AGENDA ITEM
Public Utilities Commission
City and County of San Francisco

DEPARTMENT: Infrastructure Division

AGENDA NUMBER: 6a
MEETING DATE: October 27, 2026

Calendar: Consent Calendar
Project Manager: John Wong

Accept Closeout, Approve Modification No. 4 (Final), and Authorize Final Payment for Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and Wawona Streets, and Sloat Blvd Sewer Replacement

Summary of Proposed
Commission Action:

Accept work performed by Precision Engineering, Inc. , under Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and Wawona Streets, and Sloat Blvd Sewer Replacement; approve Modification No. 4 (Final), decreasing the contract amount by $ 18,855, and increasing the contract duration by 177 calendar days, for a total contract amount of $7,539,231 and a total contract duration of 704 calendar days (approximately one year and eleven months), to adjust the final contract amount to the value of actual contract quantities completed and to complete all contract work ; and authorize final payment to the contractor.

Background: San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise inspected existing sewers on several streets within the City and County of San Francisco (specific locations listed below) and determined they should be replaced. The existing main sewers replaced/lined range in size from 8- to 21-inch diameter and were constructed primarily in the 1920s. Staff coordinat ed the contract work with the San Francisco Municipal Transportation Agency (SFMTA) L Taraval Improvement Project Segment B contract and took advantage of SFMTA’s shutdown of the L -Taraval Light Rail Vehicle service. The work under Contract No. WW -684 was intended to replace/line the existing sewer facilities at the subject locations to minimize future disruption along this portion of the L Taraval service area.

On November 8, 2022 , by Resolution No. 22-0192, this
Commission awarded Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and Wawona Streets, and Sloat Blvd Sewer Replacement, to Precision Engineering, Inc. The original contract amount was $7,342,613 and the original contract duration was 375 calendar days (approximately one year and one month).

On March 26, 2024, by Resolution No. 24 -0073, this Commission approved an increase in the duration contingency by 115 days.

Agenda Title: WW-684, 45th, 46th, 47th Aves, Vicente and Wawona Streets, and Sloat Blvd Sewer Replacement Commission Meeting Date: October 27, 2026

Page 2 ends

Scope of Contract: The contract work is in San Francisco, CA and work locations include:
• Sloat Blvd from Lower Great Hwy to 44th Avenue;
• 47th Avenue from Sloat Blvd to Taraval Street;
• 46th Avenue from Sloat Blvd to Ulloa Street;
• 45th Avenue from Sloat Blvd to Vicente Street;
• Wawona Street from 47th Avenue to 44th Avenue; and
• Vicente Street from 47th Avenue to 45th Avenue.

The original contract work consisted of:
• Replacing the existing main sewers with approximately 2,720 linear feet of 12 -inch diameter, 830 linear feet of 15 - inch diameter, 232 linear feet of 18 -inch diameter and 13 linear feet of 21-inch diameter vitreous clay pipe (VCP); and • Cured-in-place lining of approximately 4,828 linear feet of existing 8-inch diameter and 334 linear feet of existing 12 - inch diameter main sewers.

Modifications to the
Contract:

Modification No. 1: Staff issued Modification No. 1 increasing the contract amount by $12,472, within the original contract cost contingency, with no change to the contract duration, for a total contract amount of $7,355,085, to address unforeseen and differing site conditions.

Modification No. 2: Staff issued Modification No. 2 increasing the contract duration by 152 consecutive calendar days, within the duration contingency authorized under Resolution No. 24-0073, for a revised contract duration of 527 consecutive calendar days, with no change to the contract amount , to provide additional time needed for Staff to complete review and approval of contract submittals, obtain permits, and for unforeseen site conditions.

Modification No. 3: Staff issued Modification No. 3 increasing the contract amount by $203,000, within the original contract cost contingency, with no change to the contract duration, for a total contract amount of $7,558,085, to address unforeseen and differing site conditions.

Recommended Modification No. 4 (Final) : Staff recommends that the Commission approve Modification 4 (Final), decreasing the contract amount by $ 18,855, and increasing the contract duration by 177 calendar days, for a total contract amount of $7,539,230 and a total contract duration of 704 consecutive calendar days, to adjust the final contract amount to the value of actual contract quantities completed and to complete all contract work.

Funding and Costs: Funding Source: Wastewater Enterprise Renewal and Replacement Program, Project No. 10034367, 45th, 46th, 47th Agenda Title: WW-684, 45th, 46th, 47th Aves, Vicente and Wawona Streets, and Sloat Blvd Sewer Replacement Commission Meeting Date: October 27, 2026

Page 3 ends

Aves, Vicente, Wawona Streets and Sloat Blvd. Sewer
Replacement
Original Contract Amount: $7,342,613
Original 10% Cost Contingency: $734,261
Approved Increase to Cost Contingency: $0
Modified Increases to Contract Amount: $215,472
Total Current Contract Amount: $7,558,085
Current Cost Contingency: $518,789
[Proposed] Modification No. 4 (Final) Amount: ($18,855) Total [Proposed] Final Contract Amount: $7,539,230

Schedule: Notice-to-Proceed Date: February 27, 2023
Original Contract Duration: 375 consecutive calendar days Original 10% Duration Contingency: 37 calendar days
Approved Increase to Duration Contingency: 115 calendar days Modified Increases to Contract Duration: 152 calendar days Total Current Duration Amount: 527 consecutive calendar days Current Duration Contingency: 0 calendar days
[Proposed] Modification No. 4 (Final) Duration: 177 calendar days
Total [Proposed] Total Contract Duration: 704 consecutive calendar days

Local Business
Enterprise Utilization
and Non-
Discrimination in
Contracting:

The Contract Monitoring Division (CMD) established a 10% Local Business Enterprise (LBE) subcontracting requirement for this contract. The contractor committed to a n 14.04% LBE
subcontractor participation with its bid submittal.

Precision Engineering, Inc., achieved a final LBE subcontractor participation of 13.57% for this contract, which was less than the original committed 14.04%. The CMD determined Precision Engineering, Inc., has made a good faith effort to substantially comply with the LBE subcontracting requirements associated with this project and concurs with closeout of this contract.

Attachment(s): Contract Monitoring Division Closeout Memorandum

VICINTY MAP LOCATION MAP

WW-684, 45th, 46th, 47th Aves, Vicente, Wawona Streets and Sloat Blvd Sewer Replacement

PUBLIC UTILITIES COMMISSION
City and County of San Francisco

RESOLUTION NO. __________________

WHEREAS, The San Francisco Public Utilities Commission (SFPUC) Wastewater Enterprise inspected existing sewers on the subject streets in the City and County of San Francisco and determined that the existing sewers needed to be replaced; and

WHEREAS, On November 8, 2022, by Resolution No. 22-0192, the Commission awarded Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and Wawona Streets, and Sloat Blvd Sewer Replacement to Precision Engineering, Inc.; and

WHEREAS, The original contract amount was $7,342,613 and the original contract duration was 375 consecutive calendar days; and

WHEREAS, The contract Notice-to-Proceed date was February 27, 2023; and

WHEREAS, Staff issued Modification No. 1, increasing the contract amount by $12,472, within the original contract cost contingency, with no change to the contract duration, for a total contract amount of $ 7,355,085, to address unforeseen and differing site conditions; and

WHEREAS, On March 26, 2024, by Resolution No. 24 -0073, this Commission approved an increase in the duration contingency by 115 days; and

WHEREAS, Staff issued Modification No. 2 increasing the contract duration by 152 consecutive calendar days, within the duration contingency authorized under Resolution No. 24-0073, for a revised contract duration of 5 27 consecutive calendar days, with no change to the contract amount , to provide additional time needed for Staff to complete review and approval of contract submittals, obtain permits, and for unforeseen site conditions; and

WHEREAS, Staff issued Modification No. 3, increasing the contract amount by $203,000, within the original contract cost contingency, with no change to the contract duration, for a total contract amount of $ 7,558,085, to address unforeseen and differing site conditions; and

WHEREAS, Staff recommends the Commission approve Modification No. 4 (Final) decreasing the contract amount by $18,855 and increasing the contract duration by 177 calendar days, for a final total contract amount of $7,539,230 and a total contract duration of 704 consecutive calendar days, to adjust the final contract amount to the value of actual contract quantities completed and to complete all contract work; and

WHEREAS, The Contract Monitoring Division established a Local Business Enterprise (LBE) subcontracting requirement of 10% for this contract, and the contractor

committed to an LBE subcontractor participation of 14.04% with its bid submittal and the contractor achieved 13.57% final LBE subcontractor participation; and

WHEREAS, Funds are available from Project No. 10034367, 45th, 46th, 47th Aves, Vicente, Wawona Streets and Sloat Blvd. Sewer Replacement; now, therefore, be it,

RESOLVED, That this Commission hereby accepts work performed by Precision Engineering, Inc. , under Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and Wawona Streets, and Sloat Blvd Sewer Replacement , approves Modification No. 4 (Final), decreasing the contract amount by $18,855, and increasing the contract duration by 177 calendar days , for a total contract amount of $ 7,539,230 and a total contract duration of 704 consecutive calendar days , and authorizes final payment to the contractor.

I hereby certify that the foregoing resolution was adopted by the San Francisco Public Utilities Commission at its meeting of October 27, 2026.

__________________________________
Director of Commission Affairs
San Francisco Public Utilities Commission

City & County of San Francisco
Daniel Lurie, Mayor
Office of the City Administrator
Carmen Chu, City Administrator

Contract Monitoring Division
Regina Chan, Director

1455 Market Street, Suite 16A, San Francisco, CA 94103 Telephone (415) 554-0630

MEMORANDUM

Date: June 26, 2026

To: John Wong, SFPUC
Aileen Caylao, SFPUC
Gary Hom, SFPUC

From: Jim Oerther, CMD

Subject: Closeout for WW-684 45th, 46th, 47th Aves, Vicente, Wawona Sts and Sloat Blvd Sewer Replacement (PeopleSoft Contract ID: 1000028186)

The Contract Monitoring Division (“CMD”) has determined that Precision Engineering (“Precision”), the LBE prime contractor, has made a good faith effort to substantially comply with the LBE subcontracting requirements associated with this project.

At the time the project was advertised, a Micro/Small-LBE subcontracting participation requirement of 10% was established. Precision’s Section 00 43 36 reflected a Micro/Small- LBE subcontracting participation of 14.04%. Precision was awarded the contract in the amount of $7,342,612,20. After four (4) change orders, the final contract amount is $7,539,230.14. Precision’s Micro/Small-LBE subcontracting participation is as follows:

Firm
LBE
Status,
Type and
Size
Scope of
Work
Original Credited
Contract Participation
Final Credited
Contract Participation
Roadway
Construction
Inc
SF LBE
(Micro)
Grinding &
Paving $660,612.20 9.00% $785,452.67 10.42%
Camajani
Trucking
SF LBE
(Small) Trucking $250,000 3.40% $227,290.75 3.01%
CMC Traffic
Control
SF LBE
(Small)
Labor
Support $120,000 1.63% $0.00 0.00%
DR Traffic
Control
Specialists
SF LBE
(Micro)
Traffic
Control -- -- $10,469 0.14%
TOTAL $1,030,612.20 14.04% $1,023,212.42 13.57%

Precision achieved 13.57% of the 14.04% commitment made to the LBEs at the award.

CMC Traffic Control Specialists was unable to perform the work due to not having the required contractor’s license (General A). They were to do labor support for bid items SW- 5, SW-6, and SW-7 to assist in performing hand digging, street base placement, and

temporary asphalt placement work. Precision did outreach to other LBEs to perform this work but no other LBEs were interested. To make the shortfall and to maximize the LBE sub participation, Precision made the good faith effort to engage another LBE, DR Traffic Control Specialists to do traffic control.

Based on the foregoing, CMD has no further action on this contract. Should you have any questions, please do not hesitate to contact me by email at [email protected] or at (415) 554-0642.