limit of $19,375,899, and a revised duration limit of 1,131 consecutive calendar days.

Funding and Costs: Funding Source: Sewer System Improvement Program funded Project No. 10034718-1, Channel Force Main Intertie
Original Contract Amount: $15,796,272
Original 10% Cost Contingency: $1,579,627
Approved Increases to Cost Contingency: $0
Modified Increases to Contract Amount: $717,031
Total Current Contract Amount: $16,513,303
Remaining Cost Contingency: $862,596
Requested Additional Cost Contingency: $2,000,000
Total [Proposed] Revised Cost Limit: $19,375,899

Schedule: Notice-to-Proceed Date: June 26, 2023
Original Contract Duration: 710 consecutive calendar days Original 10% Duration Contingency: 71 calendar days
Approved Increase to Duration Contingency: 0 calendar days Modified Increases to Contract Duration: 0 calendar days Remaining Duration Contingency: 71 calendar days
Requested Additional Duration Contingency: 350 consecutive calendar days
Total [Proposed] Revised Duration Limit: 1,131 c onsecutive calendar days

Local Business
Enterprise Utilization
and Non-
Discrimination in
Contracting :

The Contract Monitoring Division established a 16% Local Business Enterprise (LBE) subcontracting requirement for this contract. The contractor committed to a 16.52% LBE subcontractor participation with its bid submittal, and this remains unchanged.

Agenda Title: Contract No. WW-723R, Channel Force Main Intertie Commission Meeting Date: February 25, 2025

Page 4 ends

Project Vicinity Map

Project Location Map

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise, Sewer System Improvements Program identified the need to construct a pipeline connection between the Channel Force Main and the Islais Creek Transport/Storage Box to increase operational flexibility for dry weather sewage conveyance; and

WHEREAS, On December 13, 2022, by Resolution No. 22- 0215, the Commission awarded Contract No. WW-723R, Channel Force Main Intertie to Anvil Builders, Inc.; and

WHEREAS, The original contract amount was for $15,796,272 and the original contract duration was 710 consecutive calendar days; and

WHEREAS, The contract Notice-to-Proceed date was June 26, 2023; and

WHEREAS, Staff issued M odification Nos. 1- 4, increasing the contract amount by $717,031, within the original 10% contingency, for additional permit and agreement fees and ongoing dewatering activities and in support of shoring system , for a total contract amount of $16,513,303, with no change to the contract duration; and

WHEREAS, Staff recommends an
increase of $2,000,000 to the cost contingency and an
increase of 350 consecutive calendar days to the duration contingency, to address extensive dewatering needed due to unforeseen site conditions, and extend dry weather allowed work into 2025, for a revised cost limit of $ 19,375,899, and a revised duration limit of 1,131 consecutive calendar days; and

WHEREAS, The Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting participation of 16% for this contract, the contractor committed to 16.52% LBE subcontractor participation with its bid submittal, and this remains unchanged; and

WHEREAS, Funds are available from Project No. 10034718- 1, Channel Force Main Intertie; now, therefore, be it

RESOLVED, That this Commission hereby authorizes an increase of $2, 000,000 to the existing cost contingency and an increase of 350 calendar days to the existing duration contingency, for Contract No. WW-723R, Channel Force Main Intertie, for a total remaining cost contingency of $2,862,596 and a total duration contingency of 421 calendar days, for a revised cost limit of $19,375,899 and a revised duration limit of 1,131 consecutive calendar days.

I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of February 25, 2025.

Director of Commission Affairs
San Francisco Public Utilities Commission