Cities Index.
Contract No. WW-783

CleanPowerSF Sfpuc Commission
July 22, 2025

Document
Contract No. WW-783
Meeting
July 22, 2025
Body
CleanPowerSF Sfpuc Commission
Pages
3
Original file
587 KB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

DEPARTMENT

Infrastructure Division

AGENDA NO. 6a

MEETING DATE

July 22, 2025

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Calendar: Consent Calendar
Project Manager: Aileen Caylao

Award Contract No. WW-783, As-Needed Spot Sewer Replacement No. 47

Summary of Proposed
Commission Action:

Award Contract No. WW-783, As -Needed Spot Sewer Replacement No. 47, to the sole, responsible bidder that submitted a responsive bid, J. Flores Construction Company, Inc., in the amount of $11,378,108 and with a duration of 400 consecutive calendar days (approximately one year and one month) in accordance with the San Francisco Administrative Code section

6.23(c)(2), to replace sections of existing sewer pipes on an as-needed basis at locations that staff will determine throughout the City and County of San Francisco.

Background: The Sa n Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise requires contract services to address spot sewer replacement of localized sections of existing sewer lines, on short notice . The contract
services will cover the City and County of San Francisco at specific locations to be determined by staff over the contract duration.

Scope of Contract: The contract work consists of as -needed replacement of localized sections of existing sewer lines, on short notice, at locations to be determined, within the City and County of San Francisco.

Funding and Costs: Funding Source: SFPUC Wastewater Enterprise Renewal and Replacement Program, Project No. 10041684, As -Needed Spot Sewer Replacement No. 47

Engineer’s Estimate: $10,600,000
Award: $11,378,108

Schedule: Estimated Notice-To-Proceed Date: September 2025 Estimated Completion Date: August 2026
Contract Duration: 400 consecutive calendar days (approximately one year and one month)

Bid History:

Advertised: March 7, 2025

Bids Received: On April 3, 2025, the SFPUC received and publicly opened one sealed bid as follows:

Agenda Title: WW-783, As-Needed Spot Sewer Replacement No. 47 Commission Meeting Date: July 22, 2025

Page 2 ends

Bid Rank &
Firm
Base Bid
Amount
LBE Bid
Discount
Adjusted Bid
with LBE
Discount
Final
Rank

1. J. Flores
Construction
Company,
Inc.
$11,378,107.50 2% $11,150,545.35 1

Application of bid preferences in accordance with Chapter 14B of the San Francisco Administrative Code did not change the final ranking of the low bidder.

Outreach: SFPUC staff conducted extensive outreach during the contract advertisement period and after the bid date. Based on the results, the General Manager determined that
neither additional outreach efforts, nor
modification of requirements in the c ontract, would likely result in more than one bid at bid prices substantially lower than the bid price received if SPFUC were to re-advertise this contract.

Negotiations with the
Sole Bidder:

Post-Bid Survey and Reasons for Negotiations:

Under San Francisco Administrative Code section 6.23(c)(2), when the SFPUC advertises a public work project in accordance with the required procedures and receives only one responsive bid, and the bid exceeds the Engineer’s Estimate, the Department Head shall determine:

1. Whether outreach efforts would result in more than one bid; and

2. Whether removal or modification of certain requirements in the contract would result in more than one bid.

If the SFPUC concludes that neither step is likely to result in more than one bid at prices substantially lower than the bid price received, then the Commission may authorize the General Manager to negotiate with the sole bidder or any qualified contractor.

SFPUC staff conducted the following reviews to determine whether more than one bid would likely result in more than one bid at prices substantially lower than the bid price received:

1. Whether outreach efforts would result in more than one bid

Staff sent email notifications to 113 individual contacts, as well as advertising the contract as an upcoming contract on the SFPU C Contractors Assistance Center’s website during the contract advertisement period. Post bid, Staff contacted firms on the Plan Holders List and the interested parties list. One of the firms who responded stated to Staff that they were unlikely to submit a Agenda Title: WW-783, As-Needed Spot Sewer Replacement No. 47 Commission Meeting Date: July 22, 2025

Page 3 ends

Due to the nature of the as-needed contract, there is no accompanying Location Map. competitive bid for the nature of the work. Three firms indicated a current high volume of work within their company with limited resource capacity and elected not to submit a bid for this contract.

2. Whether removal or modification of certain requirements in the contract would result in more than one bid.

The requirements in the contract documents are needed in order to perform and complete the urgent sewer replacement work in a timely manner and in compliance with the WWE’s requirements.

Under these circumstances, the General Manager concluded that re - advertising the contract would not result in more than one bid at a substantially lower price than the present bid.

Environmental
Review:

Award of this as -needed contract does not constitute a “project” under the California Environmental Quality Act (CEQA) Guidelines section 15378 because it does not involve commitment to any specific project that may result in a physical change in the environment. Staff will not authorize the contractor to commence any work under this contract until the proposed work is reviewed and any appropriate environmental review under the CEQA, if required, has been completed.

Local Business
Enterprise Utilization
and Non-
Discrimination in
Contracting:

The Contract Monitoring Division established a n 8% Local Business Enterprise (LBE) subcontracting requirement for this contract. J. Flores Construction Company, Inc. , committed to a n 8.09% LBE subcontractor participation with its bid submittal.

Attachment(s): 1. Contract Monitoring Division Memorandum

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) needs to perform as-needed replacement of localized sections of existing sewer lines, on short notice, at locations to be determined by Wastewater Enterprise staff throughout the City and County of San Francisco and procured this contract to perform the work in a cost -effective and time -efficient manner; and

WHEREAS, On March 7, 2025, SFPUC advertised Contract No. WW-783, As-Needed Spot Sewer Replacement No. 47; and

WHEREAS, The Engineer’s Estimate is $10,600,000 for this construction work; and

WHEREAS, The contract duration is 400 consecutive calendar days; and

WHEREAS, On April 3, 2025, SFPUC received and publicly opened one sealed bid; and

WHEREAS, In accordance with San Francisco Administrative Code section 6.23(c)(2), SFPUC staff conducted extensive outreach during the contract advertisement period and after the bid date. Based on the results, the General Manager determined that neither additional outreach efforts, nor modification of requirements in the contract, would not likely result in more than one bid at bid prices substantially lower than the bid price received if SFPUC was to re -advertise this contract; and

WHEREAS, SFPUC staff and the Contract Monitoring Division (CMD) review ed the bids and the application of bid preferences and have determined that J. Flores Construction Company, Inc., is the sole responsible bidder that submitted a responsive bid; and

WHEREAS, The CMD established an 8% Local Business Enterprise (LBE) subcontracting participation requirement for this contract, and J. Flores Construction Company, Inc., committed to 8.09% LBE subcontractor participation in its bid submittal; and

WHEREAS, Award of this as -needed contract does not constitute a “project” under the California Environmental Quality Act (CEQA) Guidelines section 15378 because it does not involve commitment to any specific project that may result in a physical change in the environment and Staff will not authorize the contractor to commence any work under this contract until the proposed work is reviewed and any appropriate environmental review under the CEQA, if required, has been completed; and

WHEREAS, Funds are available from Project No. 10041684, As-Needed Spot Sewer Replacement No. 47; now, therefore, be it

RESOLVED, That this Commission hereby awards Contract No. WW-783, As-Needed Spot Sewer Replacement No. 47 , in the amount of $11,378,108, and with a duration of 400 consecutive calendar days , to the sole responsible bidder that submitted a responsive bid, J.

Flores Construction Company, Inc.

I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of July 22, 2025.

Director of Commission Affairs
San Francisco Public Utilities Commission
City & County of San Francisco
Daniel Lurie, Mayor
Office of the City Administrator
Carmen Chu, City Administrator

Contract Monitoring Division
Stephanie Tang, Director

MEMORANDUM

Date: May 9, 2025

To: Aileen Caylao, SFPUC

From: Jason Chow, CMD

Subject: CMD Review of Bids Submitted on 4/3/2025 for WW-783 As-Needed Spot Sewer Replacement No. 47

J Flores Construction Co. (“JFlores”) is the sole/responsive bidder on this contract

The bid discount was applied to bidders who are certified by the Contract Monitoring Division, (“CMD”) as an LBE in the type of work that is specified for the bidder by the Contract Awarding Authority. [Sec. 14B.7(D)]

Bidder

LBE Status, Type
and Size

Base Bid
Bid Discount
Adjusted Bid
with
Bid Discount
J. Flores Construction Co. SF LBE-OBE (Small) $11,378,107.50

2% $11,150,545.35

J. Flores Construction Co. (“JFlores”) satisfactorily demonstrated how they will meet the LBE subcontractor participation requirement.

A combination of Micro-LBE and Small-LBE participation will count toward LBE subcontractor participation compliance. JFlores’ commitment for this contract:

Requirement % Commitment %

Micro/Small LBE 8.00% 8.09%

In their bid, JFlores listed the following subcontractors on this contract.

Supplier Name Scope of Work

LBE

LBE Size

LBE
Percent

Percent
Of
Work
Amount
B & G Transportion Inc

Trucking (Various SW
Items) (Partial)

SF-LBE Micro 100%

5.45%

$620,000

Sullivan's Concrete
Sawing

Sawcut (Various SW
Items) (Partial)

SF-LBE Micro 100% 1.10% $125,000

Esquivel Grading &
Paving, Inc.

SW-31 (Partial); SW-
32 (Partial), SW-48
(Partial)

SF-LBE Small 100% 1.54%

$175,500

SAK Construction

SW-03A (Partial), SW-
24, SW-25, SW-26,
SW-27, & SW-38, SW-
39 1.72% $194,850

H & R Plumbing and
Drain Cleaning, Inc.

SW-03A (Partial), SW-
40 0.30% $34,600

SFPUC utilizes SOLIS system. For SOLIS, the LBE credited percentages are listed below:

LBE Subcontractor LBE Status Listed Amount LBE Credited Participation
Amount
LBE Credited
Participation
Percentage
B & G Transportion Inc

SF LBE-OBE (Micro)
$620,000

$620,000

5.45%
Sullivan's Concrete
Sawing

SF LBE-OBE (Micro) $125,000

$125,000

1.10%
Esquivel Grading &
Paving, Inc.

SF LBE-MBE (Small)
$175,500

$175,500

1.54%
TOTAL $920,500.00 $920,500.00 8.09%

JFlores satisfied the “Good Faith Efforts” requirement.

JFlores utilized Approach A and exceeded the LBE subcontractor participation requirement by 35%.

CMD finds JFlores is responsive to pre-award requirements of Chapter 14B. Once awarded, the contract will be monitored for compliance with the LBE subcontractor participation commitment, as well as other 14B requirements.

Primary CMD contact for the contract: Jason Chow, [email protected]

CMD must be contacted immediately for:
- Subcontractor addition/substitution;
- Contract modification that cumulatively increases the original contract value by 20%; - Prompt payment issues;
- Any other issues pertaining to LBE subcontractor participation

Noncompliance may result in penalties, including monetary fines. Please communicate with CMD early.

[JC]