Cities Index.
Contract No. WW-704 Various Locations Sewer Replacement No. 9

CleanPowerSF Sfpuc Commission
June 24, 2025

Document
Contract No. WW-704 Various Locations Sewer Replacement No. 9
Meeting
June 24, 2025
Body
CleanPowerSF Sfpuc Commission
Pages
4
Original file
1.6 MB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

DEPARTMENT

Wastewater Enterprise

AGENDA NO.

10 MEETING DATE

June 24, 2025

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Calendar: Regular Calendar
Project Manager: Aileen Caylao

Accept Closeout, Approve Modification, and Authorize Final Payment for Contract No.

WW-704, Various Locations Sewer Replacement No. 9

Summary of Proposed
Commission Action:

Accept work performed by JDB and Sons Construction, Inc. , under Contract No. WW -704, Various Locations Sewer Replacement No. 9; approve Modification No. 4 (Final) decreasing the contract amount by $10,750 for a total contract amount of $3,637,491 and increas ing the contract duration by 11 calendar days for a total contract duration of 785 consecutive calendar days (approximately two years and three months), to adjust the final contract amount to the value of actual contract quantities completed and adjust the final contract duration to complete pavement restoration work scope; and authorize final payment to the contractor.

Background: The San Francisco Public Utilities Commission (SFPUC) inspected the existing sewers on the subject streets listed below, which are located in the City and County of San Francisco,
and determined that SFPUC should
replace them.

On November 9, 2021, by Resolution 21- 0168, the Commission awarded Contract No. WW- 704, Various Locations Sewer Replacement No. 9, to JDB and Sons Construction, Inc. The original contract amount was $3,898,770 and original contract duration was 310 consecutive calendar days.

On August 8, 2023, by Resolution No. 23- 0142, the Commission approved an increase of 219 calendar days to the contract duration contingency, for a total contract duration limit of 560 consecutive calendar days, with no change to the contract amount.

On March 12, 2024, by Resolution 24-0058, the Commission approved an increase of 214 calendar days to the contract duration contingency, for a
total contract duration limit of 774 consecutive calendar days, with no change to the contract amount.

Scope of Contract: The contract work is within the City and County of San Francisco, and locations include:
• Francisco Street, from Stockton Street to Grant Street; • Hawthorne Street, from Howard Street to Folsom Street; Agenda Title: WW-704, Various Locations Sewer Replacement No. 9 Commission Meeting Date: June 24, 2025

Page 2 ends

• Federal Street, from 2nd Street to End of Street;
• Grove Street, from Scott Street to Divisadero Street; • Scott Street, from Hayes Street to Grove Street;
• Noe Street, from 16th Street/ Market Street to 17th Street; • Broderick Street, from Haight Street to Page Street;
• Page Street, from Baker Street to Lyon Street;
• Baker Street, from Haight to Page Street;
• Capp Street, from 21st Street to 22nd Street;
• 24th Street, from Chattanooga Street to Church Street; • California Street, from 22nd Avenue to 23rd Avenue; and • Cervantes Boulevard, from Bay Street/ Fillmore Street to Alhambra Street.

The contract work consists of:
• Replacing existing sewer with 2,508 feet of 12- inch diameter, 689 feet of 15 -inch diameter and 206 feet of 21 -inch diameter vitreous clay pipe, and
• Installing cured-in-place lining on 259 feet of existing 12- inch diameter sewers, 332 feet of existing 14- inch diameter sewers, and 551 feet of existing 18-inch diameter sewers.

Modifications to the
Contract:

Modification No. 1: Staff issued Modification No. 1 , increasing the contract duration by 250 calendar days , in accordance with Resolution No. 23-0142, to provide time for the Contractor to complete the remaining work scope due to shortage of available workforce , for a revised contract duration of 560 consecutive calendar days , with no change to the contract amount.

Modification No. 2: Staff issued Modification No. 2, increasing the contract amount by $59,125, within the original 10% contingency, and increasing the contract duration by 214 calendar days, in accordance with Resolution No. 24-0058, to coordinate with SFMTA overhead Muni lines support and to address unforeseen underground conditions encountered on Federal Street, for a revised contract amount of $3,957,895 and revised contract duration of 774 consecutive calendar days.

Modification No. 3: Staff issued Modification N o. 3 decreasing the contract amount by $309,654, within the original 10% contingency, to adjust actual quantities completed to date, for a revised contract amount of $3,648,241, with no change to the contract duration.

Proposed Modification No. 4 (Final): Staff recommends Commission authorization to decrease the contract amount by $10,750 1 and increase the contract duration by 11 calendar days, to adjust the final contract amount to the value of actual contract quantities completed and adjust the final contract duration to complete pavement restoration work scope, for a total Agenda Title: WW-704, Various Locations Sewer Replacement No. 9 Commission Meeting Date: June 24, 2025

Page 3 ends

contract amount of $3,637,49 and a total contract duration of 785 consecutive calendar days.

Funding and Costs: Funding Source: Wastewater Enterprise Renewal and Replacement Program, Public Works Street Resurfacing Program and Public Works Curb Ramp Program, Project No. 10035307,
Various Locations Sewer
Replacement No. 9
Original Contract Amount: $3,898,770
Original 10% Cost Contingency: $389,877
Modified Decreases to Contract Amount: ($250,529)
Total Current Contract Amount: $3,648,241
Recommended Modification No. 4 (Final) Amount: ($10,750) Total Revised Contract Amount: $3,637,491

Schedule: Notice-to-Proceed Date: April 18, 2022
Original Contract Duration: 310 consecutive calendar days Original 10% Duration Contingency: 31 calendar days
Approved Increase to Duration Contingency: 433 calendar days Modified Increases to Contract Duration: 464 calendar days Total Current Contract Duration: 774 consecutive calendar days Recommended Modification No. 4 (Final) Duration: 11 calendar days Total Revised Contract Duration: 785 consecutive calendar days

Local Business
Enterprise Utilization
and Non-
Discrimination in
Contracting:

The Contract Monitoring Division established a 20% Local Business Enterprise (LBE) subcontracting requirement for this contract. The contractor’s bid committed to a 21.05% LBE subcontractor participation with its bid submittal. The Contract Monitoring Division determined the contractor complied with its Local Business Enterprise subcontracting goal achieving a final subcontractor participation of 20.46%

Attachment(s): 1. Contract Monitoring Division Memorandum Agenda Title: WW-704, Various Locations Sewer Replacement No. 9 Commission Meeting Date: June 24, 2025

Page 4 ends

Project Location Map

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, On November 9, 2021, by Resolution No. 21- 0168, the Commission awarded Contract No. WW-704, Various Locations Sewer Replacement No. 9, to JDB and Sons Construction, Inc.; and

WHEREAS, The original contract amount was for $3,898,770 and the original contract duration was 310 consecutive calendar days; and

WHEREAS, The contract Notice-to-Proceed date was April 18, 2022; and

WHEREAS, On August 8, 2023, by Resolution No. 23- 0142, the Commission approved an increase of 219 calendar days to the existing contract duration contingency, for a total duration limit of 560 consecutive calendar days, with no change to the contract amount; and

WHEREAS, On March 12, 2024, by Resolution No. 24- 0058, the Commission approved an increase of 214 calendar days to the existing duration contingency for a total duration limit of 774 consecutive calendar days, to allow for possible modifications, with no change to the contract amount; and

WHEREAS, Modification Nos. 1- 3 cumulatively decreased the contract amount by $250,529 and increased the contract duration by 464 calendar days, to provide time for the Contractor to complete work scope coordination with San Francisco Municipal Transportation Authority overhead Muni lines support, address unforeseen underground conditions encountered on Federal Street and adjust actual quantities completed to date , for a total contract amount of $3,648,241 and a total contract duration of 774 consecutive calendar days; and

WHEREAS, Staff recommends the Commission approve Modification No. 4 (Final) to decrease the contract amount by $10,750 and increase the contract duration by 11 calendar days , for a total contract amount of $3,637,491 and a total contract duration of 785 consecutive calendar days, to adjust the final contract amount to the value of actual contract quantities completed and adjust the final contract duration to complete pavement restoration work scope ; and

WHEREAS, JDB and Sons Construction, Inc., completed the work scope under Contract No. WW-704, Various Locations Sewer Replacement No. 9; and

WHEREAS, The Contract Monitoring Division determined that the contractor complied with the established Local Business Enterprise (LBE) subcontracting participation of 20% for this contract by achieving a final LBE subcontractor participation of 20.46%; and

WHEREAS, Funds are available from Project No. 10035307, Various Locations Sewer Replacement No. 9; now, therefore, be it

RESOLVED, That this Commission hereby accepts the work performed by JDB and Sons Construction, Inc., under Contract No. WW -704, Various Locations Sewer Replacement No. 9; approves Modification No. 4 (Final), decreasing the contract amount by $10,750 and increasing the contract duration by 11 calendar days , for a total contract amount of $3,637,491 and a total contract duration of 785 consecutive calendar days ; and authorizes final payment to the contractor.

I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of June 24, 2025.

Director of Commission Affairs
San Francisco Public Utilities Commission
City & County of San Francisco
Daniel Lurie, Mayor
Office of the City Administrator
Carmen Chu, City Administrator

Contract Monitoring Division
Stephanie Tang, Director

1455 Market Street, Suite 16A, San Francisco, CA 94103
Telephone (415) 554 0630

MEMORANDUM

Date: May 9, 2025

To: Aileen Caylao, SFPUC

From: Jovi Cuntapay-Vitin, CMD

Subject: Closeout for WW-704 Various Locations Sewer Replacement No. 9 (PeopleSoft Contract ID: 1000024680)

The Contract Monitoring Division (“CMD”) has determined that JDB & Sons Construction, Inc. (“JDB”), the LBE prime contractor, has made a good faith effort to comply with the LBE subcontracting requirements associated with this project.

At the time the project was advertised, a LBE subcontracting participation requirement of 20% was established. At the time of bid, JDB’s Section 00 43 36 reflected a LBE subcontracting participation commitment of 21.05%. JDB was awarded the contract in the amount of $3,898,770.00. At closeout, the final contract amount is $3,637,490.70. JDB’s LBE subcontracting participation commitment is as follows:

Firm Scope of
Work LBE Status
Original
Credited
Contract
Participation
Final Credited
Contract Participation
Total Traffic
Control, Inc.

Traffic
Control
(Partial)

SF LBE-OBE
(Micro) 0.64% $69,016.00 1.90%
Roadway
Construction, Inc.

Asphalt
Partial

SF LBE-MBE
(Micro) 15.77% $519,847.96 14.29%
R&S
Construction
Management Inc.

Concrete
Partial

SF LBE-MBE
(Micro) 4.64% $155,481.75 4.27%
TOTAL 21.05% $744,345.71 20.46%

Pursuant to communications with JDB and as confirmed by the San Francisco Public Utilities Commission (“SFPUC”) staff, the descoping or reduction of scope by the SFPUC impacted the project’s overall LBE participation. Most of the bid items that were descoped/reduced were slated to be performed by the listed LBE subs. These are bid items are R-3, R-4, R-7, R-9, R- 10, R-11, R-13, R-18 and R-19.

Based on the foregoing, CMD concurs with the closeout of this contract.