AGENDA ITEM
Public Utilities Commission
City and County of San Francisco
DEPARTMENT: Infrastructure Division
AGENDA NUMBER: 6g
MEETING DATE: September 8, 2026
Calendar: Consent Calendar
Project Manager: Judy Chin
Award Job Order Contract No. JOC-114, General Engineering (A-License) Construction, San Francisco, Santa Mateo, Santa Clara, and Alameda Counties
Summary of Proposed
Commission Action:
Award Job Order Contract No. JOC-114, General Engineering (A- License) Construction, San Francisco, Santa Mateo, Santa Clara, and Alameda Counties, in the amount not-to-exceed $5,000,000, with a guaranteed minimum task order opportunity amount of $50,000, and a duration of two years, to the responsible bidder that submitted the lowest responsive bid, Corcus Construction, Inc., to perform A-licensed general engineering construction work on San Francisco Public Utilities Commission systems and operations around the San Francisco Bay Area.
Background: A Job Order Contract (JOC) is an indefinite quantity contract that enables the San Francisco Public Utilities Commission (SFPUC) to complete tasks quickly and efficiently on an as -needed basis under a single, competitively bid construction contract using published pre-set unit prices. The competitive process is based on Adjustment Factors, which are the contractor’s mark -ups (overhead and profit) for when and where the work will be performed (regular time, over time, and county). For example, a bidder might bid a lower mark -up for regular hours in San Francisco than for counties further away that require additional travel time.
Staff multiplies the Adjustment Factors by each bid line item and adds all the line items together to calculate the Award Criteria Figure. Upon review by the Contract Monitoring Division, the Award Criteria Figure may be modified by application of the Local Business Enterprise (LBE) bid discount. SFPUC staff then uses the Award Criteria Figure, as may be adjusted by the LBE bid discount, to compare the bids and determine the apparent low bidder.
The SFPUC has used Job Order Contracts for a wide range of construction activities including general building construction and general
engineering construction, specialized electrical work in power turbines and switchyards, spot sewer repair, marine related services, lighting upgrades, repair of heating, ventilation, and air conditioning systems, and energy efficiency retrofits.
Agenda Title: JOC-114, General Engineering (A-License) Construction, San Francisco, Santa Mateo, Santa Clara, and Alameda Counties Commission Meeting Date: September 8, 2026
The SFPUC will issue task orders to the selected contractor to perform specific scopes of work during the term of this contract.
Each task order is priced based on pre-set unit prices, as published with the Advertisement for Bids, multiplied by the appropr iate Adjustment Factor from the contractor’s bid.
The not-to-exceed amount of this proposed contract is $5,000,000.
Under San Francisco Administrative Code S ection 6.62, the Commission may increase the maximum contract value by up to 150% of the original contract value (an additional $2,500,000) for a total potential maximum contract amount of up to $7,500,000.
The duration of this proposed contract is two years. Under San Francisco Administrative Code Section 6.62, the Commission may extend the term up to five years. The SFPUC may not issue any new task orders under this contract after four years from the date the Controller certifies the availability of funds for this contract.
Scope of Contract: The contract work locations are San Francisco, San Mateo, Santa Clara, and Alameda Counties. The scope of work for potential task orders consists of:
• Concrete;
• Construction Traffic Control Services;
• Earthwork and Paving;
• Electrical;
• General Building Construction;
• General Engineering Construction;
• Hazardous Waste and Remediation Services;
• Landscape;
• Lenel Systems Integration;
• Pipeline;
• Pipeline Inspection – Remote Inspection Tool;
• PLC System Integration;
• Tree Service;
• Well Drilling; and,
• Well Pump Repair.
Funding and Costs: Award: Not-to-exceed amount of $5,000,000 with a guaranteed minimum task order opportunity of $50,000.
Funding: Funding for the contract will be available from various SFPUC Enterprise Funds when Staff issues task orders.
Schedule: Estimated Notice-to-Proceed Date: November 2026
Duration: two years
Agenda Title: JOC-114, General Engineering (A-License) Construction, San Francisco, Santa Mateo, Santa Clara, and Alameda Counties Commission Meeting Date: September 8, 2026
(The Commission may approve additional time at a later date up to the five -year maximum duration allowed by the San Francisco Administrative Code for Job Order Contracts.)
Estimated Completion Date: November 2028
Bid History: Advertised: March 20, 2026
Bids Received: On April 16, 2026, SFPUC received and publicly opened five bids, as follows:
Bid Rank
Award
Criteria
Figure
Bid Discount
Award Criteria
Figure with
Bid Discount
Final Rank
1. Yerba Buena
Engineering and
Construction, Inc.
1.1400 10% = 0.11400 1.02600 -
2. Corcus
Construction, Inc. 1.1668 10% = 0.11668 1.05012 1
3. Minerva
Construction, Inc. 1.2082 10%= 0.12082 1.08738 2
4. Marinship
Development
Interest, LLC
1.2505 10% = 0.12505 1.12545 3
5. Cal State
Constructors, Inc. 1.3415 10%= 0.13415 1.20735 4
Application of bid discount in accordance with Chapter 14B of the San Francisco Administrative Code did not change the final ranking of the low bidder.
Protest: On April 23, 2026, Corcus Construction, Inc. protested the bid submitted by Yerba Buena Engineering and Construction, Inc. The basis for the protest was that Yerba Buena Engineering and Construction, Inc. , failed to comply with the subcontractor listing requirements in Section 00 43 35 Instructions for Proposed Subcontractors Form. The SFPUC provided Yerba Buena
Engineering and Construction, Inc., an opportunity to respond, and the firm submitted its response on April 29, 2026. SFPUC staff, in consultation with the Contract Administration Bureau and the City Attorney’s Office, reviewed the protest, the response, and all rebuttals and determined that the Yerba Buena Engineering and Construction, Inc.’s bid was nonresponsive to the requirements of Section 00 43 35. On June 29, 2026, the SFPUC issued a final determination rejecting the nonresponsive bid submitted by Yerba Buena Engineering and Construction, Inc. Following that determination, staff concluded that Corcus Construction, Inc. , is the responsible bidder that submitted the lowest responsive bid.
Agenda Title: JOC-114, General Engineering (A-License) Construction, San Francisco, Santa Mateo, Santa Clara, and Alameda Counties Commission Meeting Date: September 8, 2026
Environmental
Review:
This action does not constitute a project under the California Environmental Quality Act (CEQA) Guidelines Section 15378 because it will not result in a physical change in the environment , and it does not represent an approval of a specific project.
Staff will not authorize any work involving ground disturbance or any other physical changes in the environment until any necessary environmental review has been completed pursuant to the CEQA.
Local Business
Enterprise Utilization
and Non-
Discrimination In
Contracting:
The Contract Monitoring Division (CMD) established a 20% Local Business Enterprise (LBE) subcontracting requirement for this contract. Corcus Construction, Inc. , committed to a 27% LBE subcontractor participation in its bid submittal.
Attachment: CMD Memorandum
PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO. __________________
WHEREAS, The San Francisco Public Utilities Commission (SFPUC) requires as- needed construction for a wide range of construction activities to support its facilities, including general building construction and general engineering construction, specialized electrical work in power turbines and switchyards, spot sewer repair, marine related services, lighting upgrades, repair of heating, ventilation, and air conditioning systems, and energy efficiency retrofits, and the SFPUC typically utilizes a Job Order Contract (JOC) to perform this work; and
WHEREAS, On March 20 , 2026, the SFPUC advertised Job Order Contract No.
JOC-114, General Engineering (A -License) Construction, San Francisco, Santa Mateo, Santa Clara, and Alameda Counties; and
WHEREAS, On April 16, 2026, the SFPUC received and publicly opened five bids in which the bidders submitted their proposed profit and overhead percentage markups on specified unit prices for work to be specified under task orders; and
WHEREAS, Staff and the Contract Monitoring Division (CMD) reviewed the bidder and their bid for responsibility, responsiveness, and application of bid preferences, and determined Corcus Construction, Inc. , to be the responsible bidder that submitted the lowest responsive bid; and
WHEREAS, The Contract Monitoring Division established a 20 % Local Business Enterprise (LBE) subcontracting requirement for this contract, and Corcus Construction, Inc., committed to a 27% LBE subcontractor participation with its bid submittal; and
WHEREAS, The contract not-to-exceed amount is $5,000,000 with a guaranteed minimum task order opportunity of $50,000, to perform A -licensed general engineering construction work on SFPUC systems in San Francisco, San Mateo, Santa Clara, and Alameda Counties; and
WHEREAS, The contract duration is two years; and
WHEREAS, Staff will issue task orders that identify the scope of work, cost, and duration for various discrete construction activities that the c ontractor will perform under this Job Order Contract; and
WHEREAS, This action does not constitute a project under the California Environmental Quality Act (CEQA) Guidelines Section 15378 because it will not result in a physical change in the environment, and it does not represent an approval of a specific project; and
WHEREAS, Staff will not authorize any work involving ground disturbance or any other physical changes in the environment until any necessary environmental review has been completed pursuant to the CEQA; and
WHEREAS, Funds will be available from various SFPUC Enterprise funds for SFPUC issued task orders; now, therefore, be it
RESOLVED, That this Commission hereby awards Job Order Contract No. JOC- 114, General Engineering (A-License) Construction, San Francisco, Santa Mateo, Santa Clara, and Alameda Counties, for a not-to-exceed amount of $5,000,000, and a duration of two years, to the responsible bidder that submitted the lowest responsive bid, Corcus Construction, Inc.
I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of September 8, 2026.
__________________________________
Director of Commission Affairs
San Francisco Public Utilities Commission
City & County of San Francisco
Daniel Lurie, Mayor
Office of the City Administrator
Carmen Chu, City Administrator
Contract Monitoring Division
Regina Chan, Director
1455 Market Street, Suite 16A, San Francisco, CA 94103 Telephone (415) 554-0630
MEMORANDUM
Date: June 30, 2026
To: Jeremy Brooks, SFPUC
Judy Chin, SFPUC
From: Jason Chow, CMD
Subject: REV. #1 – CMD Review of Bids Submitted on 4/16/2026 for JOC-114 General Engineering (A- License) Construction, San Francisco, San Mateo, Santa Clara, and Alameda Counties
**Note to the SFPUC -- Please use the tables with the blue headers for your Peoplesoft project team entry.
Bids and Bid Discount
Yerba Buena Engineering & Construction, Inc. (“YBE”) is the apparent low bidder after the bid discount.
The bid discount was applied to bidders who are certified by the Contract Monitoring Division, (“CMD”) as an LBE in the type of work that is specified for the bidder by the Contract Awarding Authority.
Bidder LBE Status,
Type and Size
Award Criteria
Figure Bid Discount
Adjusted ACF
with
Bid Discount
Yerba Buena Engineering &
Construction, Inc.
SF LBE-MBE
(Micro) 1.1400 10% 1.026
Corcus Construction, Inc. SF LBE-OBE
(Micro) 1.1668 10% 1.05012
Minerva Construction, Inc. SF LBE-OBE
(Small) 1.2082 10% 1.08738
Marinship Development
Interest LLC
SF LBE-MBE
(Small) 1.2505 10% 1.12545
Cal State Constructors, Inc. SF LBE-OBE
(Micro) 1.3415 10% 1.20735
YBE’s ACF was the lowest but the contract awarding authority did not find them responsible to bid requirements. As such, Corcus Construction (“Corcus”) becomes the lowest and responsive bidder.
LBE Subcontracting Participation Requirement
Corcus satisfactorily demonstrated how they will meet the LBE subcontractor participation requirement.
A combination of Micro-LBE and Small-LBE participation will count toward LBE subcontractor participation compliance. Corcus’s commitment for this contract:
Requirement % Commitment %
Micro/Small LBE 20.00% 27.00%
In their bid, Corcus listed the following subcontractors on this contract.
Supplier Name Scope of Work
LBE
LBE Size
LBE
Percent
Percent
Of
Work
Amount
Liffey Electric
(Full) Electrical C-10,
Lenel Systems
Integration and PCL
and Systems
Integrator
LBE SML 100% 18.00% $900,000.00
KM 106 Construction
(Full) Hazardous
Waste & Remediation
Services
LBE MICR 100% 1.00% $50,000.00
Bauman Landscape
and Construction
(Full) Landscape (C-
27) LBE SML 100% 10.00% $500,000.00
Pump Repair Service (Full) Pump Repairs
D21 Work LBE SML 100% 8.00% $400,000.00
Rockaway Construction (Full) General Building
Contracting (B) N/A N/A N/A $300,000.00
Weeks Drilling and
Pump
(Full) Well Drilling (C-
57) N/A N/A N/A $200,000.00
All Seasons Tree
Service and Land
Cleaning
(Full) Tree Service (C-
49) N/A N/A N/A $200,000.00
Liffey Electric’s LBE credited amount is $400,000.00 or 8.00%. Said firm’s portion of work is credited for less than the listed amount because per its CMD Form 6, said firm will be further subcontracting out $500,000.000 of its portion of work to non-LBE firms (Convergint—$300,000.00 and Telstar-- $200,000.00.) As such, CMD adjusted said firm’s LBE credited participation accordingly.
“Good Faith Efforts” Requirement
Corcus satisfied the “Good Faith Efforts” requirement.
Corcus utilized Approach A and exceed the LBE subcontractor participation requirement by 35%.
CMD Determination
CMD finds Corcus responsive to pre-award requirements of Chapter 14B. Once awarded, the contract will be monitored for compliance with the LBE subcontractor participation commitment, as well as other 14B requirements.
Primary CMD contact for the contract: Jason Chow, [email protected].
CMD must be contacted immediately for:
- Subcontractor addition/substitution;
- Contract modification that cumulatively increases the original contract value by 20%; - Prompt payment issues;
- Any other issues pertaining to LBE subcontractor participation
Noncompliance may result in penalties, including monetary fines. Please communicate with CMD early.