AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

DEPARTMENT: Infrastructure Division

AGENDA NUMBER: 6h
MEETING DATE: September 8, 2026
Calendar: Consent Calendar
Project Manager: Mary Tienken

Approve Increase to the Duration Contingency for Contract No. WD-2901, San Andreas Pipeline 3 – Drainage & Erosion Repair at Junipero Serra Park

Summary of Proposed
Commission Action:

Approve an increase of 180 calendar days (approximately six months) to the existing duration contingency for Contract No. WD - 2901, San Andreas Pipeline 3 – Drainage & Erosion Repair at Junipero Serra Park, with JDB & Sons Construction , Inc., for a revised duration limit of up to 576 consecutive calendar days (approximately one year and seven months), due to unforeseen poor soil conditions that required field modifications to a storm drain pipe, leading to a delay in completion of the contract work, with no change to the contract amount.

Background: The San Franc isco Public Utilities Commission (SFPUC) Water Enterprise requires repair work to address a leaking storm drain pipe that eroded a hillside and created a deep gully adjacent to SFPUC San Andreas Pipeline No. 3 easement. The storm drain
pipe is
located on property owned by San Mateo County, and discharges stormwater from catch basins that are owned by the City of San Bruno. Through a Memorandum of Understanding, the City of San Bruno has agreed to share the cost of the work and to own and maintain the new st orm drain pipe, and San Mateo County has agreed to maintain the repaired gully.

On March 25, 2025, by Resolution No. 25-0053, this Commission awarded Contract No. WD-2901, San Andreas Pipeline 3 – Drainage & Erosion Repair at Junipero Serra Park , to JDB & Sons Construction, Inc. The original contract amount was $1,192,500 and the original contract duration was 360 consecutive calendar days.

Scope of Contract: The contract work is within Junipero Serra Park, in San Mateo County, where the SFPUC has an easement for the SAPL3. The purpose of this project is to stabilize the hillside and protect the SAPL3 easement area.

The contract work consists of:
• Mobilization and demobilization;
• Traffic control work;
• Shoring of work area above gully;
• Installation of rock slope protection within the existing gully; Agenda Title: WD-2901, San Andreas Pipeline3 – Drainage & Erosion Repairs at Junipero Serra Park Commission Meeting Date: September 8, 2026

Page 2 ends

• Construction of approximately 180 linear feet of 12 -inch diameter high-density polyethylene (HDPE) storm drain pipe, including HDPE cleanouts, concrete thrust blocks, concrete trench dams, and a 12 -inch diameter perforated HDPE
spreader tee;
• T ree protection; and
• Restoration of landscape and park improvements impacted by construction.

Modifications to the
Contract:

Proposed Increase to Duration Contingency: Staff recommends the Commission approve an increase of 180 calendar days to the existing duration contingency, for a revised duration limit of up to 576 consecutive calendar days, due to unforeseen poor soil conditions that require field modifications, leading to a delay in completion of the contract work, with no change to the contract amount.

Funding and Costs: Funding Source: Project No. 10015072, Pipeline Inspection and Repair

Original Contract Amount: $1,192,500
Original 10% Cost Contingency: $119,250
Approved Increase to Cost Contingency: $0
Modified Increases to Contract Amount: $0
Total Current Contract Amount: $1,192,500
Current Cost Contingency: $119,250
Additional Cost Contingency: $0
Total Contract Cost Limit: $1,311,750

Schedule: Notice-to-Proceed Date: June 9, 2025
Estimated End Date: December 8, 2026

Original Contract Duration: 360 consecutive calendar days Original 10% Duration Contingency: 36 calendar days
Approved Increase to Duration Contingency: 0 calendar days Modified Increases to Contract Duration: 0 calendar days Total Current Contract Duration: 360 consecutive calendar days Current Duration Contingency: 36 calendar days
[Proposed] Additional Duration Contingency: 180 calendar days Total [Proposed] Duration Limit: 576 consecutive calendar days

Environmental
Review:

On October 17, 2013 , the Planning Commission certified the Final Environmental Impact Report (Final EIR) for the Peninsula Pipelines Seismic Upgrade Project (Case No. 2011.0123E), prepared pursuant to the California Environmental Quality Act (CEQA).

On October 22, 2013, by Resolution No. 13-0161, this Commission adopted CEQA Findings, including a Statement of Overriding Considerations, and a Agenda Title: WD-2901, San Andreas Pipeline3 – Drainage & Erosion Repairs at Junipero Serra Park Commission Meeting Date: September 8, 2026

Page 3 ends

Mitigation Monitoring and Reporting Program, pursuant to the CEQA, and approved the Peninsula Pipelines Seismic Upgrade Project.

On April 12, 2017, the Planning Department issued an Addendum to the Final EIR (Case No. 2011.0123E), which evaluated the replacement and/or sliplining of four segments of San Andreas Pipeline No. 2.

On January 22, 2019, by Resolution No. 19- 0014, this Commission reviewed and considered the Addendum to the Final EIR and approved Contract No. WD-2829R, San Andreas Pipeline No. 2 Replacement Project.

During construction, a leaking storm drain pipe was found at one segment, which was eroding the hillside and causing a deep gully adjacent to SFPUC’s pipelines easement.

On September 5, 2023, the Planning Department issued a Minor Project Modification to the Final EIR to extend the storm drain culvert and stabilize the eroded gully to protect San Andreas Pipeline No. 3, which is located in SFPUC’s easement closest to the gully, determining that no supplemental environmental review was needed beyond the Minor Project Modification.

This action is within the scope of the Project authorized under the Final EIR, as modified by the Addendum and the Minor Project Modification.

View the Final EIR, Addendum to the Final EIR, Minor Project Modification to the Final EIR, Resolution No. 13- 0161, Resolution No. 19- 0014, CEQA Findings, and the Mitigation Monitoring and Reporting Program.

Local Business
Enterprise
Utilization and
Non-
Discrimination
in Contracting:

The Contract Monitoring Division established a 20% Local Business Enterprise ( LBE) subcontracting requirement for this contract. The contractor committed to a 23.16% LBE subcontractor participation with its bid submittal, and this remains unchanged.

Agenda Title: WD-2901, San Andreas Pipeline3 – Drainage & Erosion Repairs at Junipero Serra Park Commission Meeting Date: September 8, 2026

Page 4 ends

Location Map

PUBLIC UTILITIES COMMISSION
City and County of San Francisco
RESOLUTION NO. __________________

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Water Enterprise requires repair work to address a leaking storm drain pipe that eroded a hillside and created a deep gully adjacent to SFPUC San Andreas Pipeline No. 3 easement; and

WHEREAS, On March 25, 2025 , by Resolution No. 25- 0053, this Commission awarded Contract No. WD-2901, San Andreas Pipeline 3 – Drainage & Erosion Repair at Junipero Serra Park to JDB & Sons Construction, Inc.; and

WHEREAS, The original contract amount was $1,192,500 and the original contract duration was 360 consecutive calendar days; and

WHEREAS, The contract Notice-to-Proceed date was June 9, 2025; and

WHEREAS, Staff recommends this Commission approve an increase of 180 calendar days to the existing duration contingency, for a revised duration limit of 576 consecutive calendar days, d ue to unforeseen soil conditions that required field modifications to a storm drain pipe, leading to a delay in completion of the contract work, with no change to the contract amount; and

WHEREAS, The Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting participation of 20% for this contract, and the contractor committed to an LBE subcontractor participation of 23.16% with its bid submittal, and this amount remains unchanged; and

WHEREAS, On October 17, 2013 , the Planning Commission certified the Final Environmental Impact Report (Final EIR) for the Peninsula Pipelines Seismic Upgrade Project (Case No. 2011.0123E), prepared pursuant to the California Environmental Quality Act (CEQA); and

WHEREAS, On October 22, 2013 , by Resolution No. 13- 0161, this Commission adopted CEQA Findings, including a Statement of Overriding Considerations, and a Mitigation Monitoring and Reporting Program, pursuant to the CEQA , and approved the Peninsula Pipelines Seismic Upgrade Project; and

WHEREAS, On April 12, 2017, the Planning Department issued an Addendum to the Final EIR (Case No. 2011.0123E), which evaluated the replacement and/or sliplining four segments of San Andreas Pipeline No. 2; and

WHEREAS, On January 22, 2019, by Resolution No. 19- 0014, this Commission reviewed and considered the Addendum to the Final EIR and approved Contract No. WD- 2829R, San Andreas Pipeline No. 2 Replacement Project, and during construction a

leaking storm drain pipe was found at one segment, which was eroding the hillside and causing a deep gully adjacent to SFPUC’s pipelines easement; and

WHEREAS, On September 5, 2023, the Planning Department issued a Minor Project Modification to the Final EIR to extend the storm drain culvert and stabilize the eroded gully to protect San Andreas Pipeline No. 3, which is located in SFPUC’s easement closest to the gully, determining that no supplemental environmental review was needed beyond the Minor Project Modification; and

WHEREAS, This action is within the scope of the Project authorized under the Final EIR, as modified by the Addendum and the Minor Project Modification; and

WHEREAS, The Planning Department is the custodian of records, located in File No. 2011.0123E, at 49 South Van Ness Avenue, Suite 1400, San Francisco, California 94103; staff have made these materials available for review by both this Commission and the public, and they are incorporated into the record before this Commission; and

WHEREAS, This Commission has reviewed and considered the information in the Project files, including the Final EIR, CEQA Findings including a Statement of Overriding Considerations, Resolution No. 13-0161, Resolution No. 19-0014, the Addendum to the Final EIR, the Minor Project Modification to the Final EIR , and Mitigation Monitoring and Reporting Program , and all written and oral information provided by the Planning Department, the public, relevant public agencies, SFPUC, and other experts, and the administrative files for the Project; and

WHEREAS, Funds are available from Water Enterprise Project No. 10015072, Pipeline Inspection and Repair; now, therefore, be it

RESOLVED, This Commission has reviewed and considered the Final EIR, Addendum to the Final EIR, the Minor Project Modification to the FEIR, and the record as a whole, and finds that the Final EIR, as modified by the Addendum and Minor Project Modification, is adequate for its use as the decision–making body for the Project, that no subsequent or supplemental environmental review is required, and incorporates the CEQA Findings and Resolution No. 13- 0161 and Resolution No. 19- 0014 by this reference thereto as though set forth in this Resolution; and, be it

FURTHER RESOLVED, This Commission further finds that since the Final EIR, as modified by the Addendum to the Final EIR and the Minor Project Modification to the Final EIR, were finalized, there have been no substantial changes in the Project or its circumstances that would require major revisions to the Final EIR, Addendum, and Minor Project Modification due to new significant environmental effects or an increase in the severity of previously identified significant impacts, and there is no new information o f substantial importance that would change the conclusions set forth in those documents ; and, be it

FURTHER RESOLVED, That this Commission hereby approves an increase of 180 calendar days to the existing duration contingency for Contract No. WD-2901, San Andreas Pipeline 3 – Drainage & Erosion Repair at Junipero Serra Park, with JDB & Sons Construction, Inc., for a total duration contingency of 216 calendar days, with no change to the cost contingency; and, be it

FURTHER RESOLVED, That this commission he reby authorizes the General Manager, or the General Manager’s designee, to consider and, if appropriate, to approve any future modifications to the contract, for a total duration limit of 576 consecutive calendar days.

I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of September 8, 2026.