AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

DEPARTMENT: Infrastructure Division

AGENDA NUMBER: 10
MEETING DATE: May 26, 2026

Calendar: Regular Calendar
Project Manager: Barbara Palacios

Approve Increase to the Duration Contingenc y for Contract No. WD -2895, San Francisco Zoo Recycled Water

Summary of
Proposed
Commission
Action:

Approve an increase of 360 calendar days to the existing duration contingency for Contract No. WD-2895, San Francisco Zoo Recycled Water, with Basset Engineering, for a revised duration limit of 1,030 consecutive calendar days (approximately two years and ten months ), with no change to the contract amount , to allow for the completion of the San Francisco Zoo Recycled Water P roject, which is delayed due to the additional time required for manufacturing and procurement of long- lead electrical power metering equipment.

Background: The San Francisco Public Utilities Commission (SFPUC) is building a recycled water facility to serve the San Francisco Zoo (Zoo) and the Lower Great Highway to support water conservation efforts. The Zoo currently relies on groundwater pumped from the Westside Groundwater Basin to supply various non- potable demands such as landscape irrigation, animal exhibit washdown, and impoundment and animal pool filling. The Lower Great Highway also relies on this groundwater for landscape irrigation.

The San Francisco Zoo Recycled Water Project (Project) mainly consists of the construction of a new recycled water pipeline, and mechanical and electrical appurtenances, in the public right -of-way to the groundwater reservoir and pump station facility that is owned and operated by the San Francisco Recreation and Parks Department . The Project will convert the Lower Great Highway’s and Zoo’s current use of groundwater supply to recycled water supply from the SFPUC Westside Recycled Water Treatment Facility, except for end uses that require potable water (such as drinking water for animals). Supplying these demands with recycled water will offset close to 100% of the Lower Great Highway’s and Zoo’s annual groundwater use and will conserve high quality groundwater to supplement potable water supplies in San Francisco. Approximately 200,000 gallons of groundwater each day will be offset by recycled water through this Project.

On February 13, 2024, by Resolution No. 24- 0027, the Commission awarded Contract No. WD -2895, San Francisco Zoo Recycled Water , to Basset Engineering, in the amount of $2,175,723 and with a duration of Agenda Title: WD-2895, San Francisco Zoo Recycled Water Commission Meeting Date: May 26, 2026

Page 2 ends

Scope of
Contract:

The contract work location is in the City and County of San Francisco on Sloat Boulevard, West of Skyline Boulevard.

The contract work includes installation of:
• 1,600 feet of 6-inch to 8-inch diameter ductile iron pipe; • Concrete vaults for pipeline turnout valves and flow meters; • Ultrasonic water level sensors;
• Groundwater air-gap assembly;
• New recycled water and groundwater flow meters;
• Motor Control Center modifications, mini power station, industrial enclosures and socket meter; and
• Data communication and network equipment.

Modifications to
the Contract:

Modification No. 1: Staff issued Modification No. 1, increasing the contract amount by $35,599, within the original 10% contingency , for a total contract amount of $2,211,322, with no change to the contract duration, to furnish and install a temporary bypass pipeline to support testing and commissioning.

Proposed Increase to Duration Contingency: Staff recommends the Commission approve an increase of 360 calendar days to the existing duration contingency , for a new duration limit of 1, 030 consecutive calendar days, with no change to the contract amount, to allow for the completion of the Project, which is delayed primarily due to the additional time required for manufacturing and procurement of long- lead electrical equipment. In late 2025, it was determined that the specified electrical power station (which distributes, measures, and records power for project instrumentation and control panels ) was incompatible with the electrical meter to be provided and installed by the SFPUC
Power Enterprise.

Another compatible meter main load center was identified to resolve the issue; however, this component had an extended procurement lead time.

Concurrent with this electrical equipment delay , there were delays with the ongoing electrical and instrumentation and control work under the base contract. Following negotiations with the c ontractor, the proposed contract time extension will be non-compensable.

Funding and
Costs:

Funding Source: Water Enterprise Capital Improvement Program 10037519, San Francisco Zoo Recycled Water Project
Original Contract Amount: $2,175,723
Original 10% Cost Contingency: $217,572
425 consecutive calendar days (approximately one year and two months).

On June 10, 2025, by Resolution No. 25- 0089, the Commission approved an increase of 203 calendar days to the duration contingency for delays related to the additional time required for manufacturing and procurement of long- lead electrical equipment, for a total duration limit of 670 consecutive calendar days (approximately one year and 10 months).

Agenda Title: WD-2895, San Francisco Zoo Recycled Water Commission Meeting Date: May 26, 2026

Page 3 ends

Approved Increase in Cost Contingency: $0
Modified Increases to Contract Amount: $35,599
Total Current Contract Amount: $2,211,322
Current Cost Contingency: $181,973
Additional Cost Contingency: $0
Total Contract Cost Limit: $2,393,295

Schedule: Notice-to-Proceed Date: June 3, 2024
Original Contract Duration: 425 consecutive calendar days Original 10% Duration Contingency: 42 calendar days
Approved Increase to Duration Contingency: 203 calendar days
Modified Increases to Contract Duration: 0 calendar days Total Current Contract Duration: 425 consecutive calendar days Current Duration Contingency: 245 calendar days
[Proposed] Additional Duration Contingency: 360 Calendar Days Total [Proposed] Duration Limit: 1,030 calendar days

Local
Business
Enterprise
Utilization and
Non-
Discrimination
in
Contracting:

The Contract Monitoring Division established a 15% Local Business Enterprise (LBE) subcontracting requirement for this contract. The contractor committed to 39.11 % LBE subcontractor participation with its bid submittal.

Agenda Title: WD-2895, San Francisco Zoo Recycled Water Commission Meeting Date: May 26, 2026

Page 4 ends

WD-2895 San Francisco Recycled Water Project

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO.

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Water Enterprise Local Water Supply Program has the objectives of expanding and diversifying its water supply portfolio and reducing the use of potable water for irrigation by supplying those demands with non-potable supplies such as recycled water; and

WHEREAS, The purpose of the San Francisco Zoo Recycled Water Project (Project) is to provide recycled water to offset the use of groundwater from the Westside Groundwater Basin for irrigation and other non- potable uses within the San Francisco Zoo and Lower Great Highway; and

WHEREAS, On February 13, 2024 , by Resolution No. 24 -0027, the Commission awarded Contract No. WD -2895, San Francisco Zoo Recycled Water , to Basset Engineering; and

WHEREAS, The original contract amount was for $2,175,723, and the original contract duration was 425 consecutive calendar days (approximately one year and two months); and

WHEREAS, The contract Notice-to-Proceed date was June 3, 2024; and

WHEREAS, On June 10, 2025, by Resolution No. 25- 0089, the Commission approved an increase of 203 calendar days to the duration contingency for Contract No.

WD-2895, for a total duration limit of 670 calendar days (approximately one year and 10 months), with no change to the contract amount, for delays related to the additional time required for manufacturing and procurement of long-lead electrical equipment; and

WHEREAS, Staff issued Modification No. 1, increasing the contract amount by $35,599, within the original cost contingency, for a total contract amount of $2,211,322, with no change to the contract duration, to furnish and install a temporary bypass pipeline to support testing and commissioning; and

WHEREAS, Staff recommends this Commission approve an increase of 360 calendar days to the existing duration contingency, for a revised duration limit of 1,030 consecutive calendar days (approximately two years and ten months ), with no change to the contract amount, to allow for the completion of the P roject, which is delayed due to the additional time required for manufacturing and procurement of long-lead electrical equipment; and

WHEREAS, The Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting participation of 15 % for this contract, the contractor committed to 39.11% LBE subcontractor participation with its bid submittal, and this

amount remains unchanged; and

WHEREAS, Funds are available from Water Capital Improvement Program, Project No. 10037519, San Francisco Zoo Recycled Water Project; now, therefore, be it

RESOLVED, The Commission hereby approves an increase of 360 calendar days to the existing duration contingency, for Contract No. WD-2895, San Francisco Zoo Recycled Water , with Basset Engineering, for a total duration contingency of 605 calendar days; and be it

FURTHER RESOLVED, That this Commission hereby authorizes the General Manager, or the General Manager’s designee, to consider, and, if appropriate, to approve modifications to the contract up to a total duration limit of 1,030 consecutive calendar days, with no change to the contract amount.

I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of May 26, 2026.

__________________________________
Director of Commission Affairs
San Francisco Public Utilities Commission