DEPARTMENT

Infrastructure Division

AGENDA NO.

10 MEETING DATE

November 10, 2025

AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

Calendar: Regular Calendar
Project Manager: Jignesh Desai

Accept Closeout, Approve Modification, and Authorize Final Payment for Contract No.

WW-685R, North Shore Pump Station Wet Weather Improvements

Summary of Proposed
Commission Action:

Accept work performed by Western Water Constructors, Inc. , under Contract No. WW-685R, North Shore Pump Station Wet Weather Improvements; approve Modification No. 19 (F inal) increasing the contract duration by 249 calendar days , for a total contract duration of 1,664 consecutive calendar days (approximately four years and six months), due to delays associated with the cutover and controls testing of existing assets and newly installed assets, with no change to contract amount; and authorize final payment to the contractor.

Background: The objective of San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise Contract No. WW-685R, North Shore Pump Station Wet Weather Improvements project , is to provide redundant effluent pumping capacity at North Shore Pump Station during wet weather. This project replaced the four existing dry weather pumps with larger capacity units so that they are capable of redundant pumping capacity during wet weather. The project also included upgrades to the motor control centers and distributed cont rol system. The implementation of this project will ensure reliable and efficient operation in keeping with the level of service and maintain regulatory compliance.

The w ork also include s improvements to the heating, ventilation, and air conditioning ( HVAC), Mechanical, Fire Protection, Electrical, and Architectural systems for Building 930, D istributed Control S ystem Server Room at the Southeast Water Pollution Control Plant.

On January 26, 2021 by Resolution No. 21- 0006, this Commission awarded Contract No. WW- 685R, North Shore Pump Station Wet Weather Improvements, to Western Water Constructors, Inc. The original contract amount was $26,010,000, and the original c ontract duration was 750 consecutive calendar days.

On January 10, 2023, by Resolution No. 23-0010, this Commission approved an increase of 250 calendar days to the duration contingency, for a total
duration limit of 1,075 calendar days, with no change to the contract amount.

On January 23, 2024, by Resolution No. 24-0016, this Commission approved Agenda Title: WW-685R, North Shore Pump Station Wet Weather Improvements Commission Meeting Date: November 10, 2025

Page 2 ends

an increase of 340 calendar days to the duration contingency , for a total duration limit of 1 ,415 consecutive calendar days , with no change to the contract amount.

Scope of Contract: The contract work is located at the North Shore Pump Station and Southeast Water Pollution Control Plant within the City and County of San Francisco.

The contract work included:

At North Shore Pump Station:
• Replacement of four dry weather pumps;
• Replacement and extension of discharge piping, select portions of 36” headers, and associated mechanical equipment;
• Upgrade of the existing dewatering system;
• Upgrades of the Ferrous chloride systems;
• Replacement of east and west channel bar screens;
• Installation of City-furnished hydraulic actuators;
• Modernization of personnel elevator;
• Upgrades to the HVAC;
• Structural upgrades for dry weather pumps, piping, ferrous chloride tank pads, and other mechanical appurtenances;
• Lighting replacement and upgrades;
• Reroofing;
• Instrumentation and Control work including Distributed Control System installation and integration;
• Electrical upgrades including motor control center modification and replacement, emergency radio communication work;
• Site grading and paving; and,
• Sewer lateral installation.

At the Southeast Water Pollution Control Plant:
• Furnished and installed HVAC split system;
• Furnished and installed uninterruptable power source and distribution panel;
• Fire protection work; and,
• Associated architectural work.

Modifications to the
Contract:

Modification No s. 1 -18: Staff issued Modification Nos. 1 thr ough 18, increasing the c ontract amount by $1,834,063, within the original 10% cost contingency, and increasing the contract duration by 665 calendar days, in accordance with Resolution Nos. 23-0010 and 24-0016, to account for supply chain delays associated with the wet weather pumps and delays associated with motor control center installation and testing, for a revised contract amount of $ 27,844,063 and revised contract duration of 1,415 Agenda Title: WW-685R, North Shore Pump Station Wet Weather Improvements Commission Meeting Date: November 10, 2025

Page 3 ends

consecutive calendar days.

Recommended Modification No. 19 (Final): Staff recommends Commission approval of Modification No. 19 (Final) to increase the contract duration by 249 calendar days , for a total c ontract duration of 1,664 consecutive calendar days , to complete the cutover and controls testing of existing assets and newly installed assets , with no change to the contract amount.

Funding and Costs: Funding Source: Wastewater Enterprise Capital Program , Project No. 10026822, North Shore Pump Station Wet Weather Improvements Original Contract Amount: $26,010,000
Original 10% Cost Contingency: $2,601,000
Modified Increases to Contract Amount: $1,834,063
Approved Increase to Cost Contingency: $0
Total Current Contract Amount: $27,844,063
[Proposed] Modification No. 19 (Final) Amount: $0
Total Proposed Final Contract Amount: $27,844,063

Schedule: Notice-to-Proceed Date: April 19, 2021
Original Contract Duration: 750 consecutive calendar days Original 10% Duration Contingency: 75 calendar days
Approved Increase to Duration Contingency: 590 calendar days Modified Increases to Contract Duration: 665 calendar days Total Current Contract Duration: 1,415 consecutive calendar days [Proposed] Modification No. 19 (Final) Duration: 249 calendar Days Total [ Proposed] Final Contract Duration: 1,664 consecutive calendar days

Local Business
Enterprise Utilization
and Non-
Discrimination in
Contracting:

The Contract Monitoring Division established a n 11% Local Business Enterprise (LBE) subcontracting requirement for this c ontract. The contractor committed to a n 11.67% LBE subcontractor participation with its bid submittal. The Contract Monitoring Division determined the contractor complied with its Local Business Enterprise subcontracting requirement by achieving a final subcontractor participation of 11.57%.

Attachment(s): 1. Contract Monitoring Division Memorandum Agenda Title: WW-685R, North Shore Pump Station Wet Weather Improvements Commission Meeting Date: November 10, 2025

Page 4 ends

Northshore Pump Station and Southeast Water Pollution Control Plant

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise initiated the North Shore Pump Station Wet Weather Improvements project to provide redundant effluent pumping capacity at North Shore Pump Station during wet weather. This project replaced the four existing dry weather pumps with larger capacity units so that they are capable of redundant pumping capacity during wet weather. The project also include d upgrades to the motor control centers and distributed control system. The implementation of this project will ensure reliable and efficient operation in keeping with the level of service and maintain regulatory compliance; and

WHEREAS, On January 26, 2021, by Resolution No. 21-0006, this Commission awarded Contract No. WW -685R, North Shore Pump Station Wet Weather Improvements , to Western Water Constructors, Inc.; and

WHEREAS, The original c ontract amount was $26,010,000 and the original c ontract duration was 750 consecutive calendar days; and

WHEREAS, The contract Notice-to-Proceed date was April 19, 2021; and

WHEREAS, On January 10, 2023, by Resolution No. 23- 0010, this Commission approved an increase of 250 calendar days to the existing duration contingency, for a total duration limit of 1,075 calendar days, with no change to the contract amount; and

WHEREAS, On January 23, 2024, by Resolution No. 24- 0016, this Commission approved an increase of 340 calendar days to the existing duration contingency for a total duration limit of 1,415 calendar days, with no change to the contract amount; and

WHEREAS, Modification Nos. 1 through 18 cumulatively increased the contract amount by $1,834,063, within the original 10% cost contingency, and increased the contract duration by 665 calendar days , in accordance with Resolution Nos. 23- 0010 and 24- 0016, to account for supply chain delays associated with the wet weather pumps and delays associated with motor control center installation and testing, for a revised contract amount of $ 27,844,063 and revised contract duration of 1,415 consecutive calendar days; and

WHEREAS, Staff recommends this Commission approve Modification No. 19 (Final) to increase the contract duration by 249 calendar days , for a total c ontract duration of 1,664 consecutive calendar days , to complete the cutover and controls testing of existing assets and newly installed assets, with no change to the contract amount; and

WHEREAS, Western Water Constructors, Inc., has completed the work scope under Contract WW-685R, North Shore Pump Station Wet Weather Improvements; and

WHEREAS, The Contract Monitoring Division determined that the contractor complied with the established Local Business Enterprise subcontracting requirement of 11% for this contract by achieving a final Local Business Enterprise subcontractor participation of 11.57% ; and

WHEREAS, Funds are available from 10026822, North Shore Pump Station Wet Weather Improvements, now, therefore, be it

RESOLVED, That this Commission hereby accepts the work performed by Western Water Constructors, Inc., under Contract No. WW-685R, North Shore Pump Station Wet Weather Improvements; approves Modification No. 19 (Final) increasing the contract duration by 249 calendar days, with no change to the contract amount, for a total contract amount of $27,844,063, and a total contract duration of 1,664 consecutive calendar days ; and authorizes final payment to the Contractor.

I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of November 10, 2025.

Director of Commission Affairs
San Francisco Public Utilities Commission

MEMORANDUM

Date: October 8, 2025

To: Mazin Hijazi, SFPUC
Erika Heineken, SFDPW

From: Jovi Cuntapay-Vitin, CMD

Subject: Closeout for WW-685R North Shore Pump Station Wet Weather Improvements (PeopleSoft Contract ID: 1000021055)

The Contract Monitoring Division (“CMD”) has determined that Western Water Constructors, Inc. (“Western Water”), the prime contractor, has made a good faith effort to comply with the LBE subcontracting requirements associated with this project.

At the time the project was advertised, an LBE subcontracting participation requirement of 11% was established. Western Water’s Section 00 43 36 reflected an LBE subcontracting participation of 11.67%.

Western Water was awarded the contract in the amount of $28,610,000.00. At closeout, the final contract amount is $27,844,062.81. Western Water’s Micro/Small LBE subcontracting participation is as follows:

Firm
LBE Status,
Type and
Size
Scope of Work
Original
Credited
Contract
Participation
Final Credited
Contract Participation
Bay Engineering,

LLC SF LBE-
OBE
(Micro)
Demo, Process
Mechanical,
Equipment
Mechanical
(partial)

9.27% $2,658,188.91 9.55%
Favour PC SF LBE-
OBE
(Micro)
Electrical (partial) 1.26% $365,020.00 1.31%
Ronald R. Nelson
Contractor, Inc.

SF LBE-
OBE
(Micro)
Concrete (partial) 1.14% $161,078.55 0.58%
R&S Construction
Management Inc

SF LBE-
MBE (Micro) Concrete (partial) - $36,116.22 0.13%
TOTAL 11.67% $3,220,403.68 11.57%

To make up the shortfall and to maximize LBE subcontracting participation, Western Water added an LBE firm (R&S Construction Management, Inc.) for the remaining concrete work and maintain the committed LBE participation.

Based on the foregoing, CMD concurs with the closeout of this contract. Should you have any questions, please contact me at [email protected].

City & County of San Francisco
Daniel L. Lurie, Mayor
Office of the City Administrator
Carmen Chu, City Administrator

Contract Monitoring Division
Regina Chan, Director

← All documents from this meeting