Cities Index.
pppgQ Water System Improvement Program Quarterly Report

CleanPowerSF Sfpuc Commission
March 11, 2025

Document
pppgQ Water System Improvement Program Quarterly Report
Meeting
March 11, 2025
Body
CleanPowerSF Sfpuc Commission
Original file
3.4 MB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services in a manner that values environmental and community interests and sustains the resources entrusted to our care.

DATE: January 31, 2025
TO: Commissioner Kate H. Stacy, President
Commissioner Joshua Arce, Vice President
Commissioner Avni Jamdar
Commissioner Steve Leveroni
FROM: Dennis J. Herrera, General Manager
SUBJECT: Water System Improvement Program
Quarterly Report (2nd Quarter / FY 2024-2025)
525 Golden Gate Avenue, 13th Floor
San Francisco, CA 94102
T 415.554.3155
F 415.554.3161
TTY 415.554.3488
Enclosed please find the Water System Improvement Program (WSIP) Quarterly Report for the 2nd Quarter (Q 2) of Fiscal Year (FY) 202 4-2025. The primary intent of the report is to provide the Commission, stakeholders, and the public with a status summary of the Water System Improvement Program based on data for the period of October 1, 2024 to December 31, 2024 . This quarterly report provides a summary update on the Regional WSIP projects. The Local WSIP was completed in June 2020.

Starti
ng this reporting period, the format of the table posted on Appendix B has changed to include all WSIP Regional projects and their phases to provide a more complete program status update.

Attachment

This page is intentionally left blank.

Published: January 31, 2025

QUARTERLY REPORT
Regional Projects
Q2 FY 2024 | 2025
October 2024 — December 2024
Rebuilding Today for a Better Tomorrow

This page is intentionally left blank.

WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 – 12/31/24)

PROGRAM DESCRIPTION
The Water System Improvement Program (WSIP) is a $4.8 billion, multi -year capital program to upgrade the City of San Francisco’s regional and local drinking water systems. The program will deliver improvements that enhance the City’s ability to provide reliable, affordable, high quality drinking water to its 26 wholesale customers and regional retail customers in Alameda, Santa Clara, and San Mateo Counties, and to 800,000 retail customers in San Francisco, in an environmentally sustainable manner. The WSIP is structured to cost -effectively meet water quality requirements, improve seismic and delivery reliability, and achieve water supply goals.

Built in the early to mid- 1900s, the water system has many components nearing the end of their working life, with crucial facilities crossing, or in close proximity to, three major earthquake faults. The San Francisco Public Utilities Commission (SFPUC) initiated the WSIP to repair, replace, and seismically upgrade the system’s deteriorating pipelines, tunnels, dams, reservoirs, pump stations, storage tanks, and treatment facilities.

The program consists of 35 local projects located within San Francisco and 52 regional projects spread over seven different counties from the Sierra foothills to San Francisco. Local projects only benefit San Francisco residents whereas regional projects benefit both City residents and the 26 wholesale agencies that receive water from the SFPUC. The management of regional projects is divided into 6 regions – San Joaquin, Sunol Valley, Bay Division, Peninsula, San Francisco Regional, and Support Projects.

The WSIP is funded through the issuance of revenue bonds. Local Measures A and E, which were approved by San Francisco voters in November 2002, allowed for the financing of improvements to the City’s water system using revenue bonds and/or other forms of revenue financing. Increases in the water rates of retail and wholesale customers are used to pay back the debt service on the bonds.

The program budget and schedule were originally adopted by the San Francisco Public Utilities Commission on March 1, 2003. The program at the time was referred to as the Capital Improvement Program (CIP). The scope of the CIP was changed significantly following the adoption of Level of Service (LOS) goals in early 2005. The program changes were so substantial that the program was renamed the WSIP and a new program budget and schedule were adopted on November 29, 2005.

Since the scope of the 2005 Revised WSIP is in general representative of the program that is in the end stage of being implemented today, the 2005 budget and schedule are considered the “Baseline Budget and Schedule.”
Subsequently, the WSIP Baseline Budget and Schedule were revised in 2007, 2009, 2011, 2013, 2014, 2015, 2016, 2017, 2018, 2020, 2022, and 2024, and these revisions were approved by the San Francisco Public Utilities Commission on February 26, 2008, July 28, 2009, July 12, 2011, April 23, 2013, April 22, 2014, December 8, 2015, April 26, 2016, February 14, 2017, April 10, 2018, April 14, 2020, April 26, 2022, and April 9, 2024, respectively.
1 WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 – 12/31/24) Program
Revision
Commission
Approval
Budget
($Million) Schedule(*)
2003 (Original) March 1, 2003 $3,628 03/15/16
2005 (Baseline) November 29, 2005 $4,343 06/30/14
2007 (Revised) February 26, 2008 $4,392 12/18/14
2009 (Revised) July 28, 2009 $4,586 12/04/15
2011 (Revised) July 12, 2011 $4,586 07/29/16
2013 (Revised) April 23, 2013 $4,640 04/11/19
2014 (Revised) April 22, 2014 $4,765 05/24/19
2015 (Revised) December 8, 2015 $4,765 05/24/19
2016 (Revised) April 26, 2016 $4,845 12/20/19
2017 (Revised) February 14, 2017 $4,845 12/20/19
2018 (Revised) April 10, 2018 $4,788 12/30/21
2020 (Revised) April 14, 2020 $4,788 05/05/23
2022 (Revised) April 26, 2022 $4,788 02/01/27
2024 (Revised) April 9, 2024 $4,793 06/30/32
* Final Program Completion Date
2 WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 - 12/31/24)

PROGRAM STATUS
This quarterly report provides a summary update on the regional projects in the Water System Improvement Program (WSIP) for the 2nd Quarter (Q2) of Fiscal Year (FY) 2024- 2025. The primary intent of the report is to provide the San Francisco Public Utilities Commission (“Commission”), stakeholders, and the public with a status summary of the program’s regional projects for the period of October 1, 2024 through December 31, 2024.

This quarterly report incorporates program and project changes from the March 2024 Revised WSIP, which was approved by the Commission on April 9, 2024 by Resolution No. 24-0089.

Program Current Status:

Figure A and Table A show the number of WSIP Regional projects and the total approved value of these projects that are active in various project phases. • “Not Applicable” category is for one project that does not include construction: Long Term Mitigation Endowment. • Program Management costs included in project budgets.

Figure A. Total Current Approved Budget for Regional Projects Active in Each Phase 3 WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 - 12/31/24) Table A. Status of WSIP Regional Projects (as of December 31, 2024) Project Phase No. of
Projects
Percent by No.
of Projects
Total Project
Value ($M)(2)
Percent by
Project Value
Planning 1 2% $51 1%
Design 0 0% $0 0%
Bid & Award 0 0% $0 0%
Construction 1 2% $164 4%
Close-Out 1 2% $96 3%
Completed 48 92% $3,485 92%
Not Applicable1 1 2% $12 0%
Total 52 100% $3,808 100%
Notes: (1) “Not Applicable” category is for the project that does not include construction: Long-Term Mitigation Endowment. (2) Program Management costs included in project budgets.

As of the end of the reporting period, one (1) regional project with a total value of $51M is in planning, one (1) regional project with a total value of $164M is in construction and forty-nine (49) projects with a total value of $3,582M are in close- out or have been completed. Forty -one (41) out of forty -three (43) Regional WSIP projects with specific Level of Service (LOS) goals have achieved their LOS goals to date.

Tables B and C provide an overall program -level cost and schedule summary of the WSIP Regional Program. The total Current Approved WSIP Budget (including Regional and Local Programs, Local Water Supply Projects, and Financing Costs) and the Current Forecasted Cost at completion are each $4,792.8 million. The Current Approved WSIP Budget and Forecasted Cost at completion for only the Regional Program (including construction contingency) are each $3,808.1 million.

Table B. Program Cost Summary
Cost Categories Expenditures
To Date
($ Million)
(A)
2005
Baseline
Budget
($ Million)
(B)
2024
Approved
Budget
($ Million)
(C)
Current
Approved
Budget
($ Million)
(D)
Q2/FY24-25
Forecasted
Costs
($ Million)
(E)
Cost
Variance
($ Million)
(F = D - E)
REGIONAL PROGRAM $3,745.5 $3,407.3 $3,808.1 $3,808.1 $3,808.1 - Local Improvement Projects $331.9 $383.2 $331.9 $331.9 $331.9 - Local Water Supply Projects $229.9 - $280.9 $280.9 $280.9 Finance $372.0 $552.0 $372.0 $372.0 $372.0 -
PROGRAM TOTAL $4,679.2 $4,342.5 $4,792.8 $4,792.8 $4,792.8 -
-
4 WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 - 12/31/24) The Current Approved and Forecasted Schedule completion for the Regional WSIP (Local WSIP was completed in June 2020) is June 2032.

Table C. 2024 Approved vs. Q2/FY24-25 Forecasted Schedule Dates Category
2005
Baseline
Start
2024
Approved
Start
Current
Approved
Start*
Actual
Start
2005
Baseline
Finish
2024
Approved
Finish
Current
Approved
Finish*
Q2/FY24-25
Forecasted
Finish***
Schedule
Variance
(Months)
Regional
Program 03/01/03 03/31/03 03/31/03 03/01/03 A*** 06/30/14 06/30/32 06/30/32 06/30/32 - Local**
Program 03/01/03 03/31/03 03/31/03 03/01/03 A*** 06/28/13 06/03/20 06/03/20 06/03/20 A Completed (-)
Overall
WSIP 03/01/03 03/31/03 03/31/03 03/01/03 A*** 06/30/14 06/30/32 06/30/32 06/30/32 - * The budget and schedule approved as part of the March 2024 WSIP, plus any additional budget and s
chedule changes approved by the Commission as part of additional contingencies on construction c
ontracts.
** Excluding Local Water Supply projects.
*** “A” represents the actual date.

As
of the end of the reporting period, the forecasted total program cost (regional and local projects) is $4,792.8M, which is the same as the current Commission Approved Budget. All approved change orders (COs) in active construction contracts total $15.1 M, and the forecasted remaining construction contingency is $5.6M. Director’s Reserve for the program included $12.9M.

P
rogress Towards Meeting Level of Service (LOS) Goals
The scope of the WSIP is based on the following Level of Service (LOS) goals for the Regional Water System: Seismic Reliability, Delivery Reliability, Water Quality Reliability, and Water Supply Reliability.

Each project that reaches construction substantial completion contributes to increasing the overall reliability of the system and achieving progress towards meeting the overall LOS goals for the system.

A
ppendix A lists the projects with their individual Primary (P) and Secondary (S) contributions towards LOS goals and indicates which projects have met their respective LOS goals. As can be seen in Appendix A, the actual operational service start dates indicate that 41 of the 43 Regional WSIP projects with specific LOS goals have achieved their LOS goals to date. The other 9 Regional WSIP projects do not have specific LOS goals. The WSIP team remains committed to achieving the overall LOS goals established for the system.
5 WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 - 12/31/24)

PROJECT STATUS
10015281 - Alameda Creek Recapture Project
Project Description: The planned facilities include the following components: four (4) identical vertical turbine pumps mounted on floating barges located in existing Pond F2 (including a mooring system); four (4) flexible discharge pipelines extending from each pump to a new pipe manifold located on shore; approximately 100-feet of 36-inch pipeline connection between the new pipe manifold and the existing Sunol Pipeline to discharge the recaptured water to the SFPUC system; throttling valves and a flow meter; electrical control building; 1,600 feet of power lines from the existing Hetch Hetchy Water & Power Calaveras Electrical Substation installed on 10 new power poles; and general site improvements. In addition, the scope includes conveyance of the water to various existing storage sites within the Sunol Valley or the Sunol Valley Water Treatment Plant, as necessary. Components may change based on a re-evaluation of the project during planning phase.

Program: Sunol Valley Region Project Status: Planning Environmental Status: Active (Various) Project Cost:

Approved
Forecast
Actual
$ 48.97 M
$ 48.97 M
$ 37.11 M
Project Schedule:

Approved
Forecast
09/30/03
09/30/03
06/30/32
06/30/32
Project Percent Complete: 78.4%
Key Milestones Environmental
Approval
Bid Advertisement Construction NTP Construction Final
Completion
Current Forecast
A 04/28/20 A 12/18/20 A 06/21/21 A 08/18/23 A
B 06/30/28 03/01/29 06/30/31
Progress and Status:

This project includes multiple construction contracts: (A) WD-2528R Alameda Creek Recapture (terminated); (B)
Alameda Creek Recapture Phase 2 (planning phase). For
Contract A, final payment to the Contractor was completed.

For Contract B, the strategy for project continuation is to focus on planning for the next two years to assume slope stabilization can be completed and a sustainable, operable facility can be built. During the quarter, the planning consultant presented examples of working pump stations
within the mining industry and example configurations and approaches. In addition, the team reviewed past alternatives and brainstormed new alternatives for consideration.

Issues and Challenges:

The budget will be re-evaluated when a new
project alternative has been selected.

Barge Pump Example at Mining Facility
02/28/29
6 WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 - 12/31/24) 10015241 - Regional Groundwater Storage and Recovery
Project Description: The scope
of work consists of two (2) phases. Phase 1 included construction of 13 wells to produce

6.2 mgd of dry year supply over 7.5 years. Phase 2 included construction of two (2) test wells, completion of the South San Francisco (SSF) Main well, pipeline, and other work. The test wells which would not be converted to production wells at this time will allow for determination as to whether the identified sites could be viable production wells, and will provide information to water quality and pumping capacities that can be used for future planning. The test wells have been completed. Phase 2 remaining work has been separated into two construction contracts due to the long lead-time required for easements and permits for construction at the South San Francisco well site. Phase 2A contract includes miscellaneous improvement work at multiple existing well sites such as installation of cathodic protection, variable frequency drives, and flowmeters; modification of valves; and rehabilitation of some wells. Phase 2B contract consists of work at the SSF Main Well and all related pipeline installation to connect the well to Cal Water's treatment facility, and also installation of electrical equipment to be connected to PG&E power.

Program: San Francisco Regional
Region Project Status: Construction Environmental Status: Completed (Various)
Project Cost:

Approved
Forecast
Actual
$ 158.35 M
$ 158.35 M
$ 135.15 M
Project Schedule:

Approved
Forecast
06/01/03
06/01/03
12/07/27
12/07/27
Project Percent Complete: 89.9%
Key Milestones Environmental
Approval
Bid Advertisement Construction NTP Construction Final
Completion
Current Forecast
A 09/07/09 A 09/07/11 A 01/30/12 A 09/05/12 A
B 08/07/14 A 09/22/14 A 04/06/15 A 09/02/22 A
C 11/10/20 A 09/27/21 A 06/23/22 A 05/30/25
D 04/01/23 A 10/27/23 A 06/24/24 A 12/10/26
Progress and Status:

This project includes multiple construction contracts: (A) WD-2600 Test Well Drilling (completed); (B) Phase 1
WD-2668 Well Station (13 wells; construction completed); (C) Phase 2A WD-2878A- Cathodic Protection and Other
Additional Work; and (D) Phase 2B WD-2878B – SSF Main
Well. For Phase 1 (Contract B), conversion of as-built
drawings to computer-aided design by City staff continued.

Design was completed for installation of steel gate at Colma BART Well and replacement of existing entrance gate with two new gates and new chain link fence at Serramonte Blvd Well Station. For Phase 2A (Contract C), vertical turbine shaft alignment has been finalized at the Lake Merced,
Colma BART, Linear Park, and Millbrae well sites. Staff is planning to increase the duration contingency for Phase 2A construction contract to provide additional time to complete remaining contract work due to procurement challenges and other delays, which will not impact the overall project schedule. For Phase 2B (Contract D), the purchase of
permanent easements are currently in escrow for water and electrical utilities from Kaiser Foundation Hospitals and for the acquisition of a 1,386-square-foot easement for an aerial water pipeline crossing over a canal including associated footings and braces from San Mateo County Flood and Sea Level Rise Resiliency District. Contractor continued
preparation of submittals, shop drawings, and request for Pump Running During 5-Day Testing at Colma Blvd Well Station information, and application of encroachment permits
from local agencies.

Issues and Challenges:

None at this time.
7 Thi
s page is intentionally left blank.

WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 - 12/31/24) 8 APPENDICES
A. LOS TABLE PROGRESS TOWARDS MEETING LOS GOALS
B. PROJECT PHASE, APPROVED BUDGET AND FORECAST COMPLETION DATES C. LIST OF ACRONYMS
WSIP Quarterly Report Q2-FY2024-2025 (10/01/24 – 12/31/24) 9 Appendices Q2-FY2024-2025 (10/01/24 – 12/31/24)
APPENDIX A. LOS Table Progress Towards Meeting LOS Goals (1) Project
No. Project Name / Construction Contract
Actual /
Approved
Substantial
Completion
Date
LOS Goals (P =Primary, S =Secondary) Actual
Operational
Service
Start
Construction
Progress
Toward LOS
Goals
Water
Quality
Seismic
Reliability
Delivery
Reliability
Water
Supply
San Joaquin Projects
CUW36401 Lawrence Livermore Water Quality
Improvement (Completed) 08/31/10 P 08/31/10 100%
CUW37301
San Joaquin Pipeline System (Completed)
(A) HH935A Crossovers
(B) HH935B Western Segment
(C) HH935C Eastern Segment
(A) 01/06/12
(B) 05/27/13
(C) 06/21/13
P
(A) 01/06/12
(B) 05/27/13
(C) 06/21/13
100%
CUW37302 Rehabilitation of Existing San Joaquin
Pipelines (Roselle Crossover; Completed) 05/13/11 P 05/13/11 100% CUW38401
Tesla Treatment Facility (Completed)
(A) DB116 Tesla Treatment Facility
Design-Build Contract
(B) HH953 Tesla Portal Protection
(A) 06/24/11
(B) 08/05/13 P S S (A) 06/24/11
(B) 08/05/13 100%
Sunol Valley Projects
CUW35201 Alameda Creek Recapture 11/18/22 P 10%
CUW35501
Standby Power Facilities - Various
Locations (Completed)
(A) WD-2553 East Bay - Standby Power
Facilities
(B) WD-2511 Peninsula - Standby Power
Facilities
(A) 09/11/08
(B) 04/15/10 P S (A) 09/11/08
(B) 04/15/10 100%
CUW35901 New Irvington Tunnel (Completed) 09/19/15 S P 02/27/15 100% CUW35902 Alameda Siphon #4 (Completed) 12/16/11 P S 12/16/11 100% CUW37001
Pipeline Repair & Readiness Improvements
(Completed)
(A) WD-2530 Phase A 8 Pipe Storage
Sites
(B) WD-2530 Phase B Pipe Rolling
Machine Facility @ Sunol Yard
(A) 02/09/07
(B) 07/14/08 P S (A) 02/09/07
(B) 07/14/08 100%
CUW37401
Calaveras Dam Replacement (Completed)
(A) WD-2551 Calaveras Dam
Replacement
(B) WD-2729 Alameda Creek Diversion
Dam
(A) 04/12/19
(B) 02/15/19
S P S (A) 04/12/19
(B) 02/15/19
(A) 100%
(B) 100%
CUW37402 Calaveras Reservoir Upgrades (Completed) 10/06/05 P 10/06/05 100% CUW37403 San Antonio Backup Pipeline (Completed) 12/31/14 P 12/31/14 100% CUW38101 SVWTP Expansion & Treated Water
Reservoir (Completed) 05/17/13 P P 05/17/13 100%
CUW38601 San Antonio Pump Station Upgrade
(Completed) 06/30/11 P 06/30/11 100%
10 Appendices Q2-FY2024-2025 (10/01/24 – 12/31/24)
Project
No. Project Name / Construction Contract
Actual /
Approved
Substantial
Completion
Date
LOS Goals (P =Primary, S =Secondary) Actual
Operational
Service
Start
Construction
Progress
Toward LOS
Goals
Water
Quality
Seismic
Reliability
Delivery
Reliability
Water
Supply
Bay Division Projects
CUW35301 BDPL Nos. 3 & 4 Crossover/Isolation
Valves (Completed) 11/15/07 P 11/15/07 100%
CUW35302 Seismic Upgrade of BDPL Nos. 3 & 4
(Completed) 10/26/15 P 06/20/14 100%
CUW36301 SCADA System - Phase II (Completed) 11/29/10 P 11/29/10 100% CUW36801 BDPL Reliability Upgrade – Tunnel
(Completed) 05/20/15 P S 10/15/14 100%
CUW36802
BDPL Reliability Upgrade – Pipeline
(Completed)
(A) WD-2541 East Bay
(B) WD-2542 Peninsula
(C) WD-2665 Cordilleras
(A) 12/09/11
(B) 06/13/12
(C) 03/05/13
P S
(A) 12/09/11
(B) 06/13/12
(C) 03/05/13
100%
CUW36803 BDPL Reliability Upgrade - Relocation of
BDPL Nos. 1 & 2 (Completed) 05/28/10 P 05/28/10 100%
CUW38001 BDPL Nos. 3 & 4 - Crossovers (Completed) 08/15/12 P S 08/15/12 100% CUW38901 SFPUC/EBMUD Intertie (Completed) 09/07/07 P 09/07/07 100% CUW39301 BDPL No. 4 Condition Assessment PCCP
Sections (Completed) 02/06/09 P S 02/06/09 100%
Peninsula Projects
CUW35401 Lower Crystal Springs Dam Improvements
(Completed) 11/20/11 P S 11/20/11 100%
CUW35601 New Crystal Springs Bypass Tunnel
(Completed) 07/14/11 P S 07/14/11 100%
CUW35701 Adit Leak Repair - Crystal
Springs/Calaveras (Completed) 11/30/07 P 11/30/07 100%
CUW36101 Pulgas Balancing - Inlet/Outlet Work
(Completed) 02/02/06 P S 02/02/06 100%
CUW36102 Pulgas Balancing - Discharge Channel
Modifications (Completed) 10/23/09 P 10/23/09 100%
CUW36103 Pulgas Balancing - Structural Rehabilitation
& Roof Replacement (Completed) 07/26/11 P S 07/26/11 100% CUW36105
Pulgas Balancing - Modifications of the
Existing Dechloramination Facility
(Completed)
08/27/12 P S 08/27/12 100%
CUW36501 Cross Connection Controls (Completed) 11/26/08 P 11/26/08 100% CUW36601 HTWTP Short-Term Improvements - Demo
Filters (Completed) 01/11/06 P S 01/11/06 100%
CUW36603
HTWTP Short-Term Improvements -
Coagulation & Flocculation/Remaining
Filters (Completed)
12/21/09 P S 12/21/09 100%
CUW36701 HTWTP Long -Term Improvements
(Completed) 09/08/15 P S 09/08/15 100%
CUW36702 Peninsula Pipelines Seismic Upgrade
(Completed) 10/30/15 P 10/30/15 100%
CUW36901 Capuchino Valve Lot Improvements
(Completed) 02/14/08 P 02/14/08 100%
CUW37101 Crystal Springs/San Andreas Transmission
Upgrade (Completed) 06/30/14 P S 09/02/14 100%
CUW37801 Crystal Springs Pipeline No. 2 Replacement
(Completed) 01/31/13 P S 01/31/13 100%
CUW37901 San Andreas Pipeline No. 3 Installation
(Completed) 03/29/11 P S 03/29/11 100%
CUW39101 Baden & San Pedro Valve Lots
Improvements (Completed) 03/31/11 P S 03/31/11 100%
11 Appendices Q2-FY2024-2025 (10/01/24 – 12/31/24)
Project
No. Project Name / Construction Contract
Actual /
Approved
Substantial
Completion
Date
LOS Goals (P =Primary, S =Secondary) Actual
Operational
Service
Start
Construction
Progress
Toward LOS
Goals
Water
Quality
Seismic
Reliability
Delivery
Reliability
Water
Supply
San Francisco Regional Projects
CUW30103
Regional Groundwater Storage and Recovery
(A) WD-2600 Test Well Drilling
(B) WD-2668 Regional Groundwater
Storage and Recovery (Phase 1)
(C) Regional Groundwater Storage and
Recovery (Phase 2A)
(D) Regional Groundwater Storage and
Recovery (Phase 2B)
(A) 07/23/12
(B) 12/31/17
(C) 12/06/24
(D) 09/11/26
P
(A) 07/23/12
(B) 07/27/22
(A) 100%
(B) 100%
(C) 91%
(D) 5%
CUW35801 Sunset Reservoir - North Basin (Completed) 09/19/08 P S 09/19/08 100% CUW37201 University Mound Reservoir - North Basin
(Completed) 05/25/11 P S 05/25/11 100%
Notes:
1 Support projects and WSIP Closeout projects are not listed in the table above since these projects do not have specific Level of Service (LOS) goals. 12 Appendix B. Project Phase, Approved Budget, and Forecast Completion Dates Q2-FY2024-2025 (10/01/24 – 12/31/24) Appendices
Project  Project Phase  Approved Budget Forecast
Completion Dates
RW‐SJ  San Joaquin Region
CUW36401  Lawrence Livermore Water Quality Improvement  Complete  $4,198,247.38  31‐Jul‐13 A CUW37301  San Joaquin Pipeline System  Complete  $203,177,750.13  31‐Mar‐16 A CUW37302  Rehabilitation of Existing San Joaquin Pipelines  Complete  $21,168,797.08  31‐Oct‐14 A CUW38401  Tesla Treatment Facility  Complete  $113,225,330.53  30‐Jan‐15 A CUW38701  Tesla Portal Disinfection Station  Complete  $2,081,277.63  29‐Jun‐07 A CUWSJI0101  WSIP Closeout ‐ San Joaquin  Complete  $2,015,907.80  31‐Mar‐21 A RW‐SV  Sunol Valley Region
CUW35201  Alameda Creek Recapture Project  Planning  $48,967,394.56  30‐Jun‐32 CUW35501  Standby Power Facilities ‐ Various Locations  Complete  $12,950,565.74  22‐Dec‐10 A CUW35901  New Irvington Tunnel  Complete  $339,945,522.94  31‐Mar‐18 A CUW35902  Alameda Siphon #4  Complete  $64,730,537.94  28‐Jun‐13 A CUW37001  Pipeline Repair & Readiness Improvements  Complete  $5,178,466.13  16‐Apr‐09 A CUW37401  Calaveras Dam Replacement  Complete  $794,059,378.86   31‐Mar‐22 A CUW37402  Calaveras Reservoir Upgrades  Complete  $1,690,552.40   28‐Jul‐06 A CUW37403  San Antonio Backup Pipeline  Complete  $53,562,178.04   30‐Jun‐16 A CUW38101  SVWTP Expansion & Treated Water Reservoir  Complete  $129,593,674.08   31‐Oct‐14 A CUW38102  SVWTP Calaveras Road  Deferred  $34,654.15   14‐Dec‐07 A CUW38201  SVWTP Treated Water Reservoir  Deferred  $5,056,595.57   02‐Mar‐07 A CUW38601  San Antonio Pump Station Upgrade  Complete  $12,886,140.43   29‐Jun‐12 A CUWSVI0101  WSIP Closeout ‐ Sunol Valley  Complete  $5,558,384.67   31‐Dec‐22 A RW‐BD  Bay Division Region
CUW35301  BDPL Nos. 3 & 4 Crossover/Isolation Valves  Complete  $27,045,625.92   31‐Jul‐09 A CUW35302  Seismic Upgrade of BDPL Nos. 3 & 4  Complete  $70,524,332.31   30‐Jul‐18 A CUW36301  SCADA System ‐ Phase II  Complete  $9,473,038.96   28‐May‐13 A CUW36801  BDPL Reliability Upgrade / Tunnel  Complete  $272,364,089.37   30‐Aug‐16 A CUW36802  BDPL Reliability Upgrade ‐ Pipeline  Complete  $216,795,625.11   31‐Mar‐16 A CUW36803  BDPL Reliability Upgrade ‐ Relocation of BDPL Nos. 1 & 2  Complete  $3,046,980.62   28‐May‐10 A CUW38001  BDPL Nos. 3 & 4 Crossovers  Complete  $29,913,049.16   30‐Jun‐14 A CUW38901  SFPUC/EBMUD Intertie  Complete  $9,167,305.97   20‐Mar‐14 A CUW39301  BDPL No. 4 Condition Assessment PCCP Sections  Complete  $1,937,599.43   06‐Feb‐09 A CUWBDP0101  WSIP Closeout ‐ Bay Division  Complete  $3,322,156.03   31‐Mar‐21 A RW‐PN  Peninsula Region
CUW35401  Lower Crystal Springs Dam Improvements  Complete  $34,860,071.88   28‐Dec‐12 A CUW35601  New Crystal Springs Bypass Tunnel  Complete  $81,435,609.73   17‐Aug‐12 A CUW35701  Adit Leak Repair ‐ Crystal Springs/Calaveras  Complete  $2,787,322.29   31‐Jul‐08 A CUW36101  Pulgas Balancing ‐ Inlet/Outlet Work  Complete  $1,765,938.44   11‐May‐06 A CUW36102  Pulgas Balancing ‐ Discharge Channel Modifications  Complete  $2,910,007.00   30‐Jul‐10 A CUW36103  Pulgas Balancing ‐ Structural Rehabilitation and Roof Replacement  Complete  $20,227,447.13   28‐Dec‐12 A CUW36104  Pulgas Balancing ‐ Laguna Creek Sedimentation  Deferred  $505,126.92   31‐Dec‐07 A CUW36105  Pulgas Balancing ‐ Modifications of the Existing Dechloramination F  Complete  $5,391,353.43   20‐Mar‐13 A CUW36501  Cross Connection Controls  Complete  $3,948,726.89   30‐Apr‐09 A CUW36601  HTWTP Short‐Term Improvements (Demo Filters)  Complete  $3,067,903.44   14‐Nov‐06 A CUW36602 HTWTP Short‐Term Improvements ‐ Remaining Filters  Deferred  $1,424,510.34   22‐Feb‐08 A CUW36603  HTWTP Short‐Term Improvements ‐ Coagulation & Flocculation/ Re  Complete  $18,604,937.13   28‐Jul‐10 A CUW36701  HTWTP Long‐Term Improvements  Complete  $273,894,601.92   30‐Dec‐16 A 13 Appendix B. Project Phase, Approved Budget, and Forecast Completion Dates Q2-FY2024-2025 (10/01/24 – 12/31/24) Appendices
Project  Project Phase Approved Budget  Forecast
Completion Dates
CUW36702  Peninsula Pipelines Seismic Upgrade  Complete  $38,779,772.41   06‐Jul‐16 A CUW36901  Capuchino Valve Lot Improvements  Complete  $2,803,153.43   19‐Aug‐08 A CUW37101 Crystal Springs/San Andreas Transmission Upgrade  Complete  $189,649,573.32   30-Jun-15 A CUW37801 Crystal Springs Pipeline No. 2 Replacement  Complete  $56,070,509.12   31-Dec-14 A CUW37901 San Andreas Pipeline No. 3 Installation  Complete  $27,519,715.96   30-Aug-12 A CUW39101 Baden and San Pedro Valve Lots Improvements  Complete  $24,993,478.00   29-Mar-13 A CUWPWI0101 WSIP Closeout - Peninsula  Complete  $13,560,085.73   30-Dec-21 A RW‐Reg  San Francisco Regional Region
CUW30103  Regional Groundwater Storage and Recovery  Construction  $158,350,433.06   07‐Dec‐27 CUW35801  Sunset Reservoir ‐ North Basin  Complete  $64,270,725.16   10‐Sep‐10 A CUW37201  University Mound Reservoir ‐ North Basin  Complete  $43,266,311.62   29‐Mar‐13 A RW‐SW  Support Projects
CUW36302 System Security Upgrades  Complete  $14,397,894.00   19-Apr-19 A CUW38801 Programmatic EIR  Complete  $10,734,567.27   30-Jun-09 A CUW38802 Bioregional Habitat Restoration  Closeout  $93,341,983.01  30‐Dec‐27 CUW38803 Vegetation Restoration of WSIP Construction Sites  Complete  $2,111,545.75  30-Jun-16 A CUW38804 Long term Mitigation Endowment  Not Applicable  $12,000,000.00  24‐Dec‐26 CUW39201 Program Management Project   Not Applicable  $121,642,047.50  30‐Jun‐32 CUW39401 Watershed and Environmental Improvement Program  Complete  $20,079,149.69  30-Jun-22 A 14 APPENDIX C. LIST OF ACRONYMS
BART Bay Area Rapid Transit
BDPL Bay Division Pipeline
CIP Capital Improvement Program
CO Change Order
DB Design, Build
EBMUD East Bay Municipal Utility District
EIR Environmental Impact Report
FY Fiscal Year
HH Hetch Hetchy
HTWTP
LOS
MGD
N/A
NIT
NTP
PCCP
PG&E
Harry Tracy Water Treatment Plant
Levels of Service
Million Gallon
s Per Day
Not Applicable
New Irvington Tunnel
Notice to Proceed
Pre-stressed Concrete Cylinder Pipe
Pacific Gas and Electric Company
RGWSR Regional Groundwater Storage and Recovery
SCADA Supervisory Control and Data Acquisition
SFPUC San Francisco Public Utilities Commission
SSF South San Francisco
SVWTP Sunol Valley Water Treatment Plant
WSIP Water System Improvement Program
Appendices Q2-FY2024-2025 (10/01/24 - 12/31/24)
15 This page is intentionally left blank.
16

← All documents from this meeting