1 Water Enterprise Capital Improvement Program (WECIP) and Water System Improvement Program (WSIP)
Quarterly Report Update
Q3 FY 2024
-

2025

June 10, 2025

Not Initiated (7), $140M
Planning (14), $778M
Design (9), $310M
Bid and Award (2), $92M
Construction (14),
$1,324M
Closeout (2), $69M
Completed (0), $0
Multi-Phases (4),
$1,389M
$4.0B
(52 Projects)
$1,257M
$2,845M
Expended Remaining
34%
% Complete
ExpendituresProject Count by Phase
· Regional and Local Program
Management costs are included in
the project budgets.

Water Enterprise CIP Program Status
(as of March 2025)
Water Enterprise CIP
Program Cost Summary
(as of March 2025 - active projects only)
3 Program Name
Expenditures
to Date
($Million)
Approved Budget
($Million)
Current
Forecasted
Cost ($Million)
Cost Variance
($Million)
New Variance
During
Q3FY25
($Million)
Regional WECIP $285 $1,697 $1704 ($7) ($4)
Water Treatment $64 $530 $530 - -
Water Transmission $36 $332 $332 - -
Water Supply & Storage $20 $139 $143 ($4) ($4)
Watershed & Lands
Management $41 $79 $79 - -
Buildings and Grounds $124 $574 $577 ($3) -
Program Management $0.4 $42 $42 - -
Local WECIP $972 $2,405 $2,406 ($1) ($1)
Local Water Transmission $575 $1,262 $1,262 - -
Local Water Supply $277 $383 $383 - -
Local Tanks/Reservoir
Improvements $27 $121 $122 ($1) ($1)
Pump Stations $1 $9 $9 - -
Buildings and Grounds $35 $405 $405 - -
Emergency Firefighting
Water System
$56 $183 $183 - -
Program Management $0.4 $41 $41 - -
Overall WECIP $1,257 $4,102 $4,110 ($7) ($4)
Regional Water Projects in Construction
• Sunol Valley Water Treatment Plant Ozone –5% complete • Harry Tracy Water Treatment Plant Filter Underdrain Replacement – 99.8% complete • Sunol Valley Chloramination Facility Master Upgrades – 8% complete • Corrosion Control – 93% complete
• San Antonio Pump Station Motor Control Center Upgrades – 3% complete • Southern Skyline Blvd Ridge Trail Extension – 67% complete • San Andreas-1 Service Road – 91% complete
• Sunol Long Term Improvements – Watershed Center – 99% complete 4 Sunol Valley Chloramination Facility
San Andreas-1 Service Road Southern Skyline Blvd. Ridge TrailSunol Valley Water Treatment Plant Ozone

Sunol Valley Water Treatment Plant Ozone
Approved Budget: $326.4M
Forecast Cost: $326.4M
Forecast Completion: March 2030
Progress and Status
• Construction continued on the drainage
and cooling water pump stations,
piping/conduit rerouting, and City trailer
installation.
• Unidentified utilities continue to be
discovered, requiring rerouting or design
adjustments.
• All Year-1 connections to be completed by
October in preparation for Sunol Valley
Water Treatment Plant winter operations.
5 Current Phase: Construction
Expended to Date: $34.9M
Concrete Pour for Open Loop Cooling Water Pump Station
Southern Skyline Blvd Ridge Trail Extension
Approved Budget: $38.0M
Forecast Cost: $38.0M
Forecast Completion: March 2026
Progress and Status
• Approximately 75% of the finished trail
surface has been placed.
• Grading continued for the Universal
Access Loop Trail and parking lot north of
Route 92.
• Remaining security fences being prepared
for installation.
6 Current Phase: Construction
Expended to Date: $25.6M
View of Retaining Wall Prior to Installation of Cable Rail

Local Water Projects in Construction
• Town of Sunol Pipeline – Issued Notice to Proceed
• Local Water Conveyance/Main Replacement – 10 contracts underway • Lead Component Services Program – 55% complete
• Westside Enhanced Water Recycling –99% complete
• College Hill Reservoir – 96% complete
• New SFWD Headquarters – 2% complete
• EFWS – Clarendon Supply – 90% complete
7 Main Replacement
Westside Enhanced Water Recycling Facility College Hill ReservoirSan Francisco Water Division Headquarters

Emergency Firefighting Water System Pipelines
Approved Budget: $154.1M
Forecast Cost: $154.1M
Forecast Completion: August 2034
Current Phase: Design
Expended to Date: $36.2M
Progress and Status
• Clarendon Supply contract in Close-out.
• Fireboat Manifolds: Planning continues for 3
locations.
• Potable EFWS Pipelines:
• Contract A (Lake Merced Pump Station to
Sloat Blvd/19th Ave) near 95% design.
• Contract B (23rd Ave/Vicente to 42nd
Ave/Lawton St) near 35% design.
• Pipeline alignment adjacent to Sunset Blvd.
being considered for optimal fire break.
8 Potable Emergency Firefighting Pipeline being
installed along 19th Avenue

Planning
$51M
(1 Project)
$62M
$3,746M
Expended Remaining
99%
% Complete
ExpendituresProject Count by Phase
$3.8B
(52 Projects)
Not Applicable*
$12M
(1 Project)
Completed
$3,485M
(48 Projects)
Construction
$164M
(1 Project)
Closeout
$96M
(1 Project)
• “Not Applicable” category is for one project that does not include construction: Long-Term Mitigation Endowment.
• Program Management costs included in project budgets.

Water System Improvement Program (WSIP)
Regional Program Status
(as of March 2025)
Regional WSIP Cost Summary
(March 2025 – active projects only)
10 Program Name
Expenditures
to Date
($Million)
Current
Approved
Budget
($Million)
Current
Forecasted
Cost ($Million)
Cost
Variance
($Million)
San Joaquin Region - - - -
Sunol Valley Region $37.2 $49.0 $49.0 -
Bay Division Region - - - -
Peninsula Region - - - -
San Francisco Regional
Region $135.7 $158.4 $158.4 -
Regional WSIP
(Total – Active Projects) $172.9 $207.4 $207.4 $0.0
Regional WSIP
(Total - All Projects) $3,746 $3,808 $3,808 $0.0
WSIP Projects Highlights
• Regional Groundwater Storage and Recovery Project
• Project 91% complete
• Phase 2A – Existing Wells Improvements - Start-up and testing completed, finishing remaining punch list items. • Phase 2B – South Sunset Main Well - Contractor
continued preparing submittals and shop drawings
and obtaining permits from local agencies.
• Alameda Creek Recapture Project
• Planning for redesigned facility under
new contract continued.
11 Regional Groundwater Storage and Recovery
Project – Phase 2B Site Preparation

QUESTIONS?
DATE:

TO:

FROM:

April 11, 2025
Commissioner Kate H. Stacy, President
Commissioner Joshua Arce, Vice President
Commissioner Avni Jamdar
Commissioner Steve Leveroni
Dennis J. Herrera, General Manager
SUBJECT: W
ater System Improvement Program
Quarterly Report (3rd Quarter / FY 2024-2025)
525 Golden Gate Avenue, 13th Floor
San Francisco, CA 94102
T 415.554.3155
F 415.554.3161
TTY 415.554.3488
Enclosed please find the Water System Improvement Program (WSIP) Quarterly Report for the 3rd Quarter (Q 3) of Fiscal Year (FY) 2024- 2025. The primary intent of the report is to provide the Commission, stakeholders, and the public with a status summary of the Water System Improvement Program based on data for the period of January 1, 2025 to March 31, 2025. This quarterly report provides a summary update on the Regional WSIP projects. The Local WSIP was completed in June 2020.

Attachment
OUR MISSION: To provide our customers with high-quality, efficient and reliable water, power and sewer services
in a manner that values environmental and community interests and sustains the resources entrusted to our c
are.

This page is intentionally left blank.

Published: Apri l 11, 2025

QUARTERLY REPORT
Regional Projects
Q3 FY 2024 | 2025
January 2025 — March 2025
Rebuilding Today for a Better Tomorrow

This page is intentionally left blank.

WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 – 03/31/25)

PROGRAM DESCRIPTION
The Water System Improvement Program (WSIP) is a $4.8 billion, multi -year capital program to upgrade the City of San Francisco’s regional and local drinking water systems. The program will deliver improvements that enhance the City’s ability to provide reliable, affordable, high quality drinking water to its 26 wholesale customers and regional retail customers in Alameda, Santa Clara, and San Mateo Counties, and to 800,000 retail customers in San Francisco, in an environmentally sustainable manner. The WSIP is structured to cost -effectively meet water quality requirements, improve seismic and delivery reliability, and achieve water supply goals.

Built in the early to mid- 1900s, the water system has many components nearing the end of their working life, with crucial facilities crossing, or in close proximity to, three major earthquake faults. The San Francisco Public Utilities Commission (SFPUC) initiated the WSIP to repair, replace, and seismically upgrade the system’s deteriorating pipelines, tunnels, dams, reservoirs, pump stations, storage tanks, and treatment facilities.

The program consists of 35 local projects located within San Francisco and 52 regional projects spread over seven different counties from the Sierra foothills to San Francisco. Local projects only benefit San Francisco residents whereas regional projects benefit both City residents and the 26 wholesale agencies that receive water from the SFPUC. The management of regional projects is divided into 6 regions – San Joaquin, Sunol Valley, Bay Division, Peninsula, San Francisco Regional, and Support Projects.

The WSIP is funded through the issuance of revenue bonds. Local Measures A and E, which were approved by San Francisco voters in November 2002, allowed for the financing of improvements to the City’s water system using revenue bonds and/or other forms of revenue financing. Increases in the water rates of retail and wholesale customers are used to pay back the debt service on the bonds.

The program budget and schedule were originally adopted by the San Francisco Public Utilities Commission on March 1, 2003. The program at the time was referred to as the Capital Improvement Program (CIP). The scope of the CIP was changed significantly following the adoption of Level of Service (LOS) goals in early 2005. The program changes were so substantial that the program was renamed the WSIP and a new program budget and schedule were adopted on November 29, 2005.

Since the scope of the 2005 Revised WSIP is in general representative of the program that is in the end stage of being implemented today, the 2005 budget and schedule are considered the “Baseline Budget and Schedule.”
Subsequently, the WSIP Baseline Budget and Schedule were revised in 2007, 2009, 2011, 2013, 2014, 2015, 2016, 2017, 2018, 2020, 2022, and 2024, and these revisions were approved by the San Francisco Public Utilities Commission on February 26, 2008, July 28, 2009, July 12, 2011, April 23, 2013, April 22, 2014, December 8, 2015, April 26, 2016, February 14, 2017, April 10, 2018, April 14, 2020, April 26, 2022, and April 9, 2024, respectively.
1 WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 – 03/31/25) Program
Revision
Commission
Approval
Budget
($Million) Schedule(*)
2003 (Original) March 1, 2003 $3,628 03/15/16
2005 (Baseline) November 29, 2005 $4,343 06/30/14
2007 (Revised) February 26, 2008 $4,392 12/18/14
2009 (Revised) July 28, 2009 $4,586 12/04/15
2011 (Revised) July 12, 2011 $4,586 07/29/16
2013 (Revised) April 23, 2013 $4,640 04/11/19
2014 (Revised) April 22, 2014 $4,765 05/24/19
2015 (Revised) December 8, 2015 $4,765 05/24/19
2016 (Revised) April 26, 2016 $4,845 12/20/19
2017 (Revised) February 14, 2017 $4,845 12/20/19
2018 (Revised) April 10, 2018 $4,788 12/30/21
2020 (Revised) April 14, 2020 $4,788 05/05/23
2022 (Revised) April 26, 2022 $4,788 02/01/27
2024 (Revised) April 9, 2024 $4,793 06/30/32
* Final Program Completion Date
2 WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 - 03/31/25)

PROGRAM STATUS
This quarterly report provides a summary update on the regional projects in the Water System Improvement Program (WSIP) for the 3rd Quarter (Q3) of Fiscal Year (FY) 2024- 2025. The primary intent of the report is to provide the San Francisco Public Utilities Commission (“Commission”), stakeholders, and the public with a status summary of the program’s regional projects for the period of January 1, 2025 through March 31, 2025.

This quarterly report incorporates program and project changes from the March 2024 Revised WSIP, which was approved by the Commission on April 9, 2024 by Resolution No. 24-0089.

Program Current Status:

Figure A and Table A show the number of WSIP Regional projects and the total approved value of these projects that are active in various project phases. • “Not Applicable” category is for one project that does not include construction: Long Term Mitigation Endowment. • Program Management costs included in project budgets.

Figure A. Total Current Approved Budget for Regional Projects Active in Each Phase 3 WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 - 03/31/25) Table A. Status of WSIP Regional Projects (as of March 31, 2025) Project Phase No. of
Projects
Percent by No.
of Projects
Total Project
Value ($M)(2)
Percent by
Project Value
Planning 1 2% $51 1%
Design 0 0% $0 0%
Bid & Award 0 0% $0 0%
Construction 1 2% $164 4%
Close-Out 1 2% $96 3%
Completed 48 92% $3,485 92%
Not Applicable1 1 2% $12 0%
Total 52 100% $3,808 100%
Notes: (1) “Not Applicable” category is for the project that does not include construction: Long-Term Mitigation Endowment. (2) Program Management costs included in project budgets.

As of the end of the reporting period, one (1) regional project with a total value of $51M is in planning, one (1) regional project with a total value of $164M is in construction and forty-nine (49) projects with a total value of $3,582M are in close- out or have been completed. Forty -one (41) out of forty -three (43) Regional WSIP projects with specific Level of Service (LOS) goals have achieved their LOS goals to date.

Tables B and C provide an overall program -level cost and schedule summary of the WSIP Regional Program. The total Current Approved WSIP Budget (including Regional and Local Programs, Local Water Supply Projects, and Financing Costs) and the Current Forecasted Cost at completion are each $4,792.8 million. The Current Approved WSIP Budget and Forecasted Cost at completion for only the Regional Program (including construction contingency) are each $3,808.1 million.

Table B. Program Cost Summary
Cost Categories Expenditures
To Date
($ Million)
(A)
2005
Baseline
Budget
($ Million)
(B)
2024
Approved
Budget
($ Million)
(C)
Current
Approved
Budget
($ Million)
(D)
Q3/FY24-25
Forecasted
Costs
($ Million)
(E)
Cost
Variance
($ Million)
(F = D - E)
REGIONAL PROGRAM $3,746.2 $3,407.3 $3,808.1 $3,808.1 $3,808.1 - Local Improvement Projects $331.9 $383.2 $331.9 $331.9 $331.9 - Local Water Supply Projects $230.0 - $280.9 $280.9 $280.9 - Finance $372.0 $552.0 $372.0 $372.0 $372.0 -
PROGRAM TOTAL $4,680.0 $4,342.5 $4,792.8 $4,792.8 $4,792.8 - 4 WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 - 03/31/25) The Current Approved and Forecasted Schedule completion for the Regional WSIP (Local WSIP was completed in June 2020) is June 2032.

Table C. 2024 Approved vs. Q3/FY24-25 Forecasted Schedule Dates Category
2005
Baseline
Start
2024
Approved
Start
Current
Approved
Start*
Actual
Start
2005
Baseline
Finish
2024
Approved
Finish
Current
Approved
Finish*
Q3/FY24-25
Forecasted
Finish***
Schedule
Variance
(Months)
Regional
Program 03/01/03 03/31/03 03/31/03 03/01/03 A*** 06/30/14 06/30/32 06/30/32 06/30/32 - Local**
Program 03/01/03 03/31/03 03/31/03 03/01/03 A*** 06/28/13 06/03/20 06/03/20 06/03/20 A Completed (-)
Overall
WSIP 03/01/03 03/31/03 03/31/03 03/01/03 A*** 06/30/14 06/30/32 06/30/32 06/30/32 - * The budget and schedule approved as part of the March 2024 WSIP, plus any additional budget and schedule changes approved by the Commission as part of additional contingencies on construction contracts.
** Excluding Local Water Supply projects.
*** “A” represents the actual date.

As of the end of the r
eporting period, the forecasted total program cost (regional and local projects) is $4,792.8M, which is the same as the current Commission Approved Budget. All approved change orders (COs) in active construction contracts total $15.1 M, and the forecasted remaining construction contingency is $5.6M. Director’s Reserve for the program included $12.9M.

Progre
ss Towards Meeting Level of Service (LOS) Goals
The scope of the WSIP is based on the following Level of Service (LOS) goals for the Regional Water System: Seismic Reliability, Delivery Reliability, Water Quality Reliability, and Water Supply Reliability.

Each project that reaches construction substantial completion contributes to increasing the overall reliability of the system and achieving progress towards meeting the overall LOS goals for the system.

Appendix A
lists the projects with their individual Primary (P) and Secondary (S) contributions towards LOS goals and indicates which projects have met their respective LOS goals. As can be seen in Appendix A, the actual operational service start dates indicate that 41 of the 43 Regional WSIP projects with specific LOS goals have achieved their LOS goals to date. The other 9 Regional WSIP projects do not have specific LOS goals. The WSIP team remains committed to achieving the overall LOS goals established for the system.
5 WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 - 03/31/25)

PROJECT STATUS
10015281 - Alameda Creek Recapture Project
Project Description: The planned facilities include the following components: four (4) identical vertical turbine pumps
mounted on floating barges located in existing Pond F2 (including a mooring system); four (4) flexible discharge pipelines extending from each pump to a new pipe manifold located on shore; approximately 100-feet of 36-inch pipeline connection between the new pipe manifold and the existing Sunol Pipeline to discharge the recaptured water to the SFPUC system; throttling valves and a flow meter; electrical control building; 1,600 feet of power lines from the existing Hetch Hetchy Water & Power Calaveras Electrical Substation installed on 10 new power poles; and general site improvements. In addition, the scope includes conveyance of the water to various existing storage sites within the Sunol Valley or the Sunol Valley Water Treatment Plant, as necessary. Components may change based on a re-evaluation of the project during planning phase.

Program: Sunol Valley Region Project Status: Planning Environmental Status: Active (Various) Project Cost:

Approved
Forecast
Actual
$ 48.97 M
$ 48.97 M
$ 37.21 M
Project Schedule:

Approved
Forecast
09/30/03
09/30/03
06/30/32
06/30/32
Project Percent Complete: 78.4%
Key Milestones Environmental
Approval
Bid Advertisement Construction NTP Construction Final
Completion
Current Forecast
A 04/28/20 A 12/18/20 A 06/21/21 A 08/18/23 A
B 06/30/28 03/01/29 06/30/31 07/03/28
Progress and Status:

This project includes multiple construction contracts: (A) WD-2825R Alameda Creek Recapture (terminated); (B)
Alameda Creek Recapture Phase 2 (planning phase). For
Contract A, closeout is complete. For Contract B, the strategy for project continuation is to focus on planning for the next two years to assume slope stabilization can be completed and a sustainable, operable facility can be built. During the quarter, the planning consultant revisited the project
assumptions with the project team to define the updated needs and level of service for the facility.

Issues and Challenges:

As reported last quarter, the budget will be re-evaluated when a new project alternative has been selected.
6 Pond F2 Looking West

WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 - 03/31/25) 10015241 - Regional Groundwater Storage and Recovery
Project Description: The scope of work consists of two (2) phases. Phase 1 included construction of 13 wells to produce

6.2 mgd of dry year supply over 7.5 years. Phase 2 included construction of two (2) test wells, completion of the South San Francisco (SSF) Main well, pipeline, and other work. The test wells which would not be converted to production wells at this time will allow for determination as to whether the identified sites could be viable production wells, and will provide information to water quality and pumping capacities that can be used for future planning. The test wells have been completed. Phase 2 remaining work has been separated into two construction contracts due to the long lead-time required for easements and permits for construction at the South San Francisco well site. Phase 2A contract includes miscellaneous improvement work at multiple existing well sites such as installation of cathodic protection, variable frequency drives, and flowmeters; modification of valves; and rehabilitation of some wells. Phase 2B contract consists of work at the SSF Main Well and all related pipeline installation to connect the well to Cal Water's treatment facility, and also installation of electrical equipment to be connected to PG&E power.

Program: San Francisco Regional
Region Project Status: Construction Environmental Status: Completed (Various)
Project Cost:

Approved
Forecast
Actual
$ 158.35 M
$ 158.35 M
$ 135.71 M
Project Schedule:

Approved
Forecast
06/01/03
06/01/03
12/07/27
12/07/27
Project Percent Complete: 91.3%
Key Milestones Environmental
Approval
Bid Advertisement Construction NTP Construction Final
Completion
Current Forecast
A 09/07/09 A 09/07/11 A 01/30/12 A 09/05/12 A
B 08/07/14 A 09/22/14 A 04/06/15 A 09/02/22 A
C 11/10/20 A 09/27/21 A 06/23/22 A 05/30/25
D 04/01/23 A 10/27/23 A 06/24/24 A 12/10/26
7 Progress and Status:

This project includes multiple construction contracts: (A) WD-2600 Test Well Drilling (completed); (B) Phase 1
WD-2668 Well Station (13 wells; construction completed); (C) Phase 2A WD-2878A- Cathodic Protection and Other
Additional Work; and (D) Phase 2B WD-2878B – SSF Main
Well. For Phase 1 (Contract B), conversion of as-built
drawings to computer-aided design by City staff continued.

Contractor is preparing cost proposal for the installation of steel gate at Colma BART Well and replacement of existing entrance gate with two new gates and new chain link fence at Serramonte Blvd Well Station. For Phase 2A (Contract C), the Commission approved the increase of the duration
contingency for Phase 2A construction contract with no
change to contract amount, to provide additional time to properly install vertical turbine line shafts with the approved operation and maintenance manual. Contractor has
completed startup and testing; and continue to finish up the remaining punch list items and change orders such as
replacement of converter for Colma BART's transmission
line
flowmeter, and repair of the ball valve actuator at Serra Bowl.

For Phase 2B (Contract D), the purchase of permanent
easements continued to be in escrow for water and electrical utilities from Kaiser Foundation Hospitals and for the
acquisition of a 1,386-square-foot easement for an aerial water pipeline crossing over a canal including associated Colma BART - Completed Pump Reinstallation
footings and braces from San Mateo County Flood and
Sea Level Rise Resiliency District. Contractor continued preparation of submittals, shop drawings, and request for information, and application of encroachment permits
from local agencies.

Issues and Challenges:

None at this time.

This page is intentionally left blank.
8 APPENDICES
A. LOS TABLE PROGRE

SS TOWARDS MEETING LOS GOALS
B. PROJECT PHASE,

APPROVED BUDGET, AND FORECAST COMPLETION DATES
C. LIST OF ACRONYMS
WSIP Quarterly Report Q3-FY2024-2025 (01/01/25 – 03/31/25) 9 Appendices Q3-FY2024-2025 (01/01/25 – 03/31/25)
LOS Table P
rogress Towards Meeting LOS Goals (1)
Project
No. Project Name / Construction Contract
Actual /
Approved
Substantial
Completion
Date
LOS Goals (P =Primary, S =Secondary) Actual
Operational
Service
Start
Construction
Progress
Toward LOS
Goals
Water
Quality
Seismic
Reliability
Delivery
Reliability
Water
Supply
San Joaquin Projects
CUW36401 Lawrence Livermore Water Quality
Improvement (Completed) 08/31/10 P 08/31/10 100%
CUW37301
San Joaquin Pipeline System (Completed)
(A) HH935A Crossovers
(B) HH935B Western Segment
(C) HH935C Eastern Segment
(A) 01/06/12
(B) 05/27/13
(C) 06/21/13
P
(A) 01/06/12
(B) 05/27/13
(C) 06/21/13
100%
CUW37302 Rehabilitation of Existing San Joaquin
Pipelines (Roselle Crossover; Completed) 05/13/11 P 05/13/11 100% CUW38401
Tesla Treatment Facility (Completed)
(A) DB116 Tesla Treatment Facility
Design-Build Contract
(B) HH953 Tesla Portal Protection
(A) 06/24/11
(B) 08/05/13 P S S (A) 06/24/11
(B) 08/05/13 100%
Sunol Valley Projects
CUW35201 Alameda Creek Recapture 11/18/22 P 10%
CUW35501
Standby Power Facilities - Various
Locations (Completed)
(A) WD-2553 East Bay - Standby Power
Facilities
(B) WD-2511 Peninsula - Standby Power
Facilities
(A) 09/11/08
(B) 04/15/10 P S (A) 09/11/08
(B) 04/15/10 100%
CUW35901 New Irvington Tunnel (Completed) 09/19/15 S P 02/27/15 100% CUW35902 Alameda Siphon #4 (Completed) 12/16/11 P S 12/16/11 100% CUW37001
Pipeline Repair & Readiness Improvements
(Completed)
(A) WD-2530 Phase A 8 Pipe Storage
Sites
(B) WD-2530 Phase B Pipe Rolling
Machine Facility @ Sunol Yard
(A) 02/09/07
(B) 07/14/08 P S (A) 02/09/07
(B) 07/14/08 100%
CUW37401
Calaveras Dam Replacement (Completed)
(A) WD-2551 Calaveras Dam
Replacement
(B) WD-2729 Alameda Creek Diversion
Dam
(A) 04/12/19
(B) 02/15/19
S P S (A) 04/12/19
(B) 02/15/19
(A) 100%
(B) 100%
CUW37402 Calaveras Reservoir Upgrades (Completed) 10/06/05 P 10/06/05 100% CUW37403 San Antonio Backup Pipeline (Completed) 12/31/14 P 12/31/14 100% CUW38101 SVWTP Expansion & Treated Water
Reservoir (Completed) 05/17/13 P P 05/17/13 100%
CUW38601 San Antonio Pump Station Upgrade
(Completed) 06/30/11 P 06/30/11 100%
10 Appendices Q3-FY2024-2025 (01/01/25 – 03/31/25)
Project
No. Project Name / Construction Contract
Actual /
Approved
Substantial
Completion
Date
LOS Goals (P =Primary, S =Secondary) Actual
Operational
Service
Start
Construction
Progress
Toward LOS
Goals
Water
Quality
Seismic
Reliability
Delivery
Reliability
Water
Supply
Bay Division Projects
CUW35301 BDPL Nos. 3 & 4 Crossover/Isolation
Valves (Completed) 11/15/07 P 11/15/07 100%
CUW35302 Seismic Upgrade of BDPL Nos. 3 & 4
(Completed) 10/26/15 P 06/20/14 100%
CUW36301 SCADA System - Phase II (Completed) 11/29/10 P 11/29/10 100% CUW36801 BDPL Reliability Upgrade – Tunnel
(Completed) 05/20/15 P S 10/15/14 100%
CUW36802
BDPL Reliability Upgrade – Pipeline
(Completed)
(A) WD-2541 East Bay
(B) WD-2542 Peninsula
(C) WD-2665 Cordilleras
(A) 12/09/11
(B) 06/13/12
(C) 03/05/13
P S
(A) 12/09/11
(B) 06/13/12
(C) 03/05/13
100%
CUW36803 BDPL Reliability Upgrade - Relocation of
BDPL Nos. 1 & 2 (Completed) 05/28/10 P 05/28/10 100%
CUW38001 BDPL Nos. 3 & 4 - Crossovers (Completed) 08/15/12 P S 08/15/12 100% CUW38901 SFPUC/EBMUD Intertie (Completed) 09/07/07 P 09/07/07 100% CUW39301 BDPL No. 4 Condition Assessment PCCP
Sections (Completed) 02/06/09 P S 02/06/09 100%
Peninsula Projects
CUW35401 Lower Crystal Springs Dam Improvements
(Completed) 11/20/11 P S 11/20/11 100%
CUW35601 New Crystal Springs Bypass Tunnel
(Completed) 07/14/11 P S 07/14/11 100%
CUW35701 Adit Leak Repair - Crystal
Springs/Calaveras (Completed) 11/30/07 P 11/30/07 100%
CUW36101 Pulgas Balancing - Inlet/Outlet Work
(Completed) 02/02/06 P S 02/02/06 100%
CUW36102 Pulgas Balancing - Discharge Channel
Modifications (Completed) 10/23/09 P 10/23/09 100%
CUW36103 Pulgas Balancing - Structural Rehabilitation
& Roof Replacement (Completed) 07/26/11 P S 07/26/11 100% CUW36105
Pulgas Balancing - Modifications of the
Existing Dechloramination Facility
(Completed)
08/27/12 P S 08/27/12 100%
CUW36501 Cross Connection Controls (Completed) 11/26/08 P 11/26/08 100% CUW36601 HTWTP Short-Term Improvements - Demo
Filters (Completed) 01/11/06 P S 01/11/06 100%
CUW36603
HTWTP Short-Term Improvements -
Coagulation & Flocculation/Remaining
Filters (Completed)
12/21/09 P S 12/21/09 100%
CUW36701 HTWTP Long -Term Improvements
(Completed) 09/08/15 P S 09/08/15 100%
CUW36702 Peninsula Pipelines Seismic Upgrade
(Completed) 10/30/15 P 10/30/15 100%
CUW36901 Capuchino Valve Lot Improvements
(Completed) 02/14/08 P 02/14/08 100%
CUW37101 Crystal Springs/San Andreas Transmission
Upgrade (Completed) 06/30/14 P S 09/02/14 100%
CUW37801 Crystal Springs Pipeline No. 2 Replacement
(Completed) 01/31/13 P S 01/31/13 100%
CUW37901 San Andreas Pipeline No. 3 Installation
(Completed) 03/29/11 P S 03/29/11 100%
CUW39101 Baden & San Pedro Valve Lots
Improvements (Completed) 03/31/11 P S 03/31/11 100%
11 Appendices Q3-FY2024-2025 (01/01/25 – 03/31/25)
Project
No. Project Name / Construction Contract
Actual /
Approved
Substantial
Completion
Date
LOS Goals (P =Primary, S =Secondary) Actual
Operational
Service
Start
Construction
Progress
Toward LOS
Goals
Water
Quality
Seismic
Reliability
Delivery
Reliability
Water
Supply
San Francisco Regional Projects
CUW30103
Regional Groundwater Storage and Recovery
(A) WD-2600 Test Well Drilling
(B) WD-2668 Regional Groundwater
Storage and Recovery (Phase 1)
(C) Regional Groundwater Storage and
Recovery (Phase 2A)
(D) Regional Groundwater Storage and
Recovery (Phase 2B)
(A) 07/23/12
(B) 12/31/17
(C) 12/06/24
(D) 09/11/26
P
(A) 07/23/12
(B) 07/27/22
(A) 100%
(B) 100%
(C) 92%
(D) 5%
CUW35801 Sunset Reservoir - North Basin (Completed) 09/19/08 P S 09/19/08 100% CUW37201 University Mound Reservoir - North Basin
(Completed) 05/25/11 P S 05/25/11 100%
Notes:
1 Support projects and WSIP Closeout projects are not listed in the table above since these projects do not have specific Level of Service (LOS) goals. 12 Appendix B. Project Phase, Approved Budget, and Forecast Completion Dates Q3-FY2024-2025 (01/01/25 – 03/31/25) Appendices
Project Project Phase Approved Budget Forecast
Completion Dates
RW‐SJ San Joaquin Region
CUW36401 Lawrence Livermore Water Quality Improvement Complete $4,198,247.38 31‐Jul‐13 A CUW37301 San Joaquin Pipeline System Complete $203,177,750.13 31‐Mar‐16 A CUW37302 Rehabilitation of Existing San Joaquin Pipelines Complete $21,168,797.08 31‐Oct‐14 A CUW38401 Tesla Treatment Facility Complete $113,225,330.53 30‐Jan‐15 A CUW38701 Tesla Portal Disinfection Station Complete $2,081,277.63 29‐Jun‐07 A CUWSJI0101 WSIP Closeout ‐ San Joaquin Complete $2,015,907.80 31‐Mar‐21 A RW‐SV Sunol Valley Region
CUW35201 Alameda Creek Recapture Project Planning $48,967,394.56 30‐Jun‐32 CUW35501 Standby Power Facilities ‐ Various Locations Complete $12,950,565.74 22‐Dec‐10 A CUW35901 New Irvington Tunnel Complete $339,945,522.94 31‐Mar‐18 A CUW35902 Alameda Siphon #4 Complete $64,730,537.94 28‐Jun‐13 A CUW37001 Pipeline Repair & Readiness Improvements Complete $5,178,466.13 16‐Apr‐09 A CUW37401 Calaveras Dam Replacement Complete $794,059,378.86 31‐Mar‐22 A CUW37402 Calaveras Reservoir Upgrades Complete $1,690,552.40 28‐Jul‐06 A CUW37403 San Antonio Backup Pipeline Complete $53,562,178.04 30‐Jun‐16 A CUW38101 SVWTP Expansion & Treated Water Reservoir Complete $129,593,674.08 31‐Oct‐14 A CUW38102 SVWTP Calaveras Road Deferred $34,654.15 14‐Dec‐07 A CUW38201 SVWTP Treated Water Reservoir Deferred $5,056,595.57 02‐Mar‐07 A CUW38601 San Antonio Pump Station Upgrade Complete $12,886,140.43 29‐Jun‐12 A CUWSVI0101 WSIP Closeout ‐ Sunol Valley Complete $5,558,384.67 31‐Dec‐22 A RW‐BD Bay Division Region
CUW35301 BDPL Nos. 3 & 4 Crossover/Isolation Valves Complete $27,045,625.92 31‐Jul‐09 A CUW35302 Seismic Upgrade of BDPL Nos. 3 & 4 Complete $70,524,332.31 30‐Jul‐18 A CUW36301 SCADA System ‐ Phase II Complete $9,473,038.96 28‐May‐13 A CUW36801 BDPL Reliability Upgrade / Tunnel Complete $272,364,089.37 30‐Aug‐16 A CUW36802 BDPL Reliability Upgrade ‐ Pipeline Complete $216,795,625.11 31‐Mar‐16 A CUW36803 BDPL Reliability Upgrade ‐ Relocation of BDPL Nos. 1 & 2 Complete $3,046,980.62 28‐May‐10 A CUW38001 BDPL Nos. 3 & 4 Crossovers Complete $29,913,049.16 30‐Jun‐14 A CUW38901 SFPUC/EBMUD Intertie Complete $9,167,305.97 20‐Mar‐14 A CUW39301 BDPL No. 4 Condition Assessment PCCP Sections Complete $1,937,599.43 06‐Feb‐09 A CUWBDP0101 WSIP Closeout ‐ Bay Division Complete $3,322,156.03 31‐Mar‐21 A RW‐PN Peninsula Region
CUW35401 Lower Crystal Springs Dam Improvements Complete $34,860,071.88 28‐Dec‐12 A CUW35601 New Crystal Springs Bypass Tunnel Complete $81,435,609.73 17‐Aug‐12 A CUW35701 Adit Leak Repair ‐ Crystal Springs/Calaveras Complete $2,787,322.29 31‐Jul‐08 A CUW36101 Pulgas Balancing ‐ Inlet/Outlet Work Complete $1,765,938.44 11‐May‐06 A CUW36102 Pulgas Balancing ‐ Discharge Channel Modifications Complete $2,910,007.00 30‐Jul‐10 A CUW36103 Pulgas Balancing ‐ Structural Rehabilitation and Roof Replacement Complete $20,227,447.13 28‐Dec‐12 A CUW36104 Pulgas Balancing ‐ Laguna Creek Sedimentation Deferred $505,126.92 31‐Dec‐07 A CUW36105 Pulgas Balancing ‐ Modifications of the Existing Dechloramination F Complete $5,391,353.43 20‐Mar‐13 A CUW36501 Cross Connection Controls Complete $3,948,726.89 30‐Apr‐09 A CUW36601 HTWTP Short‐Term Improvements (Demo Filters) Complete $3,067,903.44 14‐Nov‐06 A CUW36602 HTWTP Short‐Term Improvements ‐ Remaining Filters Deferred $1,424,510.34 22‐Feb‐08 A CUW36603 HTWTP Short‐Term Improvements ‐ Coagulation & Flocculation/ Re Complete $18,604,937.13 28‐Jul‐10 A CUW36701 HTWTP Long‐Term Improvements Complete $273,894,601.92 30‐Dec‐16 A 13 Appendix B. Project Phase, Approved Budget, and Forecast Completion Dates Q3-FY2024-2025 (01/01/25 – 03/31/25) Appendices
Project Project Phase Approved Budget Forecast
Completion Dates
CUW36702 Peninsula Pipelines Seismic Upgrade Complete $38,779,772.41 06‐Jul‐16 A CUW36901 Capuchino Valve Lot Improvements Complete $2,803,153.43 19‐Aug‐08 A CUW37101 Crystal Springs/San Andreas Transmission Upgrade Complete $189,649,573.32 30‐Jun‐15 A CUW37801 Crystal Springs Pipeline No. 2 Replacement Complete $56,070,509.12 31‐Dec‐14 A CUW37901 San Andreas Pipeline No. 3 Installation Complete $27,519,715.96 30‐Aug‐12 A CUW39101 Baden and San Pedro Valve Lots Improvements Complete $24,993,478.00 29‐Mar‐13 A CUWPWI0101 WSIP Closeout ‐ Peninsula Complete $13,560,085.73 30‐Dec‐21 A RW‐Reg San Francisco Regional Region
CUW30103 Regional Groundwater Storage and Recovery Construction $158,350,433.06 07‐Dec‐27 CUW35801 Sunset Reservoir ‐ North Basin Complete $64,270,725.16 10‐Sep‐10 A CUW37201 University Mound Reservoir ‐ North Basin Complete $43,266,311.62 29‐Mar‐13 A RW‐SW Support Projects
CUW36302 System Security Upgrades Complete $14,397,894. 00 19‐Apr‐19 A CUW38801 Programmatic EIR Complete $10,734,567.27 30‐Jun‐09 A CUW38802 Bioregional Habitat Restoration Closeout $93,341,983.01 30‐Dec‐27 CUW38803 Vegetation Restoration of WSIP Construction Sites Complete $2,111,545.75 30‐Jun‐16 A CUW38804 Long term Mitigation Endowment Not Applicable $12,000,000.00 24‐Dec‐26 CUW39201 Program Management Project Not Applicable $121,642,047.50 30‐Jun‐32 CUW39401 Watershed and Environmental Improvement Program Complete $20,079,149.69 30‐Jun‐22 A 14 APPENDIX C. LIST OF ACRONYMS
BART Bay Area Rapid Transit
BDPL Bay Division Pipeline
CIP Capital Improvement Program
CO Change Order
DB Design, Build
EBMUD East Bay Municipal Utility District
EIR Environmental Impact Report
FY Fiscal Year
HH Hetch Hetchy
HTWTP Harry Tracy Water Treatment Plant
LOS Levels of Service
MGD Million Gallons Per Day
N/A Not Applicable
NIT New Irvington Tunnel
NTP Notice to Proceed
PCCP Pre-stressed Concrete Cylinder Pipe
PG&E Pacific Gas and Electric Company
RGWSR Regional Groundwater Storage and Recovery
SCADA Supervisory Control and Data Acquisition
SFPUC San Francisco Public Utilities Commission
SSF South San Francisco
SVWTP Sunol Valley Water Treatment Plant
WSIP Water System Improvement Program