CITYWIDE PAVEMENT REHABILITATION PROJECT
July 18th, 2023

PAVEMENT ANALYSIS

PAVEMENT CONDITION OVERVIEW

ROADWAY

CONDITIONS

VERY POOR
POOR

EXCELLENT

BACKGROUND
July 18, 2023
As Part of the yearly budget Staff presented Pavement Management Inventory To keep the conditions of the streets at an acceptable level the City will have to spend additional $7 million a year from current spending of $6 million a year.

Council directed staff to devise a CIP plan to spend an additional $21 million in next two fiscal years to eliminate failed streets throughout the city.

On July 6, 2023, Capital Improvement Program (CIP) staff presented the Citywide Pavement Rehabilitation Project – Phase 1 to the Streets Infrastructure Committee. The Streets Infrastructure Committee agreed with Special Projects Administrator, Amer Jakher, to move forward with the Pilot Program

CHALLENGES
July 18, 2023
To comply with current ADA standards and design ramps using current practices it takes up to 18 months to start paving on a project.

Design and project management fees can total 15%, over $3 million for additional $21 million of paving projects. fees

OTHER OPTION
July 18, 2023
Implement a pilot program.

Use existing ADA intersection improvement layouts that have proven to work in previous projects.

Separate concrete work contract from asphalt paving.

Utilize existing concrete contract by adding additional funds to the current maintenance contract.

Advertise and award a rolling asphalt paving contract.

Provide layouts and continuous inspections of all work.

Expected time to start asphalt work is 6 months.

Pilot Program
July 18, 2023
Number of ADA ramps in Pilot program Area = 160
Total projected Concrete work cost = $1-$1.5 million
Asphalt cost estimate = $3.5-$5 million
Additional project management cost = $500K

LOCATIONS
July 18, 2023

LOCATIONS
July 18, 2023

EXAMPLES
July 18, 2023

WALNUT AVENUE AT OLIVE PLACE
BEFORE
AFTER

EXAMPLES
July 18, 2023

SAN ANTONIO AVENUE AT FILMORE STREET
BEFORE
AFTER

EXAMPLES
July 18, 2023

JEFFERSON AVENUE AT TENTH STREET
BEFORE
AFTER

EXAMPLES
July 18, 2023

SERENE AVENUE AT SIXTEENTH STREET
BEFORE
AFTER