2. Storage Availability Adjustment. The “Storage Availability Adjustment” shall be calculated as follows and applied to the Storage Capacity Payment due for the next month after the end of the monthly period for which the Monthly Storage Availability is calculated. (a) If the Monthly Storage Availability is greater than or equal to the Guaranteed Storage Availability, then:
Storage Availability Adjustment = 100% (expressed as a decimal) Exhibit M - 4
Exhibit N - 1
EXHIBIT N
STORAGE CAPACITY TESTS
Storage Capacity Test Notice and Frequency
A. Commercial Operation Storage Capacity Test(s). Upon no less than ten (10) Business Days’ prior Notice to Buyer, Seller shall schedule and complete a Commercial Operation Storage Capacity Test prior to the Commercial Operation Date. Such initial Commercial Operation Storage Capacity Test (and any subsequent Commercial Operation Storage Capacity Test permitted in accordance with Exhibit B) shall be performed in accordance with this Exhibit N and shall establish the Installed Storage Capacity hereunder based on the actual capacity and capabilities of the Storage Facility determined by such Storage Capacity Test(s).
B. Subsequent Storage Capacity Tests. Following the Commercial Operation Storage Capacity Test(s), at least fifteen (15) days in advance of the start of each Contract Year, upon no less than ten (10) Business Days’ prior Notice to Buyer, Seller shall schedule and complete a Storage Capacity Test. In addition, Buyer shall have the right to require a retest of the Storage Capacity Test at any time upon no less than five (5) Business Days prior Notice to Seller. Seller shall have the right to run a retest of any Storage Capacity Test at any time upon five (5) Business Days’ prior Notice to Buyer (or any shorter period reasonably acceptable to Buyer consistent with Prudent Operating Practice).
C. Test Results and Re-Setting of Storage Capacity. No later than five (5) days following any Capacity Test, Seller shall submit a testing report detailing results and findings of the test. The report shall include Storage Facility Meter readings and plant log sheets verifying the operating conditions and output of the Storage Facility. In accordance with Section 4.13(c) of the Agreement and Part II(I) below, after the Commercial Operation Storage Capacity Test(s), the Storage Capacity (up to, but not in excess of, the Installed Storage Capacity) determined pursuant to such Storage Capacity Test shall become the new Storage Capacity at the beginning of the first day following the completion of the test for calculating the Storage Capacity Payment and all other purposes under this Agreement.
Capacity Test Procedures
PART I. GENERAL.
(1) Each Capacity Test shall be conducted in accordance with Prudent Operating Practices, the Operating Restrictions and the provisions of this Exhibit N. For ease of reference, a Capacity Test is sometimes referred to in this Exhibit N as a “CT”.
Buyer or its representative may be present for the CT and may, for informational purposes only, use its own metering equipment (at Buyer’s sole cost). (2) Conditions Prior to Testing.
(1) EMS Functionality. The EMS shall be successfully configured to receive data from the Battery Management System (BMS), exchange Distributed Exhibit N - 2
Network Protocol 3 data with the Buyer SCADA device, and transfer data to the database server for the calculation, recording and archiving of data points.
(3) Commissioning Checklist. Commissioning shall be successfully completed per manufacturer guidance on all applicable installed Facility equipment, including verification that all controls, set points, and instruments of the EMS are configured.
PART II. REQUIREMENTS APPLICABLE TO ALL CAPACITY TESTS.
A. Test Elements. Each CT shall include the following individual test elements. The Parties acknowledge and agree that should Seller fall short of demonstrating one or more of the Test Elements as specified below, the CT will still be deemed “complete,” and any adjustments necessary to the Storage Capacity resulting from such CT, if applicable, will be made in accordance with this Exhibit N. (1) Electrical output at the lesser of the maximum discharging level (MW) and Guaranteed Storage Capacity for four (4) continuous hours; and (2) Electrical input at maximum charging level at the Storage Facility Meter (MW), as sustained until the SOC reaches at least 90%, continued by the electrical input at a rate up to the maximum charging level at the Storage Facility Meter (MW), as sustained until the SOC reaches 100%, not to exceed five (5) hours of total charging time.
(3) The dispatch of the Storage Facility during the CT shall only be done through the ADS signal from the CAISO to the Storage Facility. Seller shall not interfere with or alter the Storage Facility’s response to the ADS signal during the CT or manually alter any EMS or SCADA data recorded by the Storage Facility.
B. Parameters. During each CT, the following parameters shall be measured and recorded simultaneously for the Storage Facility, at two (2) second intervals:
(1) Time;
(2) The amount of Charging Energy;
(3) The amount of Discharging Energy;
(4) SOC; and
(5) Station Use.
Exhibit N - 3
C. Site Conditions. During each CT, the following conditions at the Site shall be measured and recorded simultaneously at thirty (30) minute intervals:
(1) Relative humidity (%);
(2) Barometric pressure (inches Hg) near the horizontal centerline of the Storage Facility; and
(3) Ambient air temperature (°F).
D. Test Showing. Each CT shall record and report the following datapoints:
(1) That the CT successfully started;
(2) The maximum sustained discharging level for four (4) consecutive hours pursuant to A(1) above;
(3) The maximum sustained charging level for four (4) consecutive hours pursuant to A(2) above;
(4) Amount of time between the Storage Facility’s electrical output going from 0 to the maximum sustained discharging level registered during the CT (for purposes of calculating the ramp rate);
(5) Amount of time between the Storage Facility’s electrical input going from 0 to the maximum sustained charging level registered during the CT (for purposes of calculating the ramp rate);
(6) Amount of Charging Energy to go from 0% SOC to 100% SOC; and (7) Amount of Discharging Energy to go from 100% SOC to 0% SOC.
E. Test Conditions.
(1) General. At all times during a CT, the Storage Facility shall be operated in compliance with Prudent Operating Practices, the Operating Restrictions, and all operating protocols recommended, required or established by the manufacturer for the Storage Facility.
(2) Abnormal Conditions. If abnormal operating conditions that prevent the testing or recordation of any required parameter occur during a CT, Seller may postpone or reschedule all or part of such CT in accordance with Part II.F below.
(3) Instrumentation and Metering. Seller shall provide all instrumentation, metering and data collection equipment required to perform the CT. The instrumentation, metering and data collection equipment electrical meters shall be calibrated in accordance with Prudent Operating Practice and, as Exhibit N - 4
applicable, the CAISO Tariff. At Buyer’s request, Seller shall provide documentation of all equipment calibration and certification. (4) Ambient Temperature. For tests requested by Buyer (and not for any CAISO-initiated test, which shall occur when directed by CAISO), the average ambient temperature, based on an aggregate of 1-minute resolution data collected throughout the SCT, must be within the range of 8 – 33 degrees Celsius.
F. Incomplete Test. If any CT is not completed in accordance herewith, Buyer may in its sole discretion: (i) accept the results up to the time the CT stopped without any modification to the Storage Capacity pursuant to Section I below; (ii) require that the portion of the CT not completed, be completed within a reasonable specified time period; or (iii) require that the CT be entirely repeated within a reasonable specified time period. Notwithstanding the above, if Seller is unable to complete a CT due to a Force Majeure Event or the actions or inactions of Buyer or the CAISO or the Transmission Provider, Seller shall be permitted to reconduct such CT on dates and at times reasonably acceptable to the Parties.
G. Test Report. Within five (5) Business Days after the completion of any CT, Seller shall prepare and submit to Buyer the completed Installed Capacity Certificate together with a written report of the results of the CT, which report shall include:
(1) A record of the personnel present during the CT that served in an operating, testing, monitoring or other such participatory role;
(2) The measured and calculated data for each parameter set forth in Part II.A through D and Part III below, including copies of the raw data taken during the test; and
(3) Seller’s statement of either Seller’s acceptance of the CT or Seller’s rejection of the CT results and reason(s) therefor.
Seller’s CT report and any submitted capacity certificate shall be deemed invalid if not delivered to Buyer within five (5) Business Days after the completion of any CT. Within five (5) Business Days after receipt of such report, Buyer shall notify Seller in writing of either Buyer’s acceptance of the CT results or Buyer’s rejection of the CT and reason(s) therefor.
If either Party rejects the results of any CT, such CT shall be repeated in accordance with Part II.F.
H. Supplementary Capacity Test Protocol. No later than sixty (60) days prior to any CT, Buyer may deliver to Seller for its review and approval (such approval not to be unreasonably delayed or withheld) a supplement to this Exhibit N with additional and supplementary details, procedures and requirements applicable to Capacity Tests based on the then-current design of the Storage Facility (“Supplementary Capacity Test Protocol”). Any additional Supplementary Exhibit N - 5
Capacity Test Protocol (and each update thereto), once approved by Seller, shall be deemed an amendment to this Exhibit N.
I. Adjustment to Storage Capacity. The Storage Capacity shall equal the quotient of (a) the total amount of Discharging Energy delivered to the Delivery Point (expressed in MWh AC) during the first four (4) hours of discharge (up to, but not in excess of, the product of (i) (A) the Guaranteed Storage Capacity (in the case of a Commercial Operation Storage Capacity Test, including under Section 5 of Exhibit B) or (B) the Installed Storage Capacity (in the case of any other Storage Capacity Test), multiplied by (ii) four (4) hours) divided by (b) four (4) hours, expressed in MW AC.
PART III –CAPACITY TEST PROTOCOL.
A. Storage Capacity
• Procedure:
(1) System Starting State: The Storage Facility will be in the on-line state at 0% SOC.
(2) Record the initial value of the Storage Facility SOC. (3) Command via ADS signal a real power charge that results in an AC power of Storage Facility’s maximum charging level, and continue charging until the earlier of (a) the Storage Facility has reached 100% SOC or (b) five (5) hours have elapsed since the Storage Facility commenced charging. (4) Record and store the Storage Facility SOC after the earlier of (a) the Storage Facility has reached 100% SOC or (b) five (5) hours of continuous charging.
Such data point shall be used for purposes of calculation of the Battery Charging Factor.
(5) Record and store the Charging Energy.
(6) Following an agreed-upon rest period, command via ADS signal a real power discharge that results in an AC power output of the lesser of (i) the Storage Facility’s maximum discharging level and (ii) the Guaranteed Storage Capacity, and maintain the discharging state until the earlier of (a) the Facility has discharged at the maximum discharging level for four (4) consecutive hours, (b) the Storage Facility has reached 0% SOC, or (c) the sustained discharging level is at least 2% less than the lesser of (i) the maximum discharging level and (ii) the Guaranteed Storage Capacity. (7) Record and store the Storage Facility SOC after four (4) hours of continuous discharging.
Exhibit N - 6
(8) Record and store the Discharging Energy as measured at the Storage Facility Meter. Such data point shall be used for purposes of calculation the effective Storage Capacity.
(9) If the Storage Facility has not reached 0% SOC pursuant to Section III.A.6, continue discharging the Storage Facility until it reaches a 0% SOC. Record and store the additional Discharging Energy, if applicable. • Test Results
(1) The resulting effective Storage Capacity measurement is the quotient of (a) the total Discharging Energy at the Storage Facility Meter pursuant to Part III Section A(8) above, divided by (b) four (4) hours.
Exhibit O - 1
EXHIBIT O - 1
OPERATING RESTRICTIONS
Ramp Rates: Dmin to Dmax: up to 100%/s
Cmin to Cmax: up to 100%/s
Dmax to Dmin: up to 100%/s
Cmax to Cmin: up to 100%/s
Frequency ramp rate: 100% MW/Hz
Regulation ramp rate: 345 MW/min
System Response Time: Idle to Dmax: <1s
Idle to Cmax: <1s
Dmax to Cmax: <1s
Cmax to Dmax: <1s
Dmin to Cmin: <1s
Cmin to Dmin: <1s
Exhibit O - 4
Maximum Stored Energy Level:
Minimum Stored Energy Level: 0 MWh, number in MWh representing the lowest level to which the Storage Facility may be discharged
Maximum Charging Capacity: 45.74 MW, number in MW representing the highest level to which the Storage Facility may be charged
Minimum Charging Capacity: 0.01 MW, number in MW representing the lowest level at which the Storage Facility may be charged
Maximum Discharging Capacity: 45.74 MW, number in MW representing the highest level at which the Storage Facility may be discharged
Minimum Discharging Capacity: 0 MW, number in MW representing the lowest level at which the Storage Facility may be discharged
Maximum State of Charge (SOC)
during Charging:
100%
Minimum State of Charge (SOC)
during Discharging:
0%
Ramp Rate: Between 0 and 345 MW/minute
Exhibit P - 1
EXHIBIT P
METERING DIAGRAM
Exhibit Q - 1
EXHIBIT Q
RTE SHORTFALL PAYMENTS
In the event that the RTEM is less than the GRTE, the monthly Storage Capacity Payment under Section 3.3(e) shall be reduced by the “RTE Shortfall Payment”, calculated as follows:
(GRTE – RTEM) x Average Monthly T4B5 Price x RTEFM x TCEM where:
GRTE = the Guaranteed Round-Trip Efficiency
RTEM = the “Round-Trip Efficiency”, as calculated by dividing (a) the total Discharging Energy for the applicable month by (b) the difference of (i) the total Charging Energy for the applicable month, minus (ii) Reimbursable Station Use for the applicable month The “Average Monthly T4B5 Price” means the average of the four (4) highest hourly average Day-Ahead Market LMPs and the five (5) lowest hourly average Day-Ahead Market LMPs, in each case in the applicable month.
The “Round-Trip Efficiency Factor” or “RTEFM” for each month is determined as follows:
If RTEM > GRTE, then RTEFM = 0
If RTEM < GRTE and RTEM > 70%, then RTEFM = 1.2
If RTEM < 70%, then RTEFM = 1.5
TCEM = the total Charging Energy charged to the Storage Facility in the applicable month.
Exhibit R - 2
IP Darden IV, LLC, a Delaware limited
liability company (“Seller”)
PENINSULA CLEAN ENERGY, a California
joint powers authority (“Buyer”)
Exhibit S - 1
EXHIBIT S
SUPPLY CHAIN CODE OF CONDUCT
Buyer is committed to ensuring that the fundamental human rights of workers are protected, including addressing the potential risks of forced labor, child labor, servitude, human trafficking and slavery across our portfolio.
Our requirements and expectations for Seller’s supply chain are detailed below in our Supply Chain Code of Conduct (“Supply Chain Code”). Seller must comply with all applicable Laws and this Supply Chain Code, even when this Supply Chain Code exceeds the requirements of applicable Law.
These standards are derived from the United Nations Guiding Principles on Business and Human Rights, the Core Conventions of the International Labour Organization (“ILO”), including the ILO Declaration on Fundamental Principles and Rights at Work, the Solar Energy Industries Association Solar Industry Commitment to Environmental & Social Responsibility, and the Responsible Business Alliance Code of Conduct.
1. Freely Chosen Employment
Forced, bonded (including debt bondage) or indentured labor, involuntary or exploitative prison labor, slavery or trafficking of persons is not permitted. This includes transporting, harboring, recruiting, transferring, or receiving persons by means of threat, force, coercion, abduction or fraud for labor or services. There shall be no unreasonable restrictions on workers’ freedom of movement in the facility in addition to unreasonable restrictions on entering or exiting company provided facilities including, if applicable, workers’ dormitories or living quarters. All work must be voluntary, and workers shall be free to leave work at any time or terminate their employment without penalty if reasonable notice is given as per worker’s contract. Employers, agents, and sub-agents’ may not hold or otherwise destroy, conceal, or confiscate identity or immigration documents, such as government-issued identification, passports, or work permits. Employers can only hold documentation ifsuch holdings are required by law.In this case, at no time should workers be denied access to their documents. Workers shall not be required to pay employers’ agents or sub-agents’ recruitment fees or other related fees for their employment. If any such fees are found to have been paid by workers, such fees shall be repaid to the worker.
2. Young Workers
Child labor is not to be used in any stage of manufacturing. The term “child” refers to any person under the age of 15, or under the age for completing compulsory education, or under the minimum age for employment in the country, whichever is greatest. Suppliers shall implement an appropriate mechanism to verify the age of workers. The use of legitimate workplace learning programs, which comply with all laws and regulations, is supported. Workers under the age of 18 shall not perform work that islikely to jeopardize their health or safety, including night shifts and overtime. Suppliers shall ensure proper management of student workers through proper maintenance of student records, rigorous due diligence of educational partners, and protection of students’ rights in Exhibit S - 2
accordance with applicable laws and regulations. Suppliers shall provide appropriate support and training to all student workers. In the absence of local law, the wage rate for student workers, interns, and apprentices shall be at least the same wage rate as other entry-level workers performing equal or similar tasks. If child labor is identified, assistance/remediation is provided.
3. Working Hours
Studies of business practices clearly link worker strain to reduced productivity, increased turnover, and increased injury and illness. Working hours are not to exceed the maximum set by local law.
Further, a workweek should not be more than 60 hours per week, including overtime, except in emergency or unusual situations. All overtime must be voluntary. Workers shall be allowed at least one day off every seven days.
4. Wages and Benefits
Compensation paid to workers shall comply with all applicable wage laws, including those relating to minimum wages, overtime hours and legally mandated benefits. In compliance with local laws, workersshall be compensated for overtime at pay rates greaterthan regular hourly rates. Deductions from wages as a disciplinary measure shall not be permitted. For each pay period, workers shall be provided with a timely and understandable wage statement that includes sufficient information to verify accurate compensation for work performed. All use of temporary, dispatch and outsourced labor will be within the limits of the local law.
5. Humane Treatment
There is to be no harsh or inhumane treatment including violence, gender-based violence, sexual harassment, sexual abuse, corporal punishment, mental or physical coercion, bullying, public shaming, or verbal abuse of workers; nor is there to be the threat of any such treatment.
Disciplinary policies and procedures in support of these requirements shall be clearly defined and communicated to workers.
6. Non-Discrimination/Non-Harassment
Suppliers should be committed to a workplace free of harassment and unlawful discrimination.
Companies shall not engage in discrimination or harassment based on race, color, age, gender, sexual orientation, gender identityand expression, ethnicity or national origin, disability, pregnancy, religion, political affiliation, union membership, covered veteran status, protected genetic information or marital status in hiring and employment practices such as wages, promotions, rewards, and access to training. Workers shall be provided with reasonable accommodation for religious practices. In addition, workers or potential workers should not be subjected to medical tests that could be used in a discriminatory way or otherwise in violation of applicable law. This was drafted in consideration of ILO Discrimination (Employment and Occupation) Convention (No.111).
7. Freedom of Association
In conformance with local law, Suppliers shall respect the right of all workers to form and join trade unions of their own choosing, to bargain collectively, and to engage in peaceful assembly as Exhibit S - 3
well as respect the right of workers to refrain from such activities. Workers and/or their representatives shall be able to openly communicate and share ideas and concerns with management regarding working conditions and management practices without fear of discrimination, reprisal, intimidation, or harassment.
8. Restricted Jurisdictions
Supplier shall not manufacture or produce products in the Xinjiang Uyghur Autonomous Region of China, or knowingly procure goods and services mined, produced or manufactured in the same.