Cities Index.
ppgQy (Q Wastewater Enterprise Quarterly Report (Q4 FY 2024-25

CleanPowerSF Sfpuc Commission
September 23, 2025

Document
ppgQy (Q Wastewater Enterprise Quarterly Report (Q4 FY 2024-25
Meeting
September 23, 2025
Body
CleanPowerSF Sfpuc Commission
Original file
3.2 MB
Text extracted from the CCA's file for reading and search. Open the original on sfpuc.sharefile.com. That file is the official record.

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

Wastewater Capital Programs Quarterly Report
Q4 Fiscal Year 2024-2025 (April 2025 – June 2025)
Bessie Tam, Wastewater Capital Programs Director, Infrastructure Presented to the San Francisco Public Utilities Commission September 23, 2025
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

Construction Updates
2 Anticipated Completion:

Fall 2025
Sunnydale Pump Station
Safety Improvements
(WW-755)

Southeast Plant Power Feed and
Primary Switchgear Upgrades
(WW-662R)
Anticipated Completion:

Summer 2027
Anticipated Completion:

Spring 2028
Geary Blvd Sewer and Water
Improvements
(WW-743)
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

SSIP Phase 1 Status
3 PROJECTS BY PHASE
(as of March 2025)
Planning
$22M
(1 Project)
Phase 1
$4.707M
(70 Projects)
Design
$76M
(3 Projects)
Completed
$570M
(54 Projects)
Construction
$3,885M
(7 Projects)
Bid & Award
$0
(0 Projects)
Closeout
$42M
(3 Projects)
Multi-Phases
$112M
(2 Projects)

75.7% Complete

PROJECTS BY PHASE
(as of June 2025)
Planning
$22M
(1 Project)
Phase 1
$4.707M
(70 Projects)
Design
$76M
(3 Projects)
Completed
$570M
(54 Projects)
Construction
$3,885M
(7 Projects)
Bid & Award
$0
(0 Projects)
Closeout
$42M
(3 Projects)
Multi-Phases
$112M
(2 Projects)

76.5% Complete
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

SSIP Status – Cost Summary
4 Section I.3 SSIP
Table 3
Negative numbers reflect cost increases
Subprograms (includes other SSIP)
Expenditures to
Date
($ Million)
(A)
Current
Approved
Budget
($ Million)
(B)
Current
Forecasted
Budget
($ Million)
(C)
Cost Variance
($ Million)
(D = B - C)
Cost Variance
Over Reporting
Period ($ Million)
(E)
Treatment Facilities $3,167.2 $6,202.1 $6,356.6 ($154.6) $1.5 Collection System $344.1 $611.5 $611.5 ($0.0) 0.0
Stormwater Management $120.9 $343.5 $342.8 $0.7 0.0
Flood Resilience Projects $74.1 $766.0 $810.0 ($44.0) 0.0 Land Reuse Projects $85.6 $88.9 $88.9 $0.0 0.0
Program Management (PM) $182.6 $340.0 $340.0 $0.0 0.0
Overall Program Total $3,974.5 $8,351.8 $8,549.7 ($197.9) $1.5 SSIP Phase 1 Total $3,769.5 $4,707.4 $4,869.5 ($162.1) $0.0 Other SSIP Subtotal
(Phase 2 and 3 priorities)
$205.0 $3,644.4 $3,680.2 ($35.8) $1.5
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

Facilities and Infrastructure Status – Cost Summary
5 Section II.3 F&I Program
Table 3
Subprograms
Expenditures to
Date
($ Million)
(A)
Current
Approved
Budget
($ Million)
(B)
Current
Forecasted
Budget
($ Million)
(C)
Cost
Variance
($ Million)
(D = B - C)
Cost Variance
Over Reporting
Period
($ Million)
(E)
Facilities and Infrastructure Program $207.8 $484.3 $471.6 $12.6 $15.6 SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

Projects Initiated

1. Dechlorination Process (NPF 500) Evaluation & Interim Rehabilitation
Planning Milestones

2. Conceptual Engineering Report: Sedimentation (NPF 040/041) Tanks Condition Improvement

3. Combined Needs Assessment and Alternative Analysis Report:

Systemwide CSD & T/S Monitoring Equipment Assessment
Design Milestones (35%, 95% or 100%)

4. Biosolids Digester Facilities Project – Biogas subproject

5. SEP Condition Improvement Projects – Part 1

6. Pump Station Security Upgrades (Cesar Chavez, Griffith Station, Channel Station, Merlin Morris Station)

7. Solids Thickening (OSP 011) Process Upgrades

8. OSP Plant-wide Ventilation (HVAC) Upgrades
Advertised & Received Bids

9. SEP 550 Booster PS Condition Inspection & Interim – Construction contract

10. Brannan Outfall 19 Discharge/Baffle Rehab & Sansome Outfall 15 Valve: Brannon St. Outfall (Contract A)

11. CSD Structure Rehab & Upgrades – Part 1 – Mariposa, Evans and Lake Merced (Contract C)
6 Section I.5 SSIP
Budget and Schedule Summary
Construction Contracts Awarded

12. Large Diameter Sewer Projects and Channel FM Intertie – West SOMA, Panhandle, and Inner Sunset Sewer
Improvements

13. CSD Structure Rehab & Upgrades – Part 1 – Laguna, Howard, and Mission Creek CSD (Contract A/B)

14. Green Infrastructure Grant Program – Panorama Elementary School
Construction Notice to Proceed

15. Seacliff No. 2 Pump Station & Force Main Upgrade

16. Buchanan Street Mall

17. SEP New Headworks (Grit) Replacement – Scope IV
Substantial Completion/Completed

18. North Shore Wet Weather Pump Station Improvements and Disinfection

19. Geary Underpass Pump Station Safe Access Enhancements

20. Taraval Sewer Improvements – Contract C 19th Avenue Sewer Milestones Achieved During the Quarter
SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

Southeast Plant Biosolids Digester Facilities Project
7 Planning through Bid & Award Construction Close Out
Project Schedule:

Forecast Budget: $2,837M
Progress and Status:
• Biosolids Digester Facilities construction continues with:
o Installation of mechanical, electrical, and plumbing work; process piping equipment at the digesters; solids
pretreatment/dewatering facilities;
o Interior and exterior architectural finishes are underway. o Concrete work and under slab installations for the
thermal hydrolysis equipment, steam generation and
digester cooling towers are in place.
o Coordination for functional testing, facility start-up and commissioning are in progress.
• For the Biogas Utilization Facility, the 35% Design package is complete.
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.

Southeast Plant New Headworks Facility Project
Forecast Budget: $717M
Progress and Status:
• New Headworks Facility work continues to proceed towards Final Completion:
o Testing for the fine screen handling, odor control, security, and fire alarm system is nearing completion.
o Southeast Plant site-scape and Evans Avenue
streetscape were completed.
o Elevators were certified by CA OSHA.
• Demolition of the former Headworks Building (SEP 012) is underway. 8
Planning through Bid & Award Construction Close Out
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029
Project Schedule:

SEWER SYSTEM IMPROVEMENT PROGRAM | Grey. Green. Clean.