Contract/Project Manager: Ilan Fussman
Approve Amendment No. 2 to Contract No. CS-1253, Power Optimization Tool
Summary of Proposed
Commission Action:
Approve Amendment No. 2 to Contract No. CS-1253, Power Optimization Tool, with NextEra Analytics Solutions, LLC , increasing the contract amount by $1,636,512, for a total not -to-exceed contract amount of $2,524,512, with no change to the contract duration of three years , for continued compliance with the California Independent System Operator ’s energy market rules and additional critical battery optimization tools and software for six additional CleanPowerSF battery storage facilities .
Background: The San Francisco Public Utilities Commission ’s (SFPUC) CleanPowerSF program currently has power supply contracts with six large battery storage facilities and plans to explore future contracts to support reliable energy service and comply with regulatory requirements . The batter y storage facilities are owned and operated by different vendors, and charge during solar energy producing hours so they can provide clean energy when CleanPowerSF’s customers and the grid need it most . The California Independent System Operator ( CAISO) mandates that a certain amount of energy be provided by C leanPowerSF to ensure the reliability of the California electric grid and will fine CleanPowerSF if that energy is not available as required.
Battery optimization software is required to develop and submit power supply bids for CleanPowerSF's battery storage facilities. This software is necessary due to the analytical complexity of charging and discharging across different timescales (hourly, 15- minutes and 5- minutes) into the CAISO’s energy markets as required by the CAISO ’s Tariff. The software integrates with third party assets, and must be compliant with the underlying power supply contract’s operating instructions , the CAISO’s Business Practice Manuals, and applicable l aw.
On February 12, 2025, under the authority delegated to the General Manager by Resolution No. 24-0185, the General Manager awarded Contract No. CS- 1253, Power Optimization Tool, to NextEra Analytics Solutions, LLC, with an amount not-to-exceed $628,560, and with a duration of three years.
Scope of Contract: Under this battery optimization software agreement, the contractor provides:
Agenda Title: CS-1253, Power Optimization Tool
Commission Meeting Date: February 24, 2026
• Hardware implementatio n and training services and for the NextEra 360 ™ Energy Management Software as a Service;
• Optimization of solar and battery storage facilities ; and, • Coordination with the battery storage facility owner and SFPUC’s Scheduling Coordinator.
Amendments to the
Contract:
Amendment No. 1: On September 15, 2025, under the authority delegated to the General Manager by Resolution No. 24-0185, the General Manager approved Amendment No. 1, increasing the contract amount by $259,440, to provide battery optimization tool software and services for one additional battery storage facility , increasing the total not -to-exceed total contract amount to $888,000, with no change to the contract duration of three years.
Proposed Amendment No. 2: Staff is seeking Commission authorization to increase the contract by $1,636,512, to provide battery optimization tool software and services for up to six additional battery storage facilities for a total of nine facilities that may be optimized with the tool, and include an as-needed one-time Scheduling Coordinator fee, if the SFPUC changes its Scheduling Coordinator for the battery storage facilities, increasing the total not-to-exceed contract amount of the contract to $2,524,512, with no change to the contract duration of three years.
Funding and Costs: Funding Source: CleanPowerSF Operating Fund
Original Not-to-Exceed Amount: $628,560
Amendment No.1 Amount: $259,440
Proposed Amendment No.2 Amount: $1,636,512
[Proposed] Total Not-To-Exceed Contract Amount: $2,524,512
Schedule: Original Duration: three years
Amendment No. 1 Duration: no change
Proposed Amendment No. 2 Duration: no change
Total Duration: three years
Environmental
Review:
This action does not constitute a project under the California Environmental Quality Act Guidelines Section 15378 because there would be no physical change in the environment.
Local Business
Enterprise Utilization
and Non-
Discrimination in
Contracting:
The Contract Monitoring Division waived the Local Business Enterprise (LBE) subcontracting requirement for this contract.
Attachment: None
PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO.
WHEREAS, The San Francisco Public Utilities Commission (SFPUC) requires the services of a qualified contractor to provide battery optimization software that is necessary to develop and submit bids for CleanPowerSF's battery storage facilities into the California Independent System Operator (CAISO) operated energy markets in compliance with CAISO Tariff. The software integrates with third party battery storage facilities , and must be compliant with the underlying power supply contract’s operating instructions , CAISO’s Business Practice Manuals, and applicable law; and
WHEREAS, On February 12, 2025, under the authority delegated by Resolution No. 24- 0185, the General Manager awarded Contract No. CS -1253, Power Optimization Tool for compliance the California Independent System Operator ’s energy market rules , to NextEra Analytics Solutions, LLC , in an amount not-to-exceed $628,560, and with a duration of three years, to provide battery optimization tool software and services to optimize solar and battery storage facilities , with NextEra Analytics Solutions, LLC ; and
WHEREAS, On September 15, 2025, under the authority delegated by Resolution No. 24- 0185, the General Manager approved Amendment No. 1, increasing the contract amount by $259,440, to provide battery optimization tool software and services for one additional battery storage facility, increasing the total not -to-exceed total contract amount to $888,000, with no change to the contract duration; and
WHEREAS, Staff recommends this Commission approve Amendment No. 2 to Contract No. CS-1253, Power Optimization Tool, to increase the contract amount by $1,636,512, to add up to six additional battery storage facilities for optimization, and a one-time scheduling coordinator change fee, if necessary , for a total not -to-exceed amount of $2,524,512, with no change to the contract duration; and
WHEREAS, The Contract Monitoring Division waived the Local Business Enterprise (LBE) subcontracting requirement for this contract; and
WHEREAS, This action does not constitute a project under the California Environmental Quality Act Guidelines Section 15378 because there would be no physical change in the environment; and
WHEREAS, Funds for these contracts are available from CleanPowerSF Operating Fund, now, therefore, be it,
RESOLVED, That this Commission hereby approves Amendment No. 2 to Contract No.
CS-1253, Power Optimization Tool , with NextEra Analytics Solutions, LLC , to continue providing battery optimization tool software and services, for up to six additional batter y storage facilities , and a one-time scheduling coordinator change fee, if necessary, increasing the contract
by $1,636,512 with no change to the contract duration, for a total not -to-exceed contract amount of $ 2,524,512, and a total duration of three years .
I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of February 24, 2026.