6. Representations and Warranties.
(a) Copy of PPA. As of the Assignment Agreement Effective Date, each of PPA Seller and PPA Buyer represents and warrants to MSCG that a true, complete, and correct copy of the PPA as of such date is attached hereto as Appendix 4.
(b) No Default. As of the Assignment Agreement Effective Date, each of PPA Seller and PPA Buyer represents and warrants to MSCG that no event or circumstance exists (or would exist with the passage of time or the giving of notice) that, to its knowledge, would give either of them the right to terminate the PPA or suspend performance thereunder. (c) Other. Each of PPA Buyer and PPA Seller represents and warrants to each other and to MSCG that:
i. It has made no prior transfer (whether by way of security or otherwise) of any interest in the Assigned Rights and Obligations; and ii. To its knowledge, all obligations of PPA Buyer and PPA Seller under the PPA required to be performed on or before the Assignment Period Start Date have been fulfilled.
(d) Representations. Each Party represents to each of the other Parties as of the Assignment Agreement Effective Date:
i. Status. It is duly organized and validly existing under the laws of the jurisdiction of its organization or incorporation and, if relevant under such laws, in good standing.
ii. Powers. It has the power to execute, this Agreement and any other documentation relating to this Agreement to which it is a party, to deliver this Agreement and any other documentation relating to this Agreement that it is required by this Agreement to deliver and to perform its obligations under this Agreement and has taken all necessary action to authorize such execution, delivery and performance. 487
iii. No Violation or Conflict. Such execution, delivery and performance of this Agreement and the consummation of the transactions contemplated hereby, including the incurrence by such Party of its obligations under this Agreement, will not result in any violation of, or conflict with: (i) any term of any material contract or agreement applicable to it; (ii) any of its charter, bylaws, or other constitutional documents; (iii) any determination or award of any arbitrator applicable to it; or (iv) any license, permit, franchise, judgment, writ, injunction or regulation, decree, order, charter, law, ordinance, rule or regulation of any Government Agency presently in effect, applicable to it or any of its assets or properties or to any obligations incurred by it or by which it or any of its assets or properties or obligations are bound or affected, and shall not cause a breach of, or default under, any such term or result in the creation of any lien upon any of its properties or assets. iv. Consents. All consents, approvals, orders or authorizations of, registrations, declarations, filings or giving of notice to, obtaining of any licenses or permits from, or taking of any other action with respect to, any Person or Government Agency that are required to have been obtained by such Party with respect to this Agreement and the transactions contemplated hereby, including the due authorization of such Party and its governing body and any approval or consent of any security holder of such Party or any holder (or any trustee for any holder) of any indebtedness or other obligation of such Party, have been obtained and are in full force and effect and all conditions of any such consents have been complied with. v. Obligations Binding. Its obligations under this Agreement constitute its legal, valid and binding obligations, enforceable in accordance with their respective terms (subject to applicable bankruptcy, reorganization, insolvency, moratorium or similar laws affecting creditors’ rights generally and subject, as to enforceability, to equitable principles of general application (regardless of whether enforcement is sought in a proceeding in equity or at law)).
vi. Non-Reliance. It is acting for its own account, and it has made its own independent decisions to enter into this Agreement and as to whether this Agreement is appropriate or proper for it based upon its own judgment and upon advice from such advisers as it has deemed necessary. It is not relying on any communication (written or oral) of the other Parties as investment advice or as a recommendation to enter into this Agreement; it being understood that information and explanations related to the terms and conditions of this Agreement shall not be considered investment advice or a recommendation to enter into this Agreement. It is entering into this Agreement as a bona-fide, arm’s-length transaction involving the mutual exchange of consideration and, once executed by all Parties, considers this Agreement a legally enforceable contract. No communication (written or oral) received from any of the other Parties shall be deemed to be an assurance or guarantee as to the expected results of this Agreement. vii. Assessment and Understanding. It is capable of assessing the merits of and understanding (on its own behalf or through independent professional advice), and understands and accepts, the terms, conditions and risks of this Agreement. It is also capable of assuming, and assumes, the risks of this Agreement. 488
viii. Status of Parties. None of the other Parties is acting as a fiduciary for or an adviser to it in respect of this Agreement.

7. Miscellaneous.

Article [__] (Confidential Information), [__] (No Consequential Damages), [__] (Amendments), [__] (No Agency, Partnership, Joint Venture or Lease), Sections [__] (Severability), [__] (Electronic Delivery), [__] (Counterparts), Section [__] (Binding Effect) and [__] (Forward Contract) of the PPA are incorporated by reference into this Agreement, mutatis mutandis, as if fully set forth herein.

8. Costs and Expenses.

The Parties shall each pay their own costs and expenses (including legal fees) incurred in connection with this Agreement and as a result of the negotiation, preparation, and execution of this Agreement.

9. Notices.

Any notice, demand, or request required or authorized by this Agreement to be given by one Party to another Party shall be delivered in accordance with [Section ___] of the PPA and to the addresses of each of PPA Seller and PPA Buyer specified in the PPA. PPA Buyer agrees to notify MSCG of any updates to such notice information, including any updates provided by PPA Seller to PPA Buyer. Notices to MSCG shall be provided to the address set forth in Appendix 3.

Each Party may update its address from time to time by notice to the other Parties.

10. Governing Law; Dispute Resolution.
(a) Governing Law. This Agreement and the rights and duties of the Parties under this Agreement will be governed by and construed, enforced and performed in accordance with the laws of the state of New York, without reference to any conflicts of laws provisions that would direct the application of another jurisdiction’s laws; provided, however, that the authority of PPA Buyer to enter into and perform its obligations under this agreement shall be determined in accordance with the laws of the state of California.
(b) Arbitration. Any dispute, claim or controversy arising out of or relating to this Agreement or the breach, termination, enforcement, interpretation or validity thereof, including the determination of the scope of this Agreement to arbitrate, shall be determined by final, non-appealable binding arbitration in San Francisco, California before three (3) arbitrators. The arbitration shall be administered by Judicial Arbitration and Mediation Services, Inc. (“JAMS”) pursuant to its Comprehensive Arbitration Rules and Procedures. Within fifteen (15) days after the commencement of arbitration, each of MSCG and PPA Buyer shall select one person to act as arbitrator, and the two so-selected arbitrators shall select a third arbitrator (the “chairperson”) within thirty (30) days of the commencement of the arbitration. If either MSCG or PPA Buyer is unable or fails to select one person to act as arbitrator, such arbitrator shall be appointed by JAMS.

If the MSCG and PPA Buyer-selected arbitrators are unable or fail to agree upon a chairperson, 489
the chairperson shall be appointed by JAMS. The chairperson shall be a person who has experience in renewable energy-related transactions, and none of the arbitrators shall have been previously employed by any Party or have any direct pecuniary interest in any Party or the subject matter of the arbitration, unless such conflict is expressly acknowledged and waived in writing by all of the Parties. The Parties shall maintain the confidential nature of the arbitration proceeding and any award, including any hearing(s), except as may be necessary to prepare for or conduct the arbitration hearing on the merits, or except as necessary in connection with a court application for a preliminary remedy, a judicial challenge to an award or its enforcement, or unless otherwise required by law or judicial decision. Any arbitration proceedings, decision or award rendered hereunder and the validity, effect and interpretation of this arbitration provision shall be governed by the Federal Arbitration Act. The arbitrator(s) shall have no authority to award consequential, treble, exemplary, or punitive damages of any type or kind regardless of whether such damages may be available under any law or right, with the Parties hereby affirmatively waiving their rights, if any, to recover or claim such damages. The responsibility for compensation and expenses of the three arbitrators and all other expenses charged by JAMS shall be equally split in one-third (1/3) shares by each of MSCG, PPA Buyer, and PPA Seller. In any arbitration arising out of or related to this Agreement, the arbitrators shall award to the prevailing Party or Parties, if any, the costs and attorney’s fees reasonably incurred in seeking to enforce the application of this Section 10(b) and by the prevailing party in connection with the arbitration. Notwithstanding the foregoing provisions of this Section 10(b), any costs incurred by a Party in seeking judicial enforcement of any written decision of the arbitrators shall be chargeable to and borne exclusively by the Party against whom such court order is obtained. The award shall be final and binding on the Parties and judgment upon any award may be entered in any court of competent jurisdiction. (c) Judicial Reference. Without limiting the provisions in Section 10(b), if Section 10(b) is deemed ineffective or unenforceable in any respect, any dispute between the Parties arising out of or in connection with this Agreement or its performance, breach, or termination (including the existence, validity and interpretation of this Agreement and the applicability of any statute of limitation period) (each, a “Dispute”) shall be resolved by a reference proceeding in California in accordance with the provisions of Sections 638 et seq. of the California Code of Civil Procedure (“CCP”), or their successor sections (a “Reference Proceeding”), which shall constitute the exclusive remedy for the resolution of any Dispute. As a condition precedent to initiating a Reference Proceeding with respect to any Dispute, the Parties shall comply with the provisions of Section 10(c)(i).
i. Notice of Dispute. Prior to initiating the Reference Proceeding, a Party (the “Disputing Party”) shall provide the other Parties (the “Responding Parties”) with a written notice of each issue in dispute, a proposed means for resolving each such issue, and support for such position (the “Notice of Dispute”). Within 10 days after receiving the Notice of Dispute, the Responding Parties shall provide the Disputing Party with a written Notice of each additional issue (if any) with respect to the dispute raised by the Notice of Dispute, a proposed means for resolving every issue in dispute, and support for such position (the “Dispute Response”). Thereafter, the Parties shall meet to discuss the matter and attempt in good faith to reach a negotiated resolution of the dispute. If the Parties do not resolve the dispute by unanimous agreement within fifteen (15) days after receipt of the Dispute Response, (the “Negotiation Period”), then any Party may provide to the other 490
Parties written notice of intent for judicial reference (the “Impasse Notice”) in accordance with the further provisions of this Section 10(c).
ii. Applicability; Selection of Referees. Within 10 days of the delivery of an Impasse Notice, each of MSCG and PPA Buyer shall nominate one (1) referee. The two (2) referees (the “Party-Appointed Referees”) shall appoint a third referee (the “Third Referee”, together with the Party-Appointed Referees, the “Referees”). The Party-Appointed Referees shall be competent and experienced in matters involving the electric energy business in the United States, with at least ten (10) years of electric energy industry experience as a practicing attorney. The Third Referee shall be an active or retired California state or federal judge. Each of the Party-Appointed Referees and the Third Referee shall be impartial and independent of each of the Parties and of the other referees and not employed by any of the Parties in any prior matter. iii. Inability to Agree upon Third Referee. If the Party-Appointed Referees are unable to agree on the Third Referee within 45 days from delivery of the Impasse Notice, then the Third Referee shall be appointed pursuant to CCP Section 640(b) in an action filed in the Superior Court of California, County of San Francisco (the “Court”), and with due regard given to the selection criteria above. A request for appointment of a referee may be heard on an ex parte or expedited basis, and the Parties agree that irreparable harm would result if ex parte relief is not granted. Pursuant to CCP Section 170.6, each of PPA Buyer and MSCG shall have one (1) peremptory challenge to the referee selected by the Court. iv. Discovery; Proceedings.
(A) The Parties agree that time is of the essence in conducting the Reference Proceeding. Accordingly, the Referees shall be requested, subject to change in the time periods specified herein for good cause shown, to (i) set the matter for a status and trial-setting conference within 20 days after the date of selection of the Third Referee, (ii) if practicable, try all issues of law or fact within 180 days after the date of the conference, and (iii) report a statement of decision within 20 days after the matter has been submitted for decision. (B) Discovery and other pre-hearing procedures shall be conducted as agreed to by the Parties, or if they cannot agree, as determined by the Third Referee after discussion with the Parties regarding the need for discovery and other pre-hearing procedures. (C) Except as expressly set forth herein, the Third Referee shall determine the manner in which the Reference Proceeding is conducted, including the time and place of hearings, the order of presentation of evidence, and all other questions that arise with respect to the course of the Reference Proceeding. The Reference Proceeding, including the trial, shall be conducted at a neutral location selected by the Parties, or if not agreed by the Parties, by the Third Referee, in San Francisco, California.
491
(D) All proceedings and hearings conducted before the Referees, except for trial, shall be conducted without a court reporter, except that when any Party so requests, a court reporter will be used at any hearing conducted before the Referees, and the Referees will be provided a courtesy copy of the transcript. The Party making such a request shall have the obligation to arrange for and pay the court reporter.
v. Decision. The Referees shall render a written statement of decision setting forth findings of fact and conclusions of law. The Referees shall have no authority to award consequential, treble, exemplary, or punitive damages of any type or kind regardless of whether such damages may be available under any law or right, with the Parties hereby affirmatively waiving their rights, if any, to recover or claim such damages. The decision shall be entered as a judgment in the court in accordance with the provisions of CCP Sections 644 and 645. The decision shall be appealable to the same extent and in the same manner that such decision would be appealable if rendered by a judge of the Court. The Parties intend this general reference agreement to be specifically enforceable in accordance with the CCP.
vi. Expenses. Each of MSCG, PPA Seller and PPA Buyer shall bear the compensation and expenses of its respective own counsel, witnesses, consultants and employees. The responsibility for compensation and expenses of the Referees and all other expenses of judicial reference shall be equally split in one-third (1/3) shares by each of MSCG, PPA Buyer, and PPA Seller
(d) Assignment Appendix Prepaid Transaction Details. From time to time, MSCG may deliver one or more completed Assignment Appendices to the other Parties hereto completing the terms that are currently bracketed therein, and each such Assignment Appendix shall be binding upon each of the Parties hereto; provided that the aggregate sum of the Assigned Products under all Assignment Appendices then in effect will not exceed the Contract Quantity under and as defined in the PPA. As set forth in Appendix 1 hereto, MSCG’s payment obligations are limited to any Assigned Products delivered pursuant to the Assignment Appendices then in effect. Each Assignment Appendix will set forth certain details relating to the commodity prepayment transaction pursuant to which all or a portion of the Assigned Products shall be delivered; provided that MSCG may, by written notice to PPA Seller and PPA Buyer, at any time and without the consent of PPA Seller or PPA Buyer, (i) rescind any Assignment Appendix or (ii) update or amend any Assignment Appendix to change any or all of the terms specified therein, including: an increase or decrease of the volume of Assigned Products to be delivered into the applicable commodity prepayment transaction (including without limitation a change thereto to reflect that all MWh of Assigned Products delivered in accordance with the PPA by PPA Seller shall be delivered into one commodity prepayment transaction, subject only the aggregate quantity limit specified above); a change in the relevant commodity prepayment transaction (i.e., the “Prepaid Agreement”) pursuant to which the Assigned Products shall be delivered; a change in the identity of the Prepay Seller; or a change to the Assignment Appendix Start Date and / or the Assignment Appendix End Date. For the avoidance of doubt, (I) more than one Assignment Appendix may be in effect at any time, and (II) at any given time, less than one hundred percent (100%) of the Contract Quantity under and as defined in the PPA may be assigned pursuant to the Assignment Appendices then in effect.
492

10. U.S. Resolution Stay Protocol. The Parties hereby confirm that they are adherents to the ISDA 2018 U.S. Resolution Stay Protocol (“ISDA U.S. Stay Protocol”), the terms of the ISDA U.S. Stay Protocol are incorporated into and form a part of this Agreement, and this Agreement shall be deemed a Protocol Covered Agreement for purposes thereof. For purposes of incorporating the ISDA U.S. Stay Protocol, MSCG shall be deemed to be a Regulated Entity, and PPA Buyer and PPA Seller each shall be deemed to be an Adhering Party. In the event of any inconsistences between this Agreement and the ISDA U.S. Stay Protocol, the ISDA U.S.

Stay Protocol will prevail.
493
IN WITNESS WHEREOF, the Parties have executed this Agreement effective as of the Assignment Agreement Effective Date.
[PPA SELLER]
By: ____________________________
Name:_______________________
Title:________________________

SAN DIEGO COMMUNITY POWER
By: ____________________________
Name:_______________________
Title:________________________
MORGAN STANLEY CAPITAL GROUP INC.

By: ____________________________
Name:_______________________
Title:________________________
494
Appendix 1
Assigned Rights and Obligations
PPA: Renewable Power Purchase Agreement dated as of [____], by and between PPA Buyer and PPA Seller, as may be amended from time to time.

Delivery Point: [____]
Further Information: PPA Seller shall transfer or, to the extent applicable, continue to transfer, to PPA Buyer the WREGIS Certificates associated with all [Renewable Energy Credits] corresponding to all [PV Energy] under the PPA pursuant to [Section ___ of the PPA], provided that the transferee of such WREGIS Certificates may be changed from time to time in accordance with the written instructions of both MSCG and PPA Buyer upon fifteen (15) Business Days’ notice, which change shall be effective as of the first day of the next calendar month after such notice period has expired, unless otherwise agreed. All Assigned Product delivered by PPA Seller to MSCG shall be a sale made at wholesale, with MSCG reselling all such Assigned Product.

Terms with initial capitalization used in this paragraph but not otherwise defined in this Agreement have the meaning set forth in the PPA.

Limitation of MSCG Liability. MSCG has separately agreed with PPA Buyer and Custodian pursuant to the Custody Agreement to pay the “Day-Ahead Average Price” as defined below into the custodial account specified in the Custody Agreement (the “Custodial Account”) for a specified portion of the Assigned Products delivered to the Delivery Point during each Month of the Assignment Period pursuant to all Assignment Appendices then in effect (the “Floating Price Payments”). MSCG agrees to pay the Floating Price Payments into the Custodial Account, and MSCG’s payment obligations under this Agreement are limited to making such payments into the Custodial Account, for application as provided in the Custody Agreement, which also provides for payment by (i) PPA Buyer of any other amounts due under the PPA for each Month of the Assignment Period and (ii) the Custodian of the net amount due to PPA Seller for each Month of the Assignment Period from the amounts received from MSCG and PPA Buyer, as applicable.

MSCG’s Floating Price Payments shall credit against and reduce the amounts otherwise due from PPA Buyer to PPA Seller under the PPA for each Month of the Assignment Period for all Assignment Appendices then in effect; provided that PPA Seller and PPA Buyer acknowledge and agree that the making of Floating Price Payments into the Custodial Account by MSCG shall not entitle (A) MSCG to any payments from PPA Seller or (B) PPA Seller to payments in excess of the net amount that would otherwise be due from PPA Buyer to PPA Seller pursuant to the terms of the PPA. At all times, PPA Buyer remains liable to PPA Seller for all amounts due and owing under the PPA. For the avoidance of doubt, MSCG’s obligations hereunder are limited to only the Assignment Appendices then in effect.
“Day-Ahead Average Price” means the result of (i) (x) the sum of the Day-Ahead Market Prices for each Pricing Interval in a Month divided by (y) the number of Pricing Intervals in such Month plus (ii) the Index Adder (as set forth in the table immediately below) for the relevant Month. As used in this definition, “Pricing Interval” means the unit of time for which [______] establishes a separate price. As used in this definition “Day-Ahead Market Price” means the Day Ahead Market or Locational Marginal Price for [_________________] for each applicable hour as published by 495
[_______], or as such price may be corrected or revised from time to time by [_____] in accordance with its rules. For the avoidance of doubt, the Day-Ahead Average Price can be a negative number.

Month Index Adder ($/MWh)
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
496
Appendix 2
Assignment Appendix - [A][B][C]
Date: [____]
“Assignment Appendix End Date” means 11:59:59 p.m. pacific prevailing time on [____], 20[_]. “Assignment Appendix Start Date” means [____] 1, 20[_]. “Custodian” means The Bank of New York Mellon Trust Company, N.A., a national banking association.
“Custody Agreement” means the [Custodial Agreement] dated as of [____], among the Issuer, PPA Buyer, MSCG, each applicable Prepay Seller and the Custodian, as from time to time amended, restated, supplemented or otherwise modified.
“Issuer” means California Community Choice Financing Authority, a joint powers authority and a public entity of the State of California established pursuant to the provisions of the Joint Exercise of Powers Act (Article 1, Chapter 5, Division 7, Title 1, Section 6500 et seq. of the California Government Code, as amended).
“Prepaid Agreement” means that certain Prepaid Energy Sales Agreement, dated as of [____], 20[_] by and between Prepay Seller and Issuer, as from time to time amended, restated, supplemented or otherwise modified.
“Prepay Power Supply Contract” means that certain Power Supply Contract, dated as of [____], 20[_] by and between Prepay Seller and Issuer, as from time to time amended, restated, supplemented or otherwise modified.
“Prepay Seller” means [_____], a [_____], or any other Person that is the prepay seller under the terms of the Prepaid Agreement from time to time.

Assigned Products subject to this Assignment Appendix: As set forth immediately below, [the percentage of Assigned Products]/[the monthly quantities of Assigned Products] delivered to the Delivery Point: [____]
497
Appendix 3
MSCG Notice Information
[To be completed before signing.]
498
Appendix 4
Copy of PPA
[To be attached.]
499

EXHIBIT B

FORM OF LIMITED ASSIGNMENT AGREEMENT
FOR MSCG AS PPA SUPPLIER3
This Limited Assignment Agreement (this “Agreement”) is entered into as of [____], 2025 (“Assignment Agreement Effective Date”) by and among Morgan Stanley Capital Group Inc., a Delaware corporation (“PPA Seller”), San Diego Community Power, a California joint powers authority (“PPA Buyer”), and Energy Prepay III, LLC, a Delaware limited liability company (“Prepay LLC”).

RECITALS
WHEREAS, PPA Buyer and PPA Seller are parties to that certain PPA as defined in Appendix 1 hereto (the “PPA”);
WHEREAS, in connection with a prepaid electricity transaction entered into between California Community Choice Financing Authority (“Issuer”), and Prepay LLC, and with effect from and including the Assignment Period Start Date (as defined below), PPA Buyer wishes to transfer by partial assignment to Prepay LLC, and Prepay LLC wishes to accept the transfer by partial assignment of, the Assigned Rights and Obligations (as defined below) for the duration of the Assignment Period (as defined below); and
THEREFORE, in consideration of the premises above and the mutual covenants and agreements herein set forth, PPA Seller, PPA Buyer and Prepay LLC (the “Parties” hereto; each is a “Party”) agree as follows:

AGREEMENT

1. Definitions.

The following terms, when used in this Agreement and identified by the capitalization of the first letter thereof, have the respective meanings set forth below, unless the context otherwise requires:
“Agreement” has the meaning specified in the first paragraph above. “Assigned Delivery Point” has the meaning specified in Appendix 1. “Assigned Products” means [all Products] under and as defined in the PPA. “Assigned Rights and Obligations” means (i) the rights of PPA Buyer under the PPA to receive the Assigned Products in each Month during the Assignment Period, as such rights may be limited or further described in Appendix 1, and (ii) the Delivered Product Payment Obligation, which right and obligation are transferred and conveyed to Prepay LLC hereunder. 3 NTD: We have updated the form consistent with the final form of LAA agreed upon by SDCP and MSCG for the bridge PPA for the first tranasction.
500
“Assignment Early Termination Date” has the meaning specified in Section 5(b). “Assignment Period” has the meaning specified in Section 5(a). “Assignment Period End Date” means 11:59:59 p.m. pacific prevailing time on [____]. “Assignment Period Start Date” means [____].
“Business Day” has the meaning specified in the Prepaid Agreement. “Claims” means all claims or actions, threatened or filed, and the resulting losses, damages, expenses, attorneys’ fees, experts’ fees, and court costs, whether incurred by settlement or otherwise, and whether such claims or actions are threatened or filed prior to or after the termination of this Agreement, in each case arising under, in respect of or related in any way to the PPA or any transaction thereunder, except for the Delivered Product Payment Obligation. “Custodian” means U.S. Bank Trust Company, National Association. “Day-Ahead Average Price” has the meaning specified in Appendix 1. “Delivered Product Payment Obligation” has the meaning specified in Section 3(a). “Energy” means three-phase, 60-cycle alternating current electric energy, expressed in megawatt hours (MWh).
“Government Agency” means the United States of America, any state thereof, any municipality, or any local jurisdiction, or any political subdivision of any of the foregoing, including, but not limited to, courts, administrative bodies, departments, commissions, boards, bureaus, agencies, or instrumentalities.
“Issuer” has the meaning specified in the first paragraph of this Agreement. “Month” means a calendar month.
“MWh” has the meaning specified in the Prepaid Agreement. “Person” means any individual, corporation, partnership, joint venture, trust, unincorporated organization, or Government Agency.
“PPA Buyer” has the meaning specified in the first paragraph of this Agreement. “PPA Seller” has the meaning specified in the first paragraph of this Agreement. “Prepaid Agreement” means that certain Prepaid Energy Sales Agreement dated as of [____], 2025 by and between Prepay LLC and Issuer.
501
“Prepay LLC” has the meaning specified in the first paragraph of this Agreement. “Prepay Power Supply Contract” means that certain Power Supply Contract dated [____], 2025 by and between PPA Buyer and Issuer.
“Receivables” has the meaning given to such term in Section 3(e). “Retained Rights and Obligations” has the meaning specified in Section 3.

2. Transfer and Undertakings.
(a) PPA Buyer hereby assigns, transfers and conveys to Prepay LLC all right, title and interest in and to the rights of PPA Buyer under the PPA to receive delivery of the Assigned Products during the Assignment Period. In connection with this assignment, PPA Buyer hereby delegates to Prepay LLC the Assigned Rights and Obligations during the Assignment Period. (b) PPA Seller hereby consents and agrees to PPA Buyer’s assignment, transfer and conveyance of all right, title and interest in and to the Assigned Products and, subject to Section 3, the delegation of the Assigned Rights and Obligations to Prepay LLC and the exercise and performance by Prepay LLC of the Assigned Rights and Obligations during the Assignment Period.
(c) Prepay LLC hereby accepts such assignment, transfer and conveyance of PPA Buyer’s right, title and interest in and to the Assigned Products during the Assignment Period, and PPA Buyer’s delegation of the Assigned Rights and Obligations during the Assignment Period and agrees to perform any such Assigned Rights and Obligations due from it during the Assignment Period to the extent expressly set forth in this Agreement.

3. Limited Assignment.

The Parties acknowledge and agree that (i) the Assigned Rights and Obligations include only a portion of PPA Buyer’s rights and obligations under the PPA, and that all rights and obligations arising under the PPA that are not expressly included in the Assigned Rights and Obligations shall be “Retained Rights and Obligations”, and (ii) the Retained Rights and Obligations include all rights and obligations of PPA Buyer arising during the Assignment Period except the rights and obligations expressly included in the Assigned Rights and Obligations. In this regard:
(a) Limited to Delivered Product Payment Obligation. Prepay LLC’s sole payment obligation hereunder will be to pay the Floating Price Payments into the Custodial Account as such terms are defined in and described on Appendix 1 (the “Delivered Product Payment Obligation”). Prepay LLC and PPA Buyer each agree to instruct the Custodian to pay PPA Seller for the Assigned Products delivered during each Month of the Assignment Period on each applicable payment date under the PPA. PPA Buyer shall remain responsible for any payment obligations under the PPA during the Assignment Period, including in the event that either (i) Prepay LLC does not make the payments into the Custodial Account as described above or (ii) the 502
Custodian does not make the payments to the PPA Seller from the Custodial Account as described above.
(b) Retained Rights and Obligations. Any Claims (other than the Delivered Product Payment Obligation or a failure to perform the same) arising or existing in connection with or related to the PPA, whether related to performance by PPA Seller, PPA Buyer or Prepay LLC, and whether arising before, during or after the Assignment Period, in each case excluding the Delivered Product Payment Obligation, will be included in the Retained Rights and Obligations and any such Claims will be resolved exclusively between PPA Seller and PPA Buyer in accordance with the PPA.
(c) Scheduling. All scheduling of Energy (including Assigned Products) and other communications related to the PPA shall take place between PPA Buyer and PPA Seller pursuant to the terms of the PPA; provided that (i) PPA Buyer and PPA Seller will provide copies of all billing statements and generation reports delivered during the Assignment Period to Prepay LLC and Issuer contemporaneously upon delivery of such statements and reports to the other party to the PPA; (ii) title to Assigned Products will pass to Prepay LLC upon delivery by PPA Seller at the Assigned Delivery Point in accordance with the PPA; (iii) immediately thereafter, title to such Assigned Products will pass to Issuer and then to PPA Buyer upon delivery by Prepay LLC at the same point where title is passed to Prepay LLC pursuant to clause (ii) above; and (iv) PPA Buyer will be deemed to be acting as Prepay LLC’s agent with regard to scheduling Assigned Products. (d) Amendments. PPA Buyer and PPA Seller will provide written notice (including copies thereof) of any proposed or actual amendment, waiver, supplement, modification, or other changes to the PPA to Prepay LLC prior to the effectiveness thereof, and the Parties hereby acknowledge and agree that an amendment, waiver, supplement, modification or other change will not have any effect on Prepay LLC’s rights or obligations under this Agreement unless Prepay LLC receives prior written notice thereof.
(e) Setoff of Receivables. Pursuant to the Prepaid Agreement, Prepay LLC has agreed to purchase the rights to payment of the net amounts owed by PPA Buyer under the Prepay Power Supply Contract (“Receivables”) in the case of non-payment by PPA Buyer. To the extent any such Receivables relate to Assigned Products purchased by Prepay LLC pursuant to the Assigned Rights and Obligations, Prepay LLC may, provided that Prepay LLC has notified PPA Seller in writing (with a copy to PPA Buyer) (a “Receivables Setoff Notice”) that the amount of any such Receivables is true and accurate, transfer such Receivables (excluding any penalties, late payment fees, late payment interest or other fees, costs or interest included in such Receivables) to PPA Seller and apply the face amount of such Receivables (excluding any penalties, late payment fees, late payment interest or other fees, costs or interest included in such Receivables) as a reduction to any Delivered Product Payment Obligations; provided, however, that at no time shall PPA Seller be required to pay Prepay LLC for any amounts by which such Receivables exceed any Delivered Product Payment Obligations then due and owed to PPA Seller. The amount of any Receivables set forth in a Receivables Setoff Notice shall be final and binding unless PPA Buyer shall have provided PPA Seller and Prepay LLC a written notice within two (2) Business Days of its receipt of a Receivables Setoff Notice containing conclusive evidence that such amount is incorrect and asserting what PPA Buyer has determined is the correct amount of Receivables. If any dispute 503
arises therefrom, Prepay LLC shall still be entitled to set-off the amount of Receivables set forth in its Receivables Setoff Notice as provided above, and any such dispute as to the correct amount of Receivables shall be settled exclusively between PPA Buyer and PPA Seller with no liability to Prepay LLC, provided that at all times, PPA Buyer remains liable to PPA Seller for all amounts due and owing under the PPA.

4. Forward Contract.

The Parties acknowledge and agree that this Agreement is intended to constitute a “forward contract” and that the Parties is intended to constitute “forward contract merchants” within the meaning of the United States Bankruptcy Code.

5. Assignment Period; Assignment Early Termination.
(a) Assignment Period. The “Assignment Period” shall begin on the Assignment Period Start Date and extend through and including the Assignment Period End Date; provided that in no event shall the Assignment Period extend past an Assignment Early Termination Date. (b) Early Termination. An “Assignment Early Termination Date” will occur under the following circumstances and as of the dates specified below:
i. the assignment of the Prepay Power Supply Contract by PPA Buyer or Issuer pursuant to Article XIII thereof, which Assignment Early Termination Date shall occur immediately as of the time of such assignment;
ii. the suspension, expiration, or termination of performance of the PPA by either PPA Buyer or PPA Seller for any reason other than the occurrence of Force Majeure under and as defined in the PPA, which Assignment Early Termination Date shall occur immediately as of the time of PPA Seller’s last performance under the PPA following such suspension, expiration, or termination;
iii. the election of Prepay LLC in its sole discretion to declare an Assignment Early Termination Date as a result of (a) any event or circumstance that would give either PPA Buyer or PPA Seller the right to terminate or suspend performance under the PPA (regardless of whether PPA Buyer or PPA Seller exercises such right) or (b) the execution of an amendment, waiver, supplement, modification or other change to the PPA that adversely affects the Assigned Rights and Obligations or Prepay LLC’s rights or obligations under this Agreement (provided that Prepay LLC shall not have a right to terminate under this clause (b) to the extent that Prepay LLC (i) receives prior notice of such change and (ii) provides its written consent thereto), which Assignment Early Termination Date shall occur upon the date set forth in a written notice of such election delivered by Prepay LLC to PPA Buyer and PPA Seller;
iv. termination or suspension of deliveries for any reason other than force majeure under the Prepaid Agreement or Prepay Power Supply Contract, which Assignment Early Termination Date shall occur immediately as of the time of the last deliveries under the relevant contract following such suspension or termination; 504
v. the election of PPA Seller or PPA Buyer in its sole discretion to declare an Assignment Early Termination Date if Prepay LLC fails to pay when due any amounts owed to PPA Seller in respect of any Delivered Product Payment Obligation and such failure continues for five Business Days following receipt by Prepay LLC of written notice thereof, which Assignment Early Termination Date shall occur upon the date set forth in a written notice of such election delivered by PPA Seller or PPA Buyer, as applicable, to Prepay LLC, and with a copy to PPA Buyer or PPA Seller, as applicable; and vi. the election of PPA Seller or PPA Buyer in its sole discretion to declare an Assignment Early Termination Date if either (a) an involuntary case or other proceeding is commenced against Prepay LLC seeking liquidation, reorganization or other relief with respect to it or its debts under any applicable Federal or State bankruptcy, insolvency, fraudulent transfer, reorganization, moratorium or similar law now or hereafter in effect or seeking the appointment of a custodian, receiver, liquidator, assignee, trustee, sequestrator or similar official of it or any substantial part of its property, and such involuntary case or other proceeding shall remain undismissed and unstayed, or an order or decree approving or ordering any of the foregoing is entered and continued unstayed and in effect, in any such event, for a period of 60 days, or (b) Prepay LLC commences a voluntary case or proceeding under any applicable Federal or State bankruptcy, insolvency, fraudulent transfer, reorganization, moratorium or other similar law or any other case or proceeding to be adjudicated as bankrupt or insolvent, or Prepay LLC consents to the entry of a decree or order for relief in an involuntary case or proceeding under any applicable Federal or State bankruptcy, insolvency, reorganization or other similar law or to the commencement of any bankruptcy or insolvency case or proceeding against it, files a petition or answer or consent seeking reorganization or relief under any applicable Federal or State law, or consents to the filing of such petition or to the appointment of or taking possession by a custodian, receiver, liquidator, assignee, trustee, sequestrator or similar official of Prepay LLC or any substantial part of its property, or makes an assignment for the benefit of creditors, or admits in writing its inability to pay its debts generally as they become due, which Assignment Early Termination Date shall occur upon the earliest date set forth in a written notice of such election delivered by PPA Seller or PPA Buyer, as applicable, to Prepay LLC, and with a copy to PPA Buyer or PPA Seller, as applicable. (c) Reversion of Assigned Rights and Obligations. The Parties acknowledge and agree that upon the occurrence of an Assignment Early Termination Date, the Assigned Rights and Obligations will revert from Prepay LLC to PPA Buyer. Any Assigned Rights and Obligations that would become due for payment or performance on or after such Assignment Early Termination Date shall immediately and automatically revert from Prepay LLC to PPA Buyer, provided that (i) Prepay LLC shall remain responsible for the Delivered Product Payment Obligation with respect to any Assigned Products delivered to Prepay LLC prior to the Assignment Early Termination Date, and (ii) any legal restrictions on the effectiveness of such reversion (whether arising under bankruptcy law or otherwise) shall not affect the occurrence of the Assignment Early Termination Date.

6. Representations and Warranties.
505
(a) Copy of PPA. As of the Assignment Agreement Effective Date, each of PPA Seller and PPA Buyer represents and warrants to Prepay LLC that a true, complete, and correct copy of the PPA is attached hereto as Appendix 3.
(b) No Default. As of the Assignment Agreement Effective Date, each of PPA Seller and PPA Buyer represents and warrants to Prepay LLC that no event or circumstance exists (or would exist with the passage of time or the giving of notice) that, to its knowledge, would give either of them the right to terminate the PPA or suspend performance thereunder. (c) Other. As of the Assignment Agreement Effective Date, each of PPA Buyer and PPA Seller represents and warrants to each other and to Prepay LLC that:
i. it has made no prior transfer (whether by way of security or otherwise) of any interest in the Assigned Rights and Obligations; and ii. to its knowledge, all obligations of PPA Buyer and PPA Seller under the PPA required to be performed on or before the Assignment Period Start Date have been fulfilled.
(d) Representations. Each Party represents to each of the other Parties:
i. Status. It is duly organized and validly existing under the laws of the jurisdiction of its organization or incorporation and, if relevant under such laws, in good standing.
ii. Powers. It has the power to execute this Agreement and any other documentation relating to this Agreement to which it is a party, to deliver this Agreement and any other documentation relating to this Agreement that it is required by this Agreement to deliver and to perform its obligations under this Agreement and has taken all necessary action to authorize such execution, delivery and performance. iii. No Violation or Conflict. Such execution, delivery and performance of this Agreement and the consummation of the transactions contemplated hereby, including the incurrence by such Party of its obligations under this Agreement, will not result in any violation of, or conflict with: (i) any term of any material contract or agreement applicable to it; (ii) any of its charter, bylaws, or other constitutional documents; (iii) any determination or award of any arbitrator applicable to it; or (iv) any license, permit, franchise, judgment, writ, injunction or regulation, decree, order, charter, law, ordinance, rule or regulation of any Government Agency, applicable to it or any of its assets or properties or to any obligations incurred by it or by which it or any of its assets or properties or obligations are bound or affected, and shall not cause a breach of, or default under, any such term or result in the creation of any lien upon any of its properties or assets. iv. Consents. All consents, approvals, orders or authorizations of, registrations, declarations, filings or giving of notice to, obtaining of any licenses or permits from, or taking of any other action with respect to, any Person or Government Agency that are required to have been obtained by such Party with respect to this 506
Agreement and the transactions contemplated hereby, including the due authorization of such Party and its governing body and any approval or consent of any security holder of such Party or any holder (or any trustee for any holder) of any indebtedness or other obligation of such Party, have been obtained and are in full force and effect and all conditions of any such consents have been complied with. v. Obligations Binding. Its obligations under this Agreement constitute its legal, valid and binding obligations, enforceable in accordance with their respective terms (subject to applicable bankruptcy, reorganization, insolvency, moratorium or similar laws affecting creditors’ rights generally and subject, as to enforceability, to equitable principles of general application (regardless of whether enforcement is sought in a proceeding in equity or at law)).
vi. Non-Reliance. It is acting for its own account, and it has made its own independent decisions to enter into this Agreement and as to whether this Agreement is appropriate or proper for it based upon its own judgment and upon advice from such advisers as it has deemed necessary. It is not relying on any communication (written or oral) of the other Parties as investment advice or as a recommendation to enter into this Agreement; it being understood that information and explanations related to the terms and conditions of this Agreement shall not be considered investment advice or a recommendation to enter into this Agreement. It is entering into this Agreement as a bona-fide, arm’s-length transaction involving the mutual exchange of consideration and, once executed by all Parties, considers this Agreement a legally enforceable contract. No communication (written or oral) received from any of the other Parties shall be deemed to be an assurance or guarantee as to the expected results of this Agreement. vii. Assessment and Understanding. It is capable of assessing the merits of and understanding (on its own behalf or through independent professional advice), and understands and accepts, the terms, conditions and risks of this Agreement. It is also capable of assuming, and assumes, the risks of this Agreement. viii. Status of Parties. None of the other Parties is acting as a fiduciary for or an adviser to it in respect of this Agreement.

7. Counterparts.

This Agreement (and each amendment, modification and waiver in respect of it) may be executed and delivered in counterparts (including by email), each of which will be deemed an original.

8. Costs and Expenses.

The Parties will each pay their own costs and expenses (including legal fees) incurred in connection with this Agreement and as a result of the negotiation, preparation, and execution of this Agreement.

9. Amendments.
507
No amendment, modification, or waiver in respect of this Agreement will be effective unless in writing and executed by each of the Parties.

10. Notices.

Any notice, demand, statement or request required or authorized by this Agreement to be given by one Party to another shall be in writing, except as otherwise expressly provided herein. It shall be sent by email transmission, courier, or personal delivery (including overnight delivery service) to each of the notice recipients and addresses for each of the other Parties designated in Appendix 2 hereto. Any such notice, demand, or request shall be deemed to be given (i) when sent by email transmission, or (ii) when actually received if delivered by courier or personal delivery (including overnight delivery service). Each Party shall have the right, upon 10 days’ prior written notice to the other Parties, to change its address at any time, and to designate that copies of all such notices be directed to another Person at another address. The Parties may mutually agree in writing at any time to deliver notices, demands or requests through alternate or additional methods.

Notwithstanding the foregoing, a Party may at any time notify the other Parties that any notice, demand, statement or request to it must be provided by email transmission for a specified period of time or until further notice, and any communications delivered by means other than email transmission during such time shall be ineffective.

11. Governing Law, Waiver of Jury Trial, Arbitration.
(a) Governing Law. This Agreement and the rights and duties of the Parties under this Agreement will be governed by and construed, enforced and performed in accordance with the laws of the State of New York, without reference to any conflicts of law provisions that would direct the application of another jurisdiction’s laws; provided, however, that the authority of PPA Buyer to enter into and perform its obligations under this Agreement shall be determined in accordance with the laws of the State of California.
(b) Waiver of Right to Trial by Jury. Each Party waives, to the fullest extent permitted by applicable law, any right it may have to a trial by jury in respect of any suit, action or proceeding relating to this Agreement.
(c) Arbitration. Any dispute, claim or controversy arising out of or relating to this Agreement or the breach, termination, enforcement, interpretation or validity thereof, including the determination of the scope of this Agreement to arbitrate, shall be determined by final, non-appealable binding arbitration in San Francisco, California before three (3) arbitrators. The arbitration shall be administered by Judicial Arbitration and Mediation Services, Inc. (“JAMS”) pursuant to its Comprehensive Arbitration Rules and Procedures. Within fifteen (15) days after the commencement of arbitration, each of Prepay LLC and PPA Buyer, on the one hand, and PPA Seller, on the other hand, shall select one (1) person to act as arbitrator, and JAMS shall appoint one (1) person to act as an arbitrator (for such an arbitration, Prepay LLC, PPA Buyer and PPA Seller are the “Arbitration Parties”), provided that if the arbitration pertains to matters and disputes solely as between PPA Buyer and Prepay LLC, and PPA Seller is neither asserting nor defending a claim in relation thereto, then each of Prepay LLC and PPA Buyer shall select one (1) 508
person to act as arbitrator, and JAMS shall appoint one (1) person to act as an arbitrator (for such an arbitration, only Prepay LLC and PPA Buyer are the “Arbitration Parties”). The JAMS appointed arbitrator shall serve as the chairperson (the “chairperson”). If any of the Arbitration Parties are unable or fail to select one (1) person to act as arbitrator, such arbitrator shall be appointed by JAMS. The chairperson shall be a person who has experience in renewable energy-related transactions, and none of the arbitrators shall have been previously employed by any Arbitration Party or have any direct pecuniary interest in any Arbitration Party or the subject matter of the arbitration, unless such conflict is expressly acknowledged and waived in writing by all of the Arbitration Parties. The Arbitration Parties shall maintain the confidential nature of the arbitration proceeding and any award, including any hearing(s), except as may be necessary to prepare for or conduct the arbitration hearing on the merits, or except as necessary in connection with a court application for a preliminary remedy, a judicial challenge to an award or its enforcement, or unless otherwise required by law or judicial decision. Any arbitration proceedings, decision or award rendered hereunder and the validity, effect and interpretation of this arbitration provision shall be governed by the Federal Arbitration Act. The arbitrator(s) shall have no authority to award consequential, treble, exemplary, or punitive damages of any type or kind regardless of whether such damages may be available under any law or right, with the Arbitration Parties hereby affirmatively waiving their rights, if any, to recover or claim such damages. The responsibility for compensation and expenses of the three (3) arbitrators and all other expenses charged by JAMS shall be shared equally between or among the Arbitration Parties, as the case may be. In any arbitration arising out of or related to this Agreement, the arbitrators shall award to the prevailing Arbitration Party or Arbitration Parties, if any, the costs and attorney’s fees reasonably incurred in seeking to enforce the application of this Section 11(c) by the prevailing party in connection with the arbitration, and the non-prevailing Arbitration Party or Arbitration Parties shall also be liable to the prevailing Arbitration Party or Arbitration Parties for the compensation and expenses of the three arbitrators and all costs charged by JAMS.

Notwithstanding the foregoing provisions of this Section 11(c), any costs incurred by an Arbitration Party in seeking judicial enforcement of any written decision of the arbitrators shall be chargeable to and borne exclusively by the Arbitration Party against whom such court order is obtained. The award shall be final and binding on the Arbitration Parties and judgment upon any award may be entered in any court of competent jurisdiction. (d) Judicial Reference. Without limiting the provisions in Section 11(c), if Section 11(c) is deemed ineffective or unenforceable in any respect, any dispute between the Parties arising out of or in connection with this Agreement or its performance, breach, or termination (including the existence, validity and interpretation of this Agreement and the applicability of any statute of limitation period) (each, a “Dispute”) shall be resolved by a reference proceeding in California in accordance with the provisions of Sections 638 et seq. of the California Code of Civil Procedure (“CCP”), or their successor sections (a “Reference Proceeding”), which shall constitute the exclusive remedy for the resolution of any Dispute. As a condition precedent to initiating a Reference Proceeding with respect to any Dispute, the Parties shall comply with the provisions of Section 11(d)i.
i. Notice of Dispute. Prior to initiating the Reference Proceeding, a Party (the “Disputing Party”) shall provide the other Parties (the “Responding Parties”; and together with the Disputing Party, the “Dispute Parties”) with a written notice of each 509
issue in dispute, a proposed means for resolving each such issue, and support for such position (the “Notice of Dispute”). Within 10 days after receiving the Notice of Dispute, the Responding Parties shall provide the Disputing Party with a written notice of each additional issue (if any) with respect to the dispute raised by the Notice of Dispute, a proposed means for resolving every issue in dispute, and support for such position (the “Dispute Response”). If the Notice of Dispute makes no claim or assertion against one of the Responding Parties, and such Responding Party, in making its Dispute Response does not make or assert a claim against either the Disputing Party or the other Responding Party and states that it has no interest in the Dispute, then such Responding Party shall not participate in the resolution of the Dispute and shall not be a “Dispute Party” for purposes of this Section 11(d). Thereafter, the Dispute Parties shall meet to discuss the matter and attempt in good faith to reach a negotiated resolution of the dispute. If the Dispute Parties do not resolve the dispute by unanimous agreement within sixty (60) days after receipt of the Dispute Response, then any Dispute Party may provide to the other Dispute Party(ies) written notice of intent for judicial reference (the “Impasse Notice”) in accordance with the further provisions of this Section 11(d).
ii. Applicability; Selection of Referees. Within 10 days of the delivery of an Impasse Notice, each of Prepay LLC and PPA Buyer, on the one hand, and PPA Seller, on the other hand, shall nominate one (1) referee, provided that if PPA Seller is not a Dispute Party, then each of Prepay LLC and PPA Buyer shall nominate (1) referee, and PPA Seller will not nominate a referee. The two (2) referees (the “Party-Appointed Referees”) shall unanimously appoint one (1) additional referee (the “Additional Referee”, together with the Party-Appointed Referees, the “Referees”). The Party-Appointed Referees shall be competent and experienced in matters involving the electric energy business in the United States, with at least ten (10) years of electric industry experience as a practicing attorney.

The Additional Referee shall be an active or retired California state or federal judge (the “Head Referee”). Each of the Party-Appointed Referees and the Additional Referee shall be impartial and independent of each of the Dispute Parties and of the other referees and not employed by any of the Dispute Parties in any prior matter. (A) If the Party-Appointed Referees are unable to agree on the Additional Referee within 45 days from delivery of the Impasse Notice, then the Additional Referee shall be appointed pursuant to CCP Section 640(b) in an action filed in the Superior Court of California, County of San Francisco (the “Court”), and with due regard given to the selection criteria above. A request for appointment of a referee may be heard on an ex parte or expedited basis, and the Dispute Parties agree that irreparable harm would result if ex parte relief is not granted. Pursuant to CCP Section 170.6, each of PPA Buyer and Prepay LLC, on the one hand, and PPA Seller, on the other hand, shall have one (1) peremptory challenge to the referee selected by the Court, provided that if PPA Seller is not a Dispute Party, then each of Prepay LLC and PPA Buyer shall have one (1) peremptory challenge to the referee selected by the Court.
iii. Discovery; Proceedings.
510
(A) The Dispute Parties agree that time is of the essence in conducting the Reference Proceeding. Accordingly, the Referees shall be requested, subject to change in the time periods specified herein for good cause shown, to (i) set the matter for a status and trial-setting conference within 20 days after the date of selection of the Head Referee, (ii) if practicable, try all issues of law or fact within 180 days after the date of the conference, and (iii) report a statement of decision within 20 days after the matter has been submitted for decision. (B) Discovery and other pre-hearing procedures shall be conducted as agreed to by the Dispute Parties, or if they cannot agree, as determined by the Head Referee after discussion with the Dispute Parties regarding the need for discovery and other pre-hearing procedures.
(C) Except as expressly set forth herein, the Head Referee shall determine the manner in which the Reference Proceeding is conducted, including the time and place of hearings, the order of presentation of evidence, and all other questions that arise with respect to the course of the Reference Proceeding. The Reference Proceeding, including the trial, shall be conducted at a neutral location selected by the Dispute Parties, or if not agreed by the Dispute Parties, by the Head Referee, in San Francisco, California.
(D) All proceedings and hearings conducted before the Referees, except for trial, shall be conducted without a court reporter, except that when any Dispute Party so requests, a court reporter will be used at any hearing conducted before the Referees, and the Referees will be provided a courtesy copy of the transcript. The Dispute Party making such a request shall have the obligation to arrange for and pay the court reporter.
iv. Decision. The Referees shall render a written statement of decision setting forth findings of fact and conclusions of law. The decision shall be entered as a judgment in the court in accordance with the provisions of CCP Sections 644 and 645. The decision shall be appealable to the same extent and in the same manner that such decision would be appealable if rendered by a judge of the Court. The Dispute Parties intend this general reference agreement to be specifically enforceable in accordance with the CCP. (e) Expenses. The Dispute Parties shall bear the compensation and expenses of its respective own counsel, witnesses, consultants and employees. The responsibility for compensation and expenses of the Referees and all other expenses of judicial reference shall be shared equally between or among the Dispute Parties, as the case may be. [Signature Page Follows]
511
IN WITNESS WHEREOF, the Parties have executed this Agreement effective as of the date first set forth above.

MORGAN STANLEY CAPITAL GROUP INC.

By: ____________________________
Name:_______________________
Title:________________________

SAN DIEGO COMMUNITY POWER
By: ____________________________
Name:_______________________
Title:________________________

ENERGY PREPAY III, LLC
By: Morgan Stanley Capital Group Inc., its Manager
By: ____________________________
Name:_______________________
Title:________________________
512
Appendix 1
Assigned Rights and Obligations
PPA: The EEI Master Power Purchase and Sale Agreement dated January 21, 2021, between PPA Buyer and PPA Seller, as amended by that First Amendment to Master Power Purchase and Sale Agreement dated as of February 8, 2021 between PPA Buyer and PPA Seller, as amended and supplemented by (i) that certain Confirmation Bundled Renewable Energy (PCC2), dated [____], 2025 between PPA Buyer and PPA Seller and (ii) that certain PCC2 & Import Energy Confirmation, dated [____], 2025 (each of (i) and (ii), a “PPA Transaction Confirmation”).

Assigned Delivery Point: The “Delivery Point” as defined in each of the PPA Transaction Confirmations.

Floating Price Payments. Prepay LLC has separately agreed with the PPA Buyer and the Custodian (pursuant to the Custodial Agreement dated [____], 2025, among PPA Buyer, Issuer, Prepay LLC, PPA Seller and the Custodian (the “Custody Agreement”)) to pay into the custodial account specified in the Custody Agreement (the “Custodial Account”) for Assigned Products delivered in each Month of the Assignment Period at the Day-Ahead Average Price (“Floating Price Payments”). Prepay LLC agrees for the benefit of the PPA Seller to pay the Floating Price Payments into the Custodial Account, and Prepay LLC’s payment obligations under this Agreement are limited to making such payments into the Custodial Account, for application as provided in the Custody Agreement. PPA Buyer and PPA Seller each acknowledge and agree that the making of Floating Price Payments into the Custodial Account by Prepay LLC shall not entitle (i) PPA Seller for payments in excess of the Contract Price for Assigned Products delivered hereunder or (ii) PPA Buyer to pay less than the Contract Price for Assigned Products delivered hereunder. PPA Buyer and Prepay LLC each acknowledge and agree that the making of Floating Price Payments into the Custodial Account by Prepay LLC shall not entitle (i) Prepay LLC to any payments from PPA Seller under the PPA or (ii) affect the Custodian’s obligation to pay the net amount due to PPA Seller pursuant to the terms of the PPA on or before the applicable payment date in the PPA. At all times the PPA Buyer shall remain obligated for the payment of all amounts owing under the terms of the PPA under each invoice.

Day-Ahead Average Price: The result of (i) (x) the sum of the Day-Ahead Market Prices for each Pricing Interval in a Month divided by (y) the number of Pricing Intervals in such Month plus (ii) the Index Adder (as set forth in the table immediately below) for the relevant Month. As used in this definition, “Pricing Interval” means each unit of time for which CAISO establishes a separate price. As used in this definition, “Day-Ahead Market Price” means the Day-Ahead Market or Locational Marginal Price for TH_SP15_GEN-APND (or any successor aggregated pricing node for SP 15) for each applicable hour as published by CAISO, or as such price may be corrected or revised from time to time by CAISO in accordance with its rules. For the avoidance of doubt, the Day-Ahead Average Price can be a negative number.

Month Index Adder ($/MWh)
[____] [____]
513
Month Index Adder ($/MWh)
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
[____] [____]
Further Information: For each Month of the Assignment Period, PPA Seller agrees that the monthly invoices it delivers under Section 6.1 of the PPA shall separately list the separate pricing components relevant for the determination of the amounts due under each such invoice. 514
Appendix 2
Notice Information
PPA Seller:

As set forth in the PPA
PPA Buyer:

As set forth in the PPA
Prepay LLC:

Energy Prepay III, LLC
c/o Morgan Stanley & Co.
[1585 Broadway
New York, NY 10036-8293]
With a mandatory copy to:
[email protected] and
[SDCP_2025[X][email protected]]
515
Appendix 3
Copy of PPA
[To be attached.]
516
EXHIBIT A5
517
Chapman Draft 05.08.25

PREPAID ENERGY PROJECT ADMINISTRATION AGREEMENT
This Prepaid Energy Project Administration Agreement (this “Agreement”) is made and entered into as of [_______ __], 2025, by and between California Community Choice Financing Authority (“CCCFA”) and San Diego Community Power (“SDCP”), with respect to the Prepaid Energy Project (defined below). CCCFA and SDCP may be referred to individually herein as a “Party” and collectively as the “Parties”. Capitalized terms used herein (including in the following Recitals) have the meanings given to such terms in Section 1.

W I T N E S S E T H:

WHEREAS, SDCP is a “community choice aggregator” under the Public Utilities Code; and
WHEREAS, SDCP and certain other community choice aggregators have joined CCCFA as a joint exercise of powers authority under and pursuant to the Act and the Joint Powers Agreement; and
WHEREAS, CCCFA’s purpose is to assist its Members (as defined in the Joint Powers Agreement), including SDCP, by undertaking the financing or refinancing of energy prepayments that can be financed with tax advantaged bonds and other obligations on behalf of one or more of the Members by, among other things, issuing or incurring Bonds (as such term is defined in the Joint Powers Agreement) and entering into related contracts with Members; and WHEREAS, CCCFA and SDCP are entering into a Power Supply Contract pursuant to which CCCFA has agreed to supply Energy to SDCP under the terms set forth therein; and WHEREAS, in order to provide such Energy to SDCP under the Power Supply Contract, CCCFA is entering into the Prepaid Energy Sales Agreement with Energy Prepay III, LLC, a Delaware limited liability company (the “Energy Supplier”), under which it will make a prepayment to the Energy Supplier for the purchase and delivery of such Energy; and WHEREAS, CCCFA will finance the prepayment under the Prepaid Energy Sales Agreement and related costs by issuing the Bonds pursuant to the Indenture; and NOW, THEREFORE, in consideration of the premises and mutual covenants set forth in this Agreement and for other good and valuable consideration, the receipt and sufficiency of which are hereby acknowledged, the Parties agree as follows:

Section 1. Defined Terms. Capitalized terms used herein shall have the meanings set forth below:
“Act” means Chapter 5 of Division 7 of Title 1 of the California Government Code, being Section 6500 and following, as amended.
518
“Annual Refund” means the annual refund, if any, to be provided to SDCP pursuant to Section 3.2(b) of the Power Supply Contract. “Assigned Delivery Point” has the meaning specified in the Assignment Agreement.
“Assigned Energy” has the meaning specified in the Assignment Agreement. “Assigned Product” means Assigned Energy and associated renewable energy credits, green energy attributes and any other product included in the Assignment Agreement.
“Assignment Agreement” means the Initial Assignment Agreement and any subsequent assignment agreement entered into consistent with the Assignment Letter Agreement.
“Assignment Letter Agreement” has the meaning specified in the Power Supply Contract.
“Base Energy” means Energy to be delivered to an Energy Delivery Point. “Bonds” means the bonds issued by CCCFA pursuant to the Indenture on or about the date of this Agreement in order to finance the prepayment required to be made to the Energy Supplier under the Prepaid Energy Sales Agreement and related costs of the Prepaid Energy Project, and any bonds issued to refund such bonds. “CCCFA” means California Community Choice Financing Authority, a joint exercise of powers authority created under and pursuant to the Act and the Joint Powers Agreement.
“CCCFA Commodity Swap” means the ISDA Master Agreement, Schedule and transaction Confirmation entered into by CCCFA and the swap counterparty named therein, and any replacement swap entered into pursuant to the Prepaid Energy Sales Agreement.
“Contract Quantity” means the quantity of Base Energy or Assigned Energy, as applicable, specified in Exhibits A-1 and A-2 of the Power Supply Contract, as such Exhibits A-1 and A-2 may be updated from time to time in accordance with the terms of the Power Supply Contract.
“Energy” means three-phase, 60-cycle alternating current electric energy, expressed in megawatt-hours.
“Energy Delivery Point” means the delivery point for delivery of SDCP’s Contract Quantity as specified in the Power Supply Contract, and shall include, if applicable, any Assigned Delivery Point and any alternate Delivery Point for SDCP. “Energy Supplier” means Energy Prepay III, LLC, a Delaware limited liability company.
519
“Indenture” means the Trust Indenture, dated as of [_______] 1, 2025, between CCCFA and the Trustee, as amended, restated, supplemented or otherwise modified from time to time.
“Initial Assignment Agreement” with respect to SDCP, the initial assignment agreement or agreements specified in the Power Supply Contract. “Joint Powers Agreement” means the Joint Powers Agreement by and among the Members of CCCFA named therein, including SDCP, providing for the creation, purposes and powers of CCCFA, as the same may be amended or supplemented from time to time in accordance with its terms.
“Power Supply Contract” means the Power Supply Contract, dated [_______ __], 2025, between CCCFA and SDCP relating to the purchase by SDCP of Energy acquired by CCCFA pursuant to the Prepaid Energy Sales Agreement, as amended, restated, supplemented or otherwise modified from time to time.
“Prepaid Energy Sales Agreement” means the Prepaid Energy Sales Agreement, dated [_______ __], 2025, between CCCFA, as buyer, and the Energy Supplier, as seller, as amended, restated, supplemented or otherwise modified from time to time. “Prepaid Energy Project” means the issuance of the Bonds by CCCFA pursuant to the Indenture, the acquisition of Energy and related undertakings of CCCFA under the Prepaid Energy Sales Agreement and the Indenture, and the sale to SDCP of such Energy and related undertakings of CCCFA under the Power Supply Contract. “Public Utilities Code” means the Public Utilities Code of the State of California, as amended.
“Qualifying Use Requirements” has the meaning set forth in Section 1.1 of the Power Supply Contract.
“Re-Pricing Agreement” means the Re-Pricing Agreement, dated as of the date of issuance of the Bonds, by and between CCCFA and Energy Supplier. “Schedule”, “Scheduled” or “Scheduling” means the actions of a Party and/or its designated representatives, including each Party’s Transmission Providers, if applicable, of notifying, requesting and confirming to each other the quantity of Energy to be delivered during any given portion of the Delivery Period at a specified Delivery Point. “SDCP” means San Diego Community Power, a community choice aggregator as defined in Section 331.1 of the Public Utilities Code.
“Tax Certificate and Agreement” means the Tax Certificate and Agreement executed and delivered by CCCFA in connection with the issuance of the Bonds relating to certain federal income tax compliance requirements relating to the Prepaid Energy Project.
“Transmission Provider(s)” means any entity or entities transmitting or transporting Energy on behalf of a Party to or from an Energy Delivery Point. 520
“Trustee” means U.S. Bank Trust Company, National Association, and its successors as Trustee under the Indenture.

Section 2. Assignment Agreements. With respect to any Assignment Agreement, the Parties acknowledge and agree as follows:
(a) as of the date of this Agreement, SDCP has entered into the Initial Assignment Agreement specified in the Power Supply Contract with respect to its entire Contract Quantity;
(b) subject to the terms of the applicable Assignment Letter Agreement, SDCP may from time to time enter into additional Assignment Agreements with respect to all or a portion of its Contract Quantity; and
(c) SDCP shall determine, independent of CCCFA, when and if any Assignment Agreement is entered into or terminated and the underlying agreement and portion of its Contract Quantity to which such Assignment Agreement relates.

Section 3. Scheduling and Delivery of Assigned Energy. Assigned Energy and any other Assigned Product delivered to CCCFA under the Prepaid Energy Sales Agreement that is attributable to an Assignment Agreement(s) entered into by SDCP shall be attributable to SDCP under the Power Supply Contract, and CCCFA shall have no responsibility for (a) any Scheduling or other operational requirements necessary for the delivery of Assigned Energy to SDCP’s Assigned Delivery Point and the transfer of other Assigned Product to SDCP, or (b) any accounting for under-deliveries or over-deliveries or other record-keeping requirements with respect to any Assigned Energy and other Assigned Product, all of which shall be the sole responsibility of SDCP pursuant to the related Assignment Agreement(s).

Section 4. Qualified Use; Remarketing of Base Energy. As provided in the Power Supply Contract, any portion of SDCP’s Contract Quantity that is not delivered as Assigned Energy is required to be delivered as Base Energy and simultaneously remarketed by Energy Supplier pursuant to the Prepaid Energy Sales Agreement. SDCP shall be responsible for accounting for any portion of SDCP’s Contract Quantity deemed delivered as Base Energy and subsequently remarketed, including accounting for any remediation of any such remarketing sales as may be required pursuant to the Qualifying Use Requirements. SDCP agrees to provide to CCCFA any information reasonably requested by it in order to comply with any reporting or record-keeping requirements related to such deemed deliveries and remarketing of Base Energy, including such information relating to compliance with the Qualifying Use Requirements, as may be required pursuant to the Prepaid Energy Sales Agreement, the Indenture or the Tax Certificate and Agreement.

Section 5. CCCFA Commodity Swap. CCCFA shall not take any action to terminate or designate the early termination of the CCCFA Commodity Swap except in accordance with written instructions of SDCP or unless otherwise required under the terms of the Prepaid Energy Sales Agreement or the Indenture.

Section 6. Directions, Consents and Waivers. CCCFA may be requested or required from time to time to provide certain directions, consents, or waivers under the terms of the Prepaid Energy Sales Agreement, the Indenture and the Re-pricing Agreement. In the event any such direction, consent or waiver relates solely to the Contract Quantity and/or Power Supply 521
Contract of SDCP and no event of default has occurred and is continuing with respect to SDCP under the Power Supply Contract, such direction, consent or waiver shall only be provided by CCCFA in accordance with written instructions provided by SDCP.

Section 7. Re-pricing Information. CCCFA shall provide, or cause Energy Supplier to provide, to SDCP such information as is required to be provided by Energy Supplier to CCCFA in accordance the Re-pricing Agreement at such times as are required under the Re-pricing Agreement.

Section 9. Project Administration Fee; Reimbursement and Refund of Operating Expenses.
(a) Under the Bond Indenture, Operating Expenses (as defined in the Indenture) relating to the Clean Energy Project are to be paid from amounts deposited monthly into the Administrative Fee Fund for each annual period ending on [______] 1 of each year. CCCFA agrees that amounts allocated on behalf of SDCP annually into the Administrative Fee Fund equal to $[_______] in the aggregate for each such annual period (the “Project Administration Fee”), shall be allocated to pay such Operating Expenses as the same become due and payable.

In the event such allocated amounts available in the Operating Fund are not sufficient to pay such Operating Expenses when due, SDCP agrees to pay such additional amounts for deposit into the Administrative Fee Fund as are necessary to pay such Operating Expenses upon receipt of notice of the amount due from the Trustee or CCCFA.
(b) As soon as practicable following the end of each annual period referred to in paragraph (a), CCCFA agrees that the amounts received in respect of the Project Administration Fee for such annual period shall be reconciled with the Operating Expenses paid or accrued for such period. In the event that, following each such reconciliation, it is determined that the amounts received in respect of the Project Administration Fee during the applicable annual period exceed Operating Expenses paid or accrued for such period, SDCP will be provided written notice thereof and the amount of such excess will be included in its Annual Refund under the Power Supply Contract.

Section 10. Notices. Notices and other information to be provided by a Party to any other Party under this Agreement shall be provided in accordance with Article XVI of the Power Supply Contract.

Section 11. Governing Law. This Agreement and the obligations of the Parties hereunder shall be governed by and determined in accordance with the laws of the State of California.

Section 12. Counterparts. This Agreement may be executed and acknowledged in multiple counterparts and by the Parties in separate counterparts, each of which shall be an original and all of which shall be and constitute one and the same instrument. 522
IN WITNESS WHEREOF, the Parties have caused this Agreement to be duly executed and delivered by their respective officers thereunto duly authorized as of the date first above written.

CALIFORNIA COMMUNITY CHOICE

FINANCING AUTHORITY
By: ________________________________
Name: Garth Salisbury
Title: Treasurer/Controller

SAN DIEGO COMMUNITY POWER
By: ________________________________
Name: ______________________________
Title: _______________________________
523
EXHIBIT A6
524
MEMORANDUM OF UNDERSTANDING (“MOU”)
Date: June [__], 2025
To: Eric Washington
Chief Financial Officer
San Diego Community Power
[email protected]
(619) 657-0403
Garth Salisbury
Treasurer – Controller
California Community Choice Financing Authority
[email protected]
(707) 535-9779
From: Morgan Stanley & Co. LLC (“Morgan Stanley”)
Re: California Community Choice Financing Authority Energy Prepayment Financing on behalf of San Diego Community Power
Overview
The California Community Choice Financing Authority (“CCCFA” or the “Issuer”) seeks to procure a 30-year supply of energy, through the issuance of Clean Energy Project Revenue Bonds (the "Bonds") to be issued by CCCFA. The CCCFA will sell all the Prepaid Energy acquired from this transaction to San Diego Community Power (“SDCP”), the “Project Participant.” Rating Agency Fee and SPO Fee
The rating agency fee and expenses (“Rating Agency Fee”) is paid from the proceeds of the Bonds. However, unlike most of the other fees associated with the issuance of the Bonds, payment of the Rating Agency Fee is not contingent upon the issuance of the Bonds.

In the event the Bonds are not issued due to market conditions, and there remains a Rating Agency Fee payable to Moody’s Investors Service or S&P Global Ratings (the “Rating Agency”), Morgan Stanley and CCCFA agree to split this Rating Agency Fee on an equal basis. If the Bonds are not issued due to the CCCFA or the Project Participant’s unwillingness or inability to proceed, other than due to an inability to achieve a minimum established target discount, the Rating Agency Fee will be their sole responsibility. To the extent CCCFA incurs any Rating Agency Fee if the bonds are not issued, the Project Participant agrees that it will be liable for such Rating Agency Fee and make direct payment to the Rating Agency therefor.

The Project Participant has or plans to engage Kestrel to provide a green bond second party opinion (the “SPO”). In the event the SPO is obtained and the Bonds are not issued (unless the Bonds are not issued due to the CCCFA or the Project Participant’s unwillingness or inability to proceed, other than due to an inability to achieve a minimum established target discount), the fee payable to Kestrel (the “SPO Fee”) shall be the responsibility of Morgan Stanley, and in such 525
event, to the extent the SPO Fee was already paid by the Project Participant or by CCCFA, Morgan Stanley agrees to reimburse the Project Participant or CCCFA, as appropriate. To the extent CCCFA incurs any SPO Fee if the bonds are not issued as a result of the Project Participant’s unwillingness or inability to proceed, other than due to an inability to achieve a minimum established target discount, the Project Participant agrees that it will be liable for such SPO Fee and make direct payment to Kestrel therefor, or to CCCFA if the SPO Fee was already paid by CCCFA.

Morgan Stanley shall have no responsibility for any fees or expenses incurred by CCCFA or the Project Participant, or their agents, employees, advisors or counsel, in connection with the issuance of the Bonds and the purchase of the Prepaid Energy, other than the Rating Agency Fee and SPO Fee as described in this MOU and as further described in the Bond Purchase Agreement (as defined herein).

Miscellaneous
CCCFA and Project Participant each acknowledge and agree that: (i) the transaction contemplated by this MOU is, in each case, an arm’s length, commercial transaction between the CCCFA and Morgan Stanley (in its role as “Underwriter” and/or the “Energy Supplier”, as applicable) in which the Underwriter and the Energy Supplier are each acting solely as a principal and not acting as a municipal advisor, financial advisor or fiduciary to CCCFA or the Project Participant; and (ii) CCCFA and the Project Participant will consult their own legal, accounting, tax, financial and other advisors, as applicable, to the extent each has deemed appropriate.

CCCFA acknowledges and agrees that Morgan Stanley is not making a commitment to extend credit, make a loan or otherwise fund the Bonds beyond the obligations contained in a mutually satisfactory bond purchase agreement (the “Bond Purchase Agreement”). CCCFA acknowledges that the services provided under this MOU involve professional judgment on Morgan Stanley’s part and that the results cannot be, and are not, guaranteed.

Nothing contained herein shall preclude the Underwriter from carrying on its customary and usual business activities. The Underwriter specifically reserves the right, but is not obligated, to bid for and maintain secondary markets on any of CCCFA’s outstanding bonds subject to appropriate information barriers. Services provided by the Underwriter in connection with this MOU shall not limit the Underwriter from providing services for CCCFA or the Project Participant in conjunction with other services requested by CCCFA or the Project Participant except as limited by rule of law or regulation.

In connection with the services agreed to herein, it is understood that the Underwriter will render professional services as an independent contractor. Neither the Underwriter nor any of its agents or employees shall be deemed an employee of CCCFA or the Project Participant for any purpose.

Except as described in this paragraph, this MOU is intended to be, and shall be construed only as, a non-binding MOU, intent on summarizing and evidencing discussions between CCCFA, the Project Participant, and Morgan Stanley, as of the date hereof. Except as described below, any legally binding obligation of the parties with respect to the transaction described herein shall exist only upon the execution and delivery of definitive agreements related thereto, into which this MOU 526
and all prior discussions shall merge. It is expressly understood that this MOU is not a contract to execute any definitive agreements or to otherwise consummate the transactions described herein. The parties will cooperate in negotiating definitive agreements providing for the transactions contemplated by this MOU, but each party reserves the right of final approval or disapproval, for any reason, of the documentation relating to such agreements. Notwithstanding the foregoing, the provisions above under the headings “Rating Agency Fee and SPO Fee” shall be binding upon the parties.

Sincerely,
_________________________
Grant Fraunfelder, Executive Director
MORGAN STANLEY & CO. LLC
ACCEPTED AND AGREED:

SAN DIEGO COMMUNITY POWER
By: ____________________________
Name: Eric Washington
Title: Chief Financial Officer
Date: June [__], 2025

CALIFORNIA COMMUNITY CHOICE FINANCING AUTHORITY
By: ____________________________
Name: Garth Salisbury
Title: Treasurer – Controller
Date: June [__], 2025
527

EXHIBIT B
Additional Project Documents
(see attached)
528

APPENDIX A

SAN DIEGO COMMUNITY POWER
Introduction
San Diego Community Power (“SDCP”) is a joint powers authority organized and existing under the Joint Exercise of Powers Act (constituting Chapter 5 of Division 7 of Title 1 (commencing with Section 6500), as amended or supplemented from time to time) (the “Joint Powers Act”), as a “community choice aggregator” (“CCA”) as defined in Section 331.1 of the Public Utilities Code of the State of California, as amended (the “Public Utilities Code”). For a general description of “community choice aggregators” in California, see the section “COMMUNITY CHOICE AGGREGATORS” in this Official Statement.

Formation, History, and Purpose of SDCP
General. SDCP was created on October 1, 2019, under the name “San Diego Regional Community Choice Energy Authority” as a CCA in California under a Joint Powers Agreement, as amended, by and among the cities participating in SDCP and named therein (the “JPA”).

San Diego Community Power was established to provide electricity services at competitive rates to residents and businesses within the municipal boundaries of its member public agencies.

Pursuant to its JPA, SDCP focuses on delivering a cleaner energy portfolio and achieving energy consumption reduction goals and the following key priorities:
• Promotion of Renewable and Distributed Energy Resources: SDCP prioritizes the use and development of local, cost-effective, renewable, and distributed energy sources, supporting local power generation and storage initiatives. Currently, SDCP procures clean energy from solar, wind, geothermal, large-hydro, and biomass sources. • Exclusion of Coal and Avoidance of Nuclear Contracts: SDCP seeks to exclude coal and avoid entering into nuclear contracts as part of its overall procurement strategy. • Economic and Workforce Development: SDCP aims to benefit the region economically by supporting workforce programs and development initiatives, such as working closely and collaboratively with local and regional developers and unions. This helps promote long-term electric rate stability and energy reliability for residents and businesses, by, for example, prioritizing local long-term power purchase agreements that lock in renewable energy supply, allowing SDCP to build its power supply portfolio while also providing power supply cost certainty.
• Community Ownership and Energy Reliability: SDCP promotes personal and community ownership of renewable generation and energy storage resources, in order to foster a sustainable and energy-independent future.

The parties to SDCP’s JPA consist of local governments whose governing bodies elect to join SDCP. Under the Public Utilities Code, when new parties join SDCP, all electricity customers in their jurisdiction, except those served under California’s Direct Access Program, automatically become SDCP’s customers for electric generation, provided customers are allowed to “opt-out.” 529
Commencement of Service and Expansion. SDCP began operations in March 2021 by serving approximately 600 municipal accounts. SDCP enrolled approximately 72,000 municipal and business customers in June 2021. SDCP enrolled approximately 700,000 residential customer accounts throughout 2022 across the city limits of San Diego, Chula Vista, La Mesa, Encinitas, and Imperial Beach. SDCP enrolled approximately 180,000 residential and non-residential customer accounts in National City and Unincorporated areas of San Diego County in 2023. As of April 21, 2025, SDCP was serving 956,724 active accounts with approximately 7,700,000 MWh of annual retail sales.

Service Area
SDCP currently serves seven jurisdictions in the County of San Diego. These jurisdictions include six cities (including San Diego, Chula Vista, Encinitas, La Mesa, Imperial Beach, and National City) and the unincorporated communities of the County of San Diego. SDCP is responsible for acquiring electric power for its service area.

Service Area Map. The service area of SDCP is shown in blue on the map below:

530
Governance and Management
Board of Directors. SDCP is governed by a seven-member board of directors (the “Board of Directors”), with a board member from each of the seven jurisdictions in the County of San Diego. SDCP’s Board of Directors has the rights and powers to set rates for the services SDCP furnishes, incur indebtedness, and issue bonds or other obligations. SDCP’s local government structure ensures public transparency. The Board of Directors meets monthly to discuss matters related to the operation of SDCP. All meetings are open to the public, and public comments are encouraged.

Management.

Karin Burns, Chief Executive Officer. As Chief Executive Officer of SDCP, Karin Burns leads the 2nd largest community choice aggregator in California with a team of mission-driven professionals providing affordable, clean electricity to approximately 956,700 customer accounts in San Diego County. In this capacity, she oversees a budget in excess of $1.0 billion, ensures sufficient and reliable clean power procurement, and develops and executes the organization’s strategic plan in collaboration with the Board and staff.

Before becoming CEO, Karin most recently served as Vice President of Corporate Development and Regional Vice President of the Pacific Region at Franklin Energy, a national provider of energy efficiency, demand response, electrification, and grid optimization solutions.

Before Franklin Energy acquired its assets, Karin served as Chief Executive Officer of Build It Green, where she oversaw a team of 40+ personnel, managed a diverse set of programs across energy efficiency, workforce development, low-income solar and energy efficiency direct installation, healthy homes and reach codes for utilities and local governments.

Previously, Karin served as Executive Director of the nonprofit Code REDD, an environmental company she built into a globally recognized brand. She spearheaded strategic planning and operations, sourced funding from USAID and the McArthur Foundation, and built the successful Stand for Trees campaign.

Before leading high-growth organizations, Karin was a Managing Director at Ambata Capital, where she managed investment and advisory projects in electric vehicles, sustainable agriculture, green buildings, and clean energy. She was previously a Vice President at Gulf Capital, where she sourced, conducted due diligence, and invested in alternative energy, new media, and energy services companies across the Gulf Cooperation Council. She has served on several boards and advisory boards of non-profits, early-stage companies and investment funds from the U.S. to Asia. She began her M&A and corporate finance career at JPMorgan Chase in Hong Kong. Karin earned a Fulbright Scholarship to India, speaks multiple languages, and spent several years overseas in emerging markets from Brazil to China. She has earned Certificates in Energy Innovation and Innovation & Entrepreneurship from Stanford School of Engineering, an M.P.A. in international development from Harvard University, an M.B.A. in finance with distinction from Edinburgh Business School, and a B.A. with Honors from Duke University. 531
Dr. Eric Washington, Chief Financial Officer. Dr. Eric Washington manages SDCP’s annual operating budget, capital investment plan, investment portfolio, and risk management functions. He helps SDCP balance decarbonization goals with the mandate of affordable clean energy at competitive rates. Eric led the development of strategies for SDCP that strengthened the organization’s net asset position and cash flow. He was also critical in growing SDCP’s net revenue from $15 million to over $1 billion in two years. Among his many contributions to SDCP, Eric spearheaded credit facility negotiations, which increased SDCP’s credit access from $35 million to $150 million.

At various points in his career, Eric has managed the administration and compliance of a $350 million nonprofit finance program, managed a $158 million real estate loan portfolio, including construction finance to developers and acquisition finance to real estate investors, and built and managed a diverse team of professionals who provided corporate fiscal analyses, compliance monitoring, and finance reporting in support of several loan officers at various production offices.

Before his role at SDCP, Eric served as a military leader in the U.S. Navy for 26 years, fostering collaboration among diverse teams to meet organizational objectives. Eric also has 25 years of experience in corporate banking and finance. He has served as a vice president, senior credit manager, senior portfolio manager, and senior relationship manager at several regional banking institutions (including California Bank & Trust and Torrey Pines Bank). Eric received his Doctor of Education (Ed.D.) from San Diego State University, M.B.A. from Webster University, and a Bachelor of Science from Southern Illinois University, Carbondale.

Jack Clark, Chief Operating Officer. Jack Clark oversees the day-to-day financial and operational management of SDCP. He works closely with the CEO and CFO to operationalize and execute the strategy and vision for SDCP. Jack has over twenty years of experience overseeing energy, environmental, and cultural programming directed at developing solutions to climate change. Jack has overseen large-scale clean energy market transformation initiatives that help stabilize the relationship between people and the environment.

Before his role at SDCP, Jack was Vice President of Partnerships for commercial vehicle electrification infrastructure at Ideanomics. He was also Senior Director of Customer Programs at Clean Power Alliance of Southern California, California’s largest community choice aggregator.

Before his time at Clean Power Alliance, Jack was Vice President of Sustainable Energy Use at DNV GL.

Before that, Jack was the Deputy Director of the Energy & Sustainability Division at the City of San Diego, where he was responsible for implementing the City’s comprehensive energy strategy, working with staff, other City departments, and community members to incorporate a broad range of energy efficiency, clean, renewable generation, and environmental quality issues into City operations and community programming. He oversaw the city operations of energy use of over 3500 accounts, billing, rates, Municipal Energy Plan, community energy and sustainability programs, compliance with the City Climate Action Plan, and Community Choice Aggregation feasibility analysis on San Diego’s goal of reaching 100% Renewable Electricity by 2035. 532
Prior to his role with the City of San Diego, Jack was the Director of Programs at the Center for Sustainable Energy, where he led the organization's growth from a regional to a national non-profit focusing on strategy, development, and execution of renewable energy, energy efficiency, clean transportation, distributed generation, and advanced clean energy market transformation initiatives. Jack received a Master of Administration in Sustainable Planning and a Bachelor of Science in Anthropology and Environmental Sciences, both from Northern Arizona University.

Veera Tyagi, General Counsel. Veera Tyagi serves as the General Counsel for SDCP.

In this capacity, Veera is responsible for ensuring compliance with general governance laws, regulatory requirements, and overseeing all contracting. Veera brings nearly twenty years of legal experience, primarily as in-house counsel for regulatory agencies, to SDCP. In that capacity, Veera handled various matters, including advising and ensuring compliance with the California Environmental Quality Act, the Federal and State Clean Air Acts, and other environmental laws, and in litigating actions in both federal and state courts that are brought under those laws. Veera also has extensive experience advising on general governmental law issues, including the Public Records Act, the Brown Act, and contract laws. Veera’s background is a Bachelor’s in Environmental Earth Systems Science from Queen’s University, and a Juris Doctorate, Cum Laude from the University of La Verne College of Law. Veera is a member of the State Bar of California.

Chief Commercial Officer (Vacant). SDCP is currently evaluating candidates for the role of Chief Commercial Officer with the position expected to be fulfilled by Q4 2025.

Customers
General. SDCP currently provides energy to approximately 956,700 municipal, residential, commercial, and industrial accounts in its service area. SDCP’s current customer load mix is approximately 41% residential, 37% medium and large commercial/industrial, 19% small commercial, and 3% agricultural and lighting-based.

Customer Energy Choices. As part of its ongoing efforts to provide clean energy at the greatest value for its customers, SDCP offers four service plans: PowerBase, PowerOn, Power100, and Power100 Green+. PowerBase is SDCP’s most affordable service plan and is currently 45% renewable and currently priced with an approximately 5.0% discount under San Diego Gas & Electric (SDG&E) rates. PowerOn is 54% renewable and currently priced approximately 3.0% below SDG&E rates. Power100 and Power100 Green+ are 100% renewable, carbon-free, and the latter is Green-e® certified. PowerOn is SDCP’s default electricity service offering. Most customers within SDCP’s service territory are automatically enrolled in PowerOn, with the exception of the City of Encinitas, whereby per City Council decision, customers within its city limits are automatically enrolled in SDCP’s Power100 service, which costs $0.01/kWh more than PowerOn.

Customers can choose to opt- up to the Power100 and Power100 Green+ options and purchase 100% renewable and carbon-free electricity at a slight premium. These options enable SDCP’s customers to take a more significant step towards reducing their carbon footprint.

Power100 Green+ provides 100% renewable, carbon-free, and Green-e® certified energy for businesses seeking LEED certification or requiring Green-e® certification to meet their corporate 533
social responsibility goals. Power100 Green+ costs $0.02 per kWh more than the standard PowerOn service level. Power100 Green+ allows customers to meet their organization’s reliability standards. Residents and businesses that do not require specific certification can still obtain 100% renewable and carbon-free power through Power100.

In 2025, the average SDCP residential customer is projected to use 341 kWh per month such that PowerOn will cost the average residential customer $1 per month above PowerBase.

Compared to SDG&E’s rates, PowerOn is expected to cost approximately $1.50 per month less for a typical residential customer. Compared to SDG&E’s rates, Power100 is expected to cost about $2 per month extra for a typical residential customer.

Customer Enrollment. Most customers within SDCP’s service territory are automatically enrolled in PowerOn, except for the City of Encinitas, wherein the City Council voted to automatically enroll customers within its city limits in SDCP’s Power100 service. Once enrolled, customers may opt up to Power100 or Power100 Green+ service, opt down to PowerBase service, or opt out of SDCP’s service.

New Customers. FY 2023-24 was SDCP’s first full year of operations, with its seven-member jurisdictions reaching full enrollment. There are no near-term plans for expansion.

Customer Election to Opt-out of Service. Customers have the right to opt out of SDCP service at any time and will not be charged any fees by SDCP if they opt out or cancel electric services. Customers who opt out before starting SDCP service or within the first 60 days of SDCP service may return to SDCP service at any time. Customers who opt out after the first 60 days of service with SDCP will be prohibited by SDG&E from returning to SDCP for one year and will be charged a one-time customer re-entry fee by SDG&E and will also be required to choose one of two options: an immediate return to SDG&E service, or a 6-month return to SDG&E service.

Cumulative Opt-Out Rate and Customer Retention. As of April 21, 2025, SDCP is serving a cumulative total count of 956,724 active accounts for a total participation rate of 95.4%.

Customers with newly established accounts or who have moved into a new service address within any of SDCP’s member jurisdictions receive two post-enrollment notices through the mail at their mailing address on file within 60 days of their account start date to notify them that they have defaulted to SDCP electric generation service.

The following graphic illustrates SDCP’s opt-out rate and customer retention data through April 21, 2025, reflected as a percentage of participation rates by jurisdiction. 534
535
Service Rates
General. SDCP electric generation rates are managed to provide cleaner electricity at competitive rates. SDCP’s Board of Directors determines rates and SDCP’s rates are not regulated by the California Public Utilities Commission (the “CPUC”). Any rate changes will be adopted at duly noticed public meetings of the SDCP Board of Directors. Under the terms of the Clean Energy Purchase Contract, SDCP covenants that it will establish, maintain, and set rates and charges to provide revenues sufficient to enable it to pay all amounts payable from the revenues of its operations and to keep any reserves as required by SDCP’s reserve policies. SDCP further covenants pursuant to the terms of the Clean Energy Purchase Contract that it will not grant any lien or security interest in, or otherwise pledge or encumber revenues if the effect of such lien, pledge or other encumbrance would result in such lien, pledge or encumbrance having priority over the obligations of SDCP under the Clean Energy Purchase Contract.

Determination of Rates for Energy. A customer’s cost of electric service is determined by SDCP’s charges for energy and SDG&E charges for transmission, distribution, and other non-by-passable charges. Changes to SDG&E or SDCP rates will impact cost comparisons between SDCP and SDG&E. SDG&E charges SDCP customers a monthly Power Charge Indifference Adjustment, which can vary annually based upon several market factors, including benchmarks for regional energy costs, resource adequacy, the year in which the community joined SDCP and other considerations, as well as a Franchise Fee Surcharge. SDCP has already accounted for these additional charges when calculating its commodity rates. Financial assistance programs like CARE (California Alternative Rates for Energy), FERA (Federal Electric Rate Assistance), and Medical Baseline Allowance remain the same for SDCP and SDG&E customers.

Current and Historical Rate Information. SDCP rates are designed to cover the costs of energy, resource adequacy, and operating, fund customer programs, and meet SDCP’s reserve and liquidity goals, as described in its Reserve Policy.

On January 18, 2024, the Board of Directors approved rates for SDCP that included:
• A 17.7% year-over-year average decrease, from 2023 to 2024, in SDCP electricity generation rates across all customer classes.
• A 23.2% year-over-year average decrease, from 2023 to 2024, in SDCP electricity generation winter rates and a 12.3% year-over-year average decrease in summer rates across all customer classes.
• Rates that support SDCP to maintain its current reserve levels and to allow it to work toward a 180-day cash-on-hand reserve target, with the goal of providing financial stability and support a credit rating.

Subsequently, on May 30, 2024, the Board of Directors approved the new PowerBase product offering that was effective July 1, 2024, which provided:
• A 2.5% discount for July through December 2024, compared to SDGE’s current rates as of March 1, 2024.
• A pathway for customers to return to SDCP’s standard service, PowerOn, or opt-up to Power100 more easily than if they opted out of SDCP service entirely. 536
• Support for SDCP’s mission to provide an affordable option that is cleaner than the competition.
• For 100% renewable energy by 2035 or sooner through customer retention, especially for price-sensitive customers.

On May 30, 2024, the Board of Directors approved the Power100 Green+ product offering, a stand-alone, 100% renewable, carbon-free energy service that is Green-e® certified. Power100 Green+ is priced as a $0.02/kWh adder to the PowerOn service and allows SDCP customers to earn LEED Tier 2 or 3 points in the renewable energy category. Currently, Power100 Green+ is only available to commercial and industrial customers.

Effective February 1, 2025, SDCP implemented rate changes resulting in the following comparisons for most SDCP customers, though exact comparisons may vary by rate schedule and customer usage:
• SDCP PowerOn is set at a ~3% discount to SDG&E’s rates on a total bill basis. • SDCP PowerBase is set at a ~5% discount to SDG&E's rates on a total bill basis.

SDCP’s Power100 and Power100 Green-e Certified services will maintain premiums of $0.01/kWh and $0.02/kWh, respectively.

California Renewable Portfolio Standards and Other Regulations General. Community choice aggregators such as SDCP are “load-serving entities” (“LSEs”) and, as such, are required to comply with California’s Renewable Portfolio Standard, Resource Adequacy requirements, and Power Source Disclosure requirements described below.

Renewable Portfolio Standard. California’s Renewable Portfolio Standard (“RPS”) requires LSEs to supply their retail sales with certain minimum quantities of eligible renewable energy. Senate Bill 100 directs all LSEs to procure 60% of their portfolios from RPS-eligible resources by 2030 and 100% of their retail sales from zero-carbon resources (or eligible renewable resources) by 2045. Based on the most recent Power Content Label filed with the California Energy Commission, in 2023, SDCP met 58.8% of its total retail sales with eligible RPS resources, which was above the 2023 RPS percentage target of 41.3%. SDCP has exceeded the annual RPS regulatory minimum requirements each year since its inception.

Resource Adequacy. Resource Adequacy (“RA”), a California program jointly administered by the CPUC, the California Energy Commission (“CEC”) and the California Independent System Operator (“CAISO”), directs LSEs to secure forward capacity and offer it into the CAISO’s Day-Ahead and Real-Time markets to ensure that there will be enough supply at suitable locations and with sufficient ramping capability to meet load. The RA program is comprised of three products: System RA, Local RA, and Flexible RA. Local RA obligations have been assigned to a Central Procurement Entity as of 2023.

Integrated Resource Planning. Integrated Resource Planning (“IRP”) requires LSEs to forecast their customer load and develop a plan to serve such load in alignment with their own vision and values and in accordance with regulatory requirements. In October 2015, California 537
codified this LSE responsibility with the passage of SB 350, which requires the CPUC to establish and oversee an IRP process to assist with meeting the state’s aggressive GHG targets (40% below 1990 levels by 2030). The IRP process, which is used in many states across the US, generally produces 10- to 20-year plans that map out both the supply-side and demand-side resources required for meeting customer load. Given the complexity of the grid and the time required to plan and build generating facilities, IRPs are critical for ensuring safe, reliable and clean power in a cost-effective manner. In addition to addressing the long-term planning horizon typical of an IRP process, the IRP process has been used in recent years to direct procurement of new capacity to meet near- and mid-term reliability and clean energy needs per CPUC Decision (“D.”) 19-11-016, D. 21-06-035 and D. 23-02-040. Pursuant to the procurement orders in these CPUC Decisions, LSEs are required to procure “Incremental System Capacity,” which is RA capacity from non-emitting, storage, and/or renewable resources that are in addition to the resources identified on a baseline list of existing, on-line and operating resources. SDCP has a strong track record of meeting its RA obligations, falling short only during periods of extreme resource scarcity. SDCP expects to meet its future RA obligations through its Energy Risk Management Policy to the extent that supply is available in the bilateral markets
Power Source Disclosure. California law requires LSEs to disclose the types of power resources used to supply retail sales. This mandate, known as the Power Source Disclosure Program (“PSDP”), is a consumer information program managed by the CEC. A key output of the PSDP is the Power Content Label (“PCL”). The PCL is an LSE-specific document that shows the breakdown of power resource types for each of the LSE’s energy products used to serve retail load and a breakdown of resource types for the overall California grid. The PCL is distributed to customers each year.

Energy Demand
Long-Term Load Forecast. SDCP’s long-term load forecast is a projection of the electricity that SDCP’s customers will consume. SDCP’s long-term load forecast considers the number and types of customers that SDCP expects to serve, historical electricity use patterns, temperature, and other weather conditions, as well as trends in energy efficiency, behind-the-meter, rooftop solar and electric vehicle adoption, appliance electrification, and other factors.

The table below shows SDCP’s long-term load forecast for 2025-2034 based on SDCP’s 2023 RPS Compliance Report filed with the CPUC on January 25, 2024. 538
Sources of Energy
General. In its procurement of energy supplies, SDCP prioritizes using and developing local renewable resources, stimulating local job creation through various programs and development, promoting personal and community ownership of distributed renewable resources, and promoting long-term electric rate stability and energy reliability for residents and businesses.

Energy Purchases. During the ordinary course of business, SDCP purchases electrical power from numerous suppliers. Electricity costs include the cost of energy and capacity arising from bilateral contracts with energy suppliers, generation credits, load, and other charges stemming from SDCP’s participation in the CAISO’s centralized market.

As SDCP strives to meet its environmental, financial, and regulatory compliance goals and requirements, long-term power purchase agreements (“PPAs”) are becoming integral components of its energy supply portfolio. Long-term PPAs provide renewable generation facility developers with a specific revenue stream against which they can finance upfront capital requirements, such that each long-term PPA that SDCP signs with a developing facility will underpin a new, incremental renewable energy project. In addition, long-term PPAs lock in renewable energy supply around which SDCP can build its power supply portfolio while providing cost certainty so that SDCP can develop its pro forma financial model. Moreover, the California RPS, modified in 2015 by Senate Bill 350, requires that SDCP provide 65% of its RPS-required renewable energy from contracts of at least ten years. Finally, in D.21-06-025, the CPUC required each LSE in California to make significant long-term purchase commitments for resource adequacy from new, incremental generation facilities that will achieve commercial operation during 2023 through 2026 for purposes of “Mid Term Reliability”. These requirements have been augmented and extended into 2026 and 2027 via CPUC’s D.23-02-040.

Over the past 18 months, SDCP staff released four requests for proposals (“RFPs”) for eligible Renewable Energy resources, including an RFP for Stand Alone Storage projects and an RFP for clean firm energy, in pursuit of long-term contracts for renewable energy. SDCP evaluated other contracting opportunities to meet SDCP’s procurement goals. The SDCP Board, through April 2025, has approved contracts for over 1,670 MW of renewable generation and over 1,960 MW of storage capacity. SDCP staff continues to negotiate with several other developers for Table 1: SDCP's 2025-2034 Load Forecast (MWh)
Year Load Forecast
2025 8,094,390
2026 8,239,804
2027 8,386,117
2028 8,428,047
2029 8,470,187
2030 8,512,538
2031 8,555,101
2032 8,597,877
2033 8,640,866
2034 8,684,070
539
additional renewable energy resources expected to be online between 2025 and 2029. Under CAISO’s revisions to their cluster study process for interconnecting future projects, SDCP staff issued an RFP in August 2024 for CAISO Cluster 15 projects, which will serve as a source of renewable and storage projects that SDCP is most interested in getting studied by the CAISO.

SDCP staff and the Energy Contracts Working Group (the “ECWG”) evaluate all RFP submissions before entering into negotiations with selected participants. Assuming that SDCP staff and shortlisted developer(s) can agree to mutually agreeable contracts consistent with terms authorized by the ECWG, SDCP staff then review the draft terms with the SDCP Board for approval and authorization for the CEO to execute the relevant documents.

SDCP also has an open request for information regarding local projects (“RFI”). The RFI has yielded eight board-approved contracts for local generation and storage facilities in the last twelve months. SDCP also released a request for offers (“RFO”) for distributed renewable energy resources (“DERs”), which focuses on a broad range of distribution-level renewable projects within San Diego County. The RFO has yielded two board approved contracts for ~25 MW of capacity.

Energy Load and Supply Risk Management. Through SDCP’s Energy Risk Management Policy, SDCP measures and updates its risks using various tools that model programmatic financial projections, market exposure, risk metrics, and short-term budget updates. The following items are measured, monitored, and reported:
• Mark-to-Market Valuation – marking to market determines the current value of contracted energy supply.
• Exposure Reporting – calculates the notional dollar risk exposure and value at risk of open portfolio positions at current market prices.
• Open Position Monitoring— calculates/monitors open positions for all energy and capacity products monthly. If energy open positions for the month following the then current month (prompt month) exceed 10% of the load, SDCP will solicit market energy to close open positions and make a commercial decision to close the position. • Counterparty Credit Exposure – calculates the notional and mark-to-market exposure to each SDCP counterparty by deal and in the aggregate. Counterparty exposure reporting includes contingent collateral posting risks arising from changes in market prices and other factors.
• Reserve Requirement Targets – no less than once per year, SDCP staff monitors SDCP’s financial reserves to ensure that they meet the targeted thresholds.

SDCP manages market price risk using its planning models, which define forecasted load, energy under contract, and SDCP’s open positions across various energy product types, including renewable energy (Portfolio Content Category I, II, and III), carbon-free energy, and system power relative to SDCP’s procurement targets.

Generally, SDCP manages its exposure to energy suppliers by exhibiting a preference for counterparties with investment-grade credit ratings as determined by Moody’s or S&P Global Ratings and using security requirements in the form of cash or letters of credit. SDCP measures its mark-to-market counterparty credit exposure in a way consistent with industry best practices. 540
SDCP manages energy delivery risks by ensuring that contracts include appropriate contractual penalties for non-delivery and acquiring energy from a geographically and technologically diverse portfolio of generating assets (with a range of generation profiles generally complementary to how SDCP’s customers use electric power). Due to known production variability and supply uncertainty related to renewable and other carbon-free energy products, SDCP includes planning margins in procuring such products to ensure that related targets/mandates are achieved.

SDCP manages load forecasting and related weather risks by contracting with qualified data management and scheduling coordinators. These coordinators independently or jointly provide the systems and data necessary to forecast and schedule load using good utility practice.

Load variability is also considered when establishing appropriate planning margins for renewable and carbon-free energy sources.

SDCP manages its regulatory and legislative risk through active participation in working groups and advocacy coalitions, such as the California Community Choice Association. SDCP also regularly participates in regulatory rulemaking proceedings and legislative affairs to protect its interests.

Procurement. All contracting for energy and energy-related products for SDCP, including but not limited to electricity, capacity, energy efficiency, distributed energy resources, demand response, and storage, are overseen by SDCP’s Power Services department. All contracts are further reviewed and approved by SDCP’s CEO and General Counsel. SDCP procures energy and RA in a way that is consistent with its Energy Risk Management Policy. Procurement is conducted through market-based transactions for products, including Fixed Price Energy, Portfolio Content Category 1 Renewable Energy, Portfolio Content Category 2 Renewable Energy, Carbon-Free Energy, and RA Capacity, as well as through longer-term PPAs entered into pursuant to statutory requirements or voluntary long-term resource acquisition decisions made independently by SDCP under its Integrated Resource Plan or other Board or Director-approved strategies.

Short-term procurement is conducted through participation in the CAISO and bilateral markets. SDCP may use various methods to procure long-term contracts, including competitive solicitations, bilaterally negotiated agreements, or regulatory proceedings, with oversight, including shortlist approvals or procurement recommendations, provided by the ECWG of the Board. Specific long-term procurement (e.g., contract terms longer than three years) is subject to Board approval.

Long-term Contracts. To date, SDCP has contracted for ~1,670 MW of nameplate capacity for renewable energy generation and 1,960 MW of nameplate capacity for energy storage projects, identified in Table 2 below, with expected commercial operation dates between 2024 and 2029. 541
Table 2: Long Term Contracts
Developer/
Project
Guaranteed
Commercial
Operation
Date
Nameplate Type
Ormat / Pomona
2 Online 10 MW Storage (2-hour)
Arevon / Vikings
Energy Farm
Online 136.8 MW-AC Generating Facility
and
145.5 MW-AC / 582 MWh Storage
Facility
Solar + Storage
Pattern / Duran
Mesa
Online 50 MW Wind
Intersect /
Oberon II
Online 75 MW Solar
Ormat /
Arrowleaf Solar
and Storage
4/15/25 42 MW-AC Generating Facility and
35 MW-AC / 140 MWh Storage
Facility
Solar + Storage
NextEra /
Yellow Pine
Solar:
6/1/27
Storage:
6/1/27
35 MW-AC Generating Facility and
35 MW-AC / 140 MWh Storage
Facility
Solar + Storage
SBE / Athos 1/1/26 200 MW Storage
Aypa / Vidal 12/1/26 160 MW (solar)
160 MW (storage)
Solar + Storage
Arevon / Avocet 4/15/26 200 MW Storage
MRP / Border 6/1/26 52 MW Storage (1-hour)
MRP / Enterprise 6/1/26 52 MW Storage (1-hour)
Wellhead /
CVEC2
6/1/26 49.7 MW Storage
Baywa / JVR
Energy Park
10/31/26 90 MW-AC solar photovoltaic
Generation Facility combined with a
70 MW-AC / 280 MWh-AC DC-coupled battery energy storage facility
Solar + Storage
Pattern / SunZia 3/31/27 150 MW Wind
NextEra / Desert
Sands
6/1/27 60 MW Long Duration
Storage
SBE / Pelicans
Jaw
9/1/26 440 MW (solar)
238.5 MW (storage)
Solar + Storage
Nobel Solar /
Purple Sage
6/1/28 400 MW (solar)
400 MW (storage)
Solar + Storage
Aypa / Euismod 6/1/28 200 MW Storage
542
Information Technology, Data Analytics and Cyber Security SDCP’s Information Technology (“IT”) and Data Analytics department is comprised of professionals who handle all aspects of information technology management, cloud infrastructure, and cybersecurity. This department is building a secure data platform that will enable and empower SDCP staff to develop full-scale in-house data management, data engineering, data science, and analytics capabilities. SDCP’s IT and Data Analytics Team focus on developing core operational competencies such as an Energy Trade & Risk Management application or Distributed Energy Resource Management platform to deliver efficiencies, simplifications, and cost savings for SDCP customers.

This department also oversees and is accountable for developing additional IT policies and standards, including responsible Artificial Intelligence and cybersecurity, identifying risk areas, and helping all personnel comply with policies and standards. All SDCP staff are responsible for reporting any noncompliance to management. SDCP makes information technology accessible only to authorized employees or designated vendors as needed, and only for authorized agency purposes.

SDCP’s IT and Data Analytics department has begun a holistic cybersecurity program leveraging the NIST 800 framework and ISO 27001 standards. SDCP’s current and new cybersecurity standards work to minimize threats and exposure to its assets and information.

SDCP additionally holds cybersecurity insurance coverage.

Financial Information
Revenues from Energy Sales and Operating Expenses. SDCP’s operating revenues are from selling electricity to commercial and residential customers throughout its territory. SDCP reports its revenue net of uncollectible accounts. In alignment with SDCP’s reserve policy and strategic goals, SDCP set rates in 2023,2024 and 2025 sufficient to grow revenue and net income to reach its 180-day cash-on-hand goal.

Other Sources of Revenue. In 2023, SDCP began receiving grant revenue from the California Public Utilities Commission Disadvantaged Communities-Green Tariff and Community Solar Green Tariff programs, which enable residential customers in disadvantaged communities who may be unable to install solar on their roof to benefit from a local solar project and receive a 20% bill discount. This funding originates from California Greenhouse Gas Auction Proceeds and Public Purpose Program funds.

In 2024, SDCP was also awarded $710,000 in grant funding from the California Department of Food and Agriculture to support its provision of technical assistance and refrigeration units to stock healthy food at stores in low income or low food-access areas throughout its service territory.

In January 2025, SDCP accepted, appropriated and developed plans to expend $124.27 million of funds from the CPUC to administer and implement energy efficiency programs focused on underserved and hard-to-reach residents, businesses, and public agencies in the region. Funds will be expended through the FY2025-29 capital investment plan. 543
SDCP additionally derives revenue from investment income. As SDCP’s operating reserves have grown, its investment income has also grown in lockstep as SDCP invests its reserves in interest-bearing accounts consistent with SDCP’s Investment Policy approved by the SDCP Board on June 27, 2024.

Financial Statements. For financial information related to SDCP, see the annual audited financial statements of SDCP for the fiscal years that ended June 30, 2024 and June 30, 2023, which are attached to this Official Statement as Appendix B.

Financial Reserves. SDCP maintains financial reserves, pursuant to the Financial Reserve Policy adopted by the Board of Directors, to be able to (a) meet SDCP’s strategic objectives; (b) secure, maintain, and improve a standalone investment grade credit rating; (c) secure favorable terms with vendors, including power producers; (d) satisfy working capital requirements; (e) adhere to contractual covenants; (f) provide funds to cover unanticipated expenditures; and (g) support rate stability.

Operating Reserve. SDCP maintains a reserve goal to secure 180 days of cash-on-hand held as unrestricted cash. Unrestricted cash equals total cash less cash held in accounts that are restricted from use (e.g., as collateral or by covenant). The contribution to operating reserves is determined through SDCP’s annual budget process as defined in the agency’s Budget Policy and SDCP’s rate-setting process as defined in the agency’s Rate Development Policy. To the extent that SDCP can meet operational expenses and maintain competitive rates, it will establish rates and adopt budgets to build and maintain its operating reserves at or above the 180-day cash-on-hand target level. As of March 31, 2025, its unrestricted net position totaled $401 million.

Risk Management. SDCP maintains a comprehensive risk management framework to identify and mitigate credit, liquidity, market, operational, regulatory, and other risks associated with participation in the California energy market. The framework employs credit risk strategies, including a preference for transacting with investment-grade counterparties, establishing credit limits, and securing collateral when necessary. SDCP utilizes hedging strategies, netting arrangements, and liquidity monitoring to address market risks. Internal controls and compliance mechanisms are in place to manage operational and regulatory risks, ensuring adherence to legal and market regulations. Risk monitoring and oversight are continuously performed through frequent reporting, with critical risks communicated promptly to stakeholders. This integrated approach enables SDCP to maintain a balanced risk profile while adapting to evolving market conditions.
544

GLOSSARY OF TERMS
AB – Assembly Bill - An Assembly Bill is a piece of legislation that is introduced in the Assembly. In other words, the Assembly, rather than the Senate, is the house of origin in the legislature for the legislation. In California, it is common for legislation to be referred to by its house of origin number (such as, AB 32) even once it becomes law.

AL - Advice Letter - An Advice Letter is a request by a CPUC jurisdictional entity for Commission approval, authorization, or other relief.

ALJ – Administrative Law Judge - ALJs preside over CPUC cases to develop the evidentiary record and draft proposed decisions for Commission action.

ARB – Air Resources Board - The California Air Resources Board (CARB or ARB) is the "clean air agency" in the government of California. CARB is charged with protecting the public from the harmful effects of air pollution and developing programs and actions to fight climate change.

AReM – Alliance for Retail Energy Markets - a not for profit corporation that advocates for continued development of successful customer choice in retail energy markets and provides a focused voice for competitive energy retailers and their customers in selected public policy forums on the state level. AREM represented direct access providers such as Constellation NewEnergy and Direct Energy.

BayREN - Bay Area Regional Energy Network - BayREN offers region-wide energy programs, services and resources to members of the public by promoting energy efficient buildings, reducing carbon emissions and building government capacity.

CAISO – California Independent System Operator - a non-profit independent system operator that oversees the operation of the California bulk electric power system, transmission lines and electricity market generated and transmitted by its members (~80% of California’s electric flow).

Its stated mission is to “operate the grid reliably and efficiently, provide fair and open transmission access, promote environmental stewardship and facilitate effective markets and promote infrastructure development.” CAISO is regulated by FERC and governed by a five-member governing board appointed by the governor.

CALCCA – California Community Choice Association – Association made up of Community Choice Aggregation (CCA) groups which represents the interests of California’s community choice electricity providers.

CALSEIA – California Solar Energy Industries - CALSEIA represents more than 200 companies doing solar-related business in California, including manufacturers, distributors, installation contractors, consultants, and educators. Members' annual dues support professional staff and a lobbyist who represent the common interests of California's solar industry at the Legislature, Governor's Office, and state and local agencies.
545
CALSLA – California City County Street Light Association - statewide association representing cities, counties and towns before the CPUC that is committed to maintaining fair and equitable street light electric rates and facilities charges, and disseminating street light related information.

CAM – Cost Allocation Mechanism - the cost recovery mechanism to cover procurement costs incurred in serving the central procurement function.

CARB – California Air Resources Board – The CARB is charged with protecting the public from the harmful effects of air pollution and developing programs and actions to fight climate change in California.

CARE – California Alternative Rates for Energy - A State program for low-income households that provides a 30% discount on monthly energy bills and a 20% discount on natural gas bills.

CARE is funded through a rate surcharge paid by all other utility customers.

CBE – Communities for a Better Environment - environmental justice organization that was founded in 1978. The mission of CBE is to build people’s power in California’s communities of color and low-income communities to achieve environmental health and justice by preventing and reducing pollution and building green, healthy and sustainable communities and environments.

CCA – Community Choice Aggregator - A community choice aggregator, sometimes referred to as community choice aggregation, allows local governments to procure power on behalf of their residents, businesses, and municipal accounts from an alternative supplier while still receiving transmission and distribution service from their existing utility provider. CCAs are an attractive option for communities that want more local control over their electricity sources, more green power than is offered by the default utility, and/or lower electricity prices. By aggregating demand, communities gain leverage to negotiate better rates with competitive suppliers and choose greener power sources.

CCSF – City and County of San Francisco - The City and County of San Francisco often engage in joint advocacy before the CPUC. San Francisco operates CleanPowerSF, a CCA.

CEC – California Energy Commission - the primary energy policy and planning agency for California, whose core responsibilities include advancing state energy policy, achieving energy efficiency, investing in energy innovation, developing renewable energy, transforming transportation, overseeing energy infrastructure and preparing for energy emergencies.

CEE – Coalition for Energy Efficiency - non-profit comprised of US and Canadian energy efficiency administrators working together to accelerate the development and availability of energy efficient products and services.

CLECA – California Large Energy Consumers Association - an organization of large, high load factor industrial customers located throughout the state; the members are in the cement, steel, industrial gas, pipeline, beverage, cold storage, food packaging, and mining industries, and share the fact that electricity costs comprise a significant portion of their costs of production. Some members are bundled customers, others are Direct Access (DA) customers, and some are served by Community Choice Aggregators (CCAs); a few members have onsite renewable generation.

CPUC – California Public Utility Commission - state agency that regulates privately owned electric, natural gas, telecommunications, water, railroad, rail transit, and passenger transportation companies, in addition to authorizing video franchises. 546
C&I – Commercial and Industrial – Business customers. C&I customers generally consume much higher volumes of electricity and gas. Many utilities segment their C&I customers by energy consumption (small, medium and large).

CP – Compliance Period – Time period to become RPS compliant, set by the CPUC (California Public Utilities Commission)
DA – Direct Access – An option that allows eligible customers to purchase their electricity directly from third party providers known as Electric Service Providers (ESP).

DA Cap – the maximum amount of electric usage that may be allocated to Direct Access customers in California, or more specifically, within an Investor-Owned Utility service territory.

DACC – Direct Access Customer Coalition a regulatory advocacy group comprised of educational, governmental, commercial and industrial customers that utilize direct access for all or a portion of their electrical energy requirements
DA Lottery – a random drawing by which DA waitlist customers become eligible to enroll in DA service under the currently-applicable Direct Access Cap.

DA Waitlist – customers that have officially registered their interest in becoming a DA customer but are not yet able to enroll in service because of DA cap limitations.

DAC – Disadvantaged Community - Disadvantaged communities refers to the areas throughout California which most suffer from a combination of economic, health, and environmental burdens. These burdens include poverty, high unemployment, air and water pollution, presence of hazardous wastes as well as high incidence of asthma and heart disease.

One way that the state identifies these areas is by collecting and analyzing information from communities all over the state. CalEnviroScreen, an analytical tool created by the California Environmental Protection Agency (CalEPA), combines different types of census tract-specific information into a score to determine which communities are the most burdened or "disadvantaged."
DASR – Direct Access Service Request – Request submitted by C&I customers to become direct access eligible.

Demand - The rate at which electric energy is delivered to or by a system or part of a system, generally expressed in kilowatts (kW), megawatts (MW), or gigawatts (GW), at a given instant or averaged over any designated interval of time. Demand should not be confused with Load or Energy.

DER – Distributed Energy Resource – A small-scale physical or virtual asset (e.g. EV charger, smart thermostat, behind-the-meter solar/storage, energy efficiency) that operates locally and is connected to a larger power grid at the distribution level.

Distribution - The delivery of electricity to the retail customer’s home or business through low voltage distribution lines.

DLAP – Default Load Aggregation Point – In the CAISO’s electricity optimization model, DLAP is the node at which all bids for demand should be submitted and settled. 547
DR – Demand Response - An opportunity for consumers to play a significant role in the operation of the electric grid by reducing or shifting their electricity usage during peak periods in response to time-based rates or other forms of financial incentives.

DRP – Distributed Resource Plans - plans that are required by statute that are intended to identify optimal locations for the deployment of distributed resources.

DWR – Department of Water Resources – DWR manages California’s water resources, systems, and infrastructure in a responsible, sustainable way.

ECR – Enhanced Community Renewable - An IOU program that reflects the "Community Solar" model of renewable energy purchasing. Customers sign up to purchase a portion of a local solar project directly from a Developer at a level that meets at least 25% of their monthly electricity demand, but up to 100%. The customer will pay the Developer for the subscribed output, and receive a credit on their utility bill that reflects their enrollment level.

ED – Energy Division - The CPUC's Energy Division develops and administers energy policy and programs to serve the public interest, advise the Commission, and ensure compliance with the Commission decisions and statutory mandates.

EE – Energy Efficiency- the use of less energy to perform the same task or produce the same result. Energy-efficient homes and buildings use less energy to heat, cool, and run appliances and electronics, and energy-efficient manufacturing facilities use less energy.

ELCC – Effective Load Carrying Capacity – The additional load met by an incremental generator while maintaining the same level of system reliability. For solar and wind resources the ELCC is the amount of capacity which can be counted for Resource Adequacy purposes.

EPIC – Electric Program Investment Charge – The EPIC program was created by the CPUC to support investments in clean energy technologies that provide benefits to the electricity ratepayers of PG&E, San Diego Gas & Electric Company (SDG&E), and Southern California Edison Company (SCE)
ERRA – Energy Resource Recovery Account – ERRA proceedings are used to determine fuel and purchased power costs which can be recovered in rates. The utilities do not earn a rate of return on these costs, and only recover actual costs. The costs are forecast for the year ahead. If the actual costs are lower than forecast, then the utility gives money back, and vice versa.

ES – Energy Storage - the capture of energy produced at one time for use at a later time to reduce imbalances between energy demand and energy production.

ESA – Energy Storage Agreement - means a battery services contract, a capacity contract, demand response contract or similar agreement.

ESP – Energy Service Provider - An energy entity that provides service to a retail or end-use customer.

EV – Electric Vehicle - a vehicle that uses one or more electric motors for propulsion.

FCR – Flexible Capacity Requirements - “Flexible capacity need” is defined as the quantity of resources needed by the CAISO to manage grid reliability during the greatest three-hour continuous ramp in each month. Resources will be considered as “flexible capacity” if they can sustain or increase output, or reduce ramping needs, during the hours of “flexible need.” “FCR” 548
means the flexible capacity requirements established for LSEs by the CPUC pursuant to the CPUC Decisions.

GHG – Greenhouse gas - water vapor, carbon dioxide, tropospheric ozone, nitrous oxide, methane, and chlorofluorocarbons (CFCs). A gas that causes the atmosphere to trap heat radiating from the earth. The most common GHG is Carbon Dioxide, though Methane and others have this effect as well.

GRC – General Rate Case – Proceedings used to address the costs of operating and maintaining the utility system and the allocation of those costs among customer classes. For California’s three large IOUs, the GRCs are parsed into two phases. Phase I of a GRC determines the total amount the utility is authorized to collect, while Phase II determines the share of the cost each customer class is responsible and the rate schedules for each class. Each large electric utility files a GRC application every three years for review by the Public Advocates Office and interested parties and approval by the CPUC.

GTSR – Green Tariff Shared Renewables - The GTSR program enables customers to receive 50 to 100 percent of their electricity demand from renewable sources. The GTSR program has two components: the Green Tariff (GT) component and the Enhanced Community Renewables (ECR) component. Through GT, a customer may pay the difference between their current generation charge and the cost of procuring 50 to 100 percent renewables. With ECR, a customer agrees to purchase a share of a community renewable (typically solar) project directly from a developer, and in exchange will receive a credit from their utility for the customer’s avoided generation procurement.

GWh – Gigawatt-hour - The unit of energy equal to that expended in one hour at a rate of one billion watts. One GWh equals 1,000 megawatt-hours.

ICA – Integration Capacity Analysis - The enhanced integrated capacity and locational net benefit analysis quantifies the capability of the system to integrate Distributed Energy Resources (DERs) within the distribution system. Results are dependent on the most limiting element of the various power system criteria such as thermal ratings, power quality, system protection limits and safety standards of existing equipment.

IDER – Integrated Distributed Energy Resources – A CPUC proceeding that aims to more effectively coordinate the integration of demand-side resources in order to better meet customer and grid needs, while enabling California to attain its greenhouse gas reduction goals.

IDSM – Integrated Demand-Side Management - an approach that joins together all the resources utilities have at their disposal to plan, generate and supply electricity in the most efficient manner possible.

IEP – Independent Energy Producers – California’s oldest and leading nonprofit trade association, representing the interest of developers and operators of independent energy facilities and independent power marketers.

IMD – Independent Marketing Division - Under state law, IOUs are prohibited from lobbying or marketing on community choice unless the IOU forms an independent marketing division funded by shareholders rather than ratepayers. SDG&E’ and its parent company Sempra were permitted by the CPUC to create such an independent marketing division, which allowed SDG&E to lobby against plans to create a CCA program.

IOU – Investor-Owned Utility – A private electricity and natural gas provider, such as SDG&E, PG&E or SCE, which are the three largest IOUs in California. 549
IRP – Integrated Resource Plan – A plan which outlines an electric utility’s resource needs in order to meet expected electricity demand long-term.
kW – Kilowatt – Measure of power where power (watts) = voltage (volts) x amperage (amps) and 1 kW = 1000 watts
kWh – Kilowatt-hour – This is a measure of consumption. It is the amount of electricity that is used over some period of time, typically a one-month period for billing purposes. Customers are charged a rate per kWh of electricity used.

LCE – Lancaster Choice Energy - the CCA that serves the City of Lancaster, California.

LCFS – Low Carbon Fuel Standard – A CARB program designed to encourage the use of cleaner low-carbon fuels in California, encourage the production of those fuels, and therefore, reduce greenhouse gas emissions.

LCR – Local (RA) Capacity Requirements – The amount of Resource Adequacy capacity required to be demonstrated in a specific location or zone.

LMP – Locational Marginal Price – Each generator unit and load pocket is assigned a node in the CAISO optimization model. The model will assign a LMP to the node in both the day- ahead and real time market as it balances the system using the least cost. The LMP is comprised of three components: the marginal cost of energy, congestion and losses. The LMP is used to financially settle transactions in the CAISO.

LNBA – Locational Net Benefits Analysis - a cost-benefit analysis of distributed resources that incorporates location-specific net benefits to the electric grid.

Load - An end use device or customer that receives power from an energy delivery system. Load should not be confused with Demand, which is the measure of power that a load receives or requires. See Demand.

LSE – Load-serving Entity – Entities that have been granted authority by state, local law or regulation to serve their own load directly through wholesale energy purchases and have chosen to exercise that authority.

LTPP – Long-Term Procurement Rulemaking - This is an “umbrella” proceeding to consider, in an integrated fashion, all of the Commission’s electric procurement policies and programs.

MCE – Marin Clean Energy - the first CCA in California that began serving customers in 2010.

They serve customers in Contra Costa, Marin, Napa and Solano counties in Northern California.

MEO – Marketing Education and Outreach - a term generally used to describe various strategies to inform customers, such as to motivate consumers to take action on energy efficiency or conservation measures and change their behavior.

MW – Megawatt – measure of power. A megawatt equals 1,000 kilowatts or 1 million watts.

MWH – Megawatt-hour – measure of energy
NAESCO – National Association of Energy Service Companies - – an advocacy and accreditation organization for energy service companies (ESCOs). Energy Service Companies 550
contract with private and public sector energy users to provide cost-effective energy efficiency retrofits across a wide spectrum of client facilities.

NBC – Non-Bypassable Charge - fees that are paid on every kilowatt-hour of electricity that is consumed from the grid. These charges can be used to fund things like energy assistance programs for low-income households and energy efficiency programs. These charges apply even if customers buy grid-supplied power from an outside power company such as a CCA.

NDA – Non-Disclosure Agreement - a contract by which one or more parties agree not to disclose confidential information that they have shared with each other.

NEM – Net Energy Metering – A program in which solar customers receive credit for excess electricity generated by solar panels.

NRDC – Natural Resources Defense Council - non-profit international environmental advocacy group.

NP-15 – North Path 15 – NP-15 is a CAISO pricing zone usually used to approximate wholesale electricity prices in northern California in PG&E’s service territory.

OIR – Order Instituting Rulemaking - A procedural document that is issued by the CPUC to start a formal proceeding. A draft OIR is issued for comment by interested parties and made final by vote of the five Commissioners of the CPUC.

OSC – Order to Show Cause - order requiring an individual or entity to explain, justify, or prove something.

ORA – Office of Ratepayer Advocates - the independent consumer advocate within the CPUC, now called Public Advocates office.

PA – Program Administrator (for EE Business Plans) IOUs and local government agencies authorized to implement CPUC-directed Energy Efficiency programs.

PCE – Peninsula Clean Energy Authority - CCA serving San Mateo County and all 20 of its cities and towns as well as the City of Los Banos.

PCC1 – RPS Portfolio Content Category 1 – Bundled renewables where the energy and REC are dynamically scheduled into a California Balancing Authority (CBA) such as the CAISO. Also known as “in-state” renewables.

PCC2 – RPS Portfolio Content Category 2 – Bundled renewables where the energy and REC are from out-of-state and not dynamically scheduled to a CBA.

PCC3 – RPS Portfolio Content Category 3 – Unbundled REC PCIA or “exit fee” - Power Charge Indifference Adjustment (PCIA) is an “exit fee” based on stranded costs of utility generation set by the California Public Utilities Commission. It is calculated annually and assessed to customers of CCAs and paid to the IOU that lost those customers as a result of the formation of a CCA.

PCL – Power Content Label – A user-friendly way of displaying information to California consumers about the energy resources used to generate the electricity they sell, as required by AB 162 (Statue of 2009) and Senate Bill 1305 (Statutes of 1997). 551
PD – Proposed Decision – A procedural document in a CPUC Rulemaking that is formally commented on by parties to the proceeding. A PD is a precursor to a final Decision voted on by the five Commissioners of the CPUC.

PG&E – Pacific Gas & Electric - the IOU that serves 16 million people over a 70,000 square mile service area in Northern California.

PHC – Prehearing Conference - CPUC hearing to discuss the scope of a proceeding among other matters. Interested stakeholders can request party status during these.

Pnode – Pricing Node – In the CAISO optimization model, it is a point where a physical injection or withdrawal of energy is modeled and for which a LMP is calculated.

PPA – Power Purchase Agreement – A contract used to purchase the energy, capacity and attributes from a renewable resource project.

PRP – Priority Review Project - transportation electrification pilot projects approved by the CPUC pursuant to SB 350.

PRRR – Progress on Residential Rate Reform – Pursuant to a CPUC decision, the IOUs must submit to the CPUC and parties periodic updates on the progress of their efforts to assist customers with residential rate design changes related to rate reform, including tier collapse and transition to a default time of use rate.

PUC – Public Utilities Code - California statute that contains 33 Divisions, and the range of topics within this Code includes natural gas restructuring, private energy producers, telecommunication services, and specific municipal utility districts and transit authorities. Primary statute for governance of utilities as well as CCAs in California.

PURPA – Public Utilities Regulatory Policy Act - federal statute passed by Congress to encourage fuel diversity via alternative energy sources and to introduce competition into the electric sector. It was meant to promote energy conservation (reduce demand) and promote greater use of domestic energy and renewable energy (increase supply). The law was created in response to the 1973 energy crisis.

RA – Resource Adequacy - Under its Resource Adequacy (RA) program, the California Public Utilities Commission (CPUC) requires load-serving entities—both independently owned utilities and electric service providers—to demonstrate in both monthly and annual filings that they have purchased capacity commitments of no less than 115% of their peak loads.

RAM – Renewables Auction Mechanism - a procurement program the Investor-owned Utilities (IOUs) may use to procure RPS eligible generation. The IOUs may use RAM to satisfy authorized procurement needs, for example, system Resource Adequacy needs, local Resource Adequacy needs, RPS needs, reliability needs, Local Capacity Requirements, Green Tariff Shared Renewables needs, and any need arising from Commission or legislative mandates.

RE – Renewable Energy - Energy from a source that is not depleted when used, such as wind or solar power.

REC - Renewable Energy Certificate - A REC is the property right to the environmental benefits associated with generating renewable electricity. For instance, homeowners who generate solar 552
electricity are credited with 1 solar REC for every MWh of electricity they produce. Utilities obligated to fulfill an RPS requirement can purchase these RECs on the open market.

RES-BCT – Renewables Energy Self-Generation Bill Credit Transfer - This program enables local governments and universities to share generation credits from a system located on one government-owned property with billing accounts at other government-owned properties. The system size limit under RES-BCT is 5 MW, and bill credits are applied at the generation-only portion of a customer's retail rate.

RFO – Request for Offers a competitive procurement process used by organizations to solicit the submission of proposals from interested parties in response to a scope of services.

RPS - Renewable Portfolio Standard - Law that requires CA utilities and other load serving entities (including CCAs) to provide an escalating percentage of CA qualified renewable power (culminating at 33% by 2020) in their annual energy portfolio.

SB – Senate Bill - a piece of legislation that is introduced in the Senate. In other words, the Senate, rather than the Assembly, is the house of origin in the legislature for the legislation.

SCE – Southern California Edison - the large IOU that serves the Los Angeles and Orange County area.

SCP – Sonoma Clean Power Authority - CCA serving Sonoma County and surrounding areas in Northern California.

SDG&E – San Diego Gas & Electric - the IOU that serves San Diego county, they own the infrastructure that delivers SDCP energy to customers.

SGIP – Self-Generation Incentive Program – A program which provides incentives to support existing, new, and emerging distributed energy resources (storage, wind turbines, waste heat to power technologies, etc.)
SUE – Super User Electric - electric surcharge that’s intended to penalize consumers for excessive energy use.

SVCE – Silicon Valley Clean Energy - CCA serving Silicon Valley Area.

TCR EPS Protocol – The Climate Registry Electric Power Sector Protocol – Online tools and resources provided by The Climate Registry to assist organizations to measure, report, and reduce carbon emissions.

TE – Transportation Electrification - For the transportation sector, electrification means replacing fossil fuels with electricity as the means of powering light-duty vehicles, medium- and heavy-duty trucks, and buses. The primary goal is to reduce greenhouse gas (GHG) emissions and, ultimately, contribute to mitigating the effects of climate change on the planet.

Time-of-Use (TOU) Rates — The pricing of delivered electricity based on the estimated cost of electricity during a particular time-block. Time-of-use rates are usually divided into three or four time-blocks per 24 hour period (on-peak, midpeak, off-peak and sometimes super off-peak) and by seasons of the year (summer and winter). Real time pricing differs from TOU rates in that it is based on actual (as opposed to forecasted) prices that may fluctuate many times a day and are weather sensitive, rather than varying with a fixed schedule. 553
TM – Tree Mortality - refers to the death of forest trees and provides a measure of forest health.

In the context of energy, the CPUC is tasked with utilizing its authority to extend contracts and take actions to authorize new contracts on bioenergy facilities that receive feedstock from high hazard zones.

TURN – The Utility Reform Network - A ratepayer advocacy group charged with ensuring that California IOUs implement just and reasonable rates.

Unbundled RECs - Renewable energy certificates that verify a purchase of a MWH unit of renewable power where the actual power and the certificate are “unbundled” and sold to different buyers.

VPP – Virtual Power Plant – A cloud-based network that leverages an aggregation of distributed energy resources (DERs) to shift energy demand or provide services to the grid. For example, thousands of EV chargers could charge at a slower speed and hundreds of home batteries could discharge to the grid during a demand peak to significantly reduce the procurement of traditional supply resources.

VAMO – Voluntary Allocation, Market Offer - the process for SDG&E to allocate a proportional share of their renewable portfolio to SDCP and other LSEs within the service territory. 554