Exhibit I Substantial Amendment - 2024-2025 Alley Improvement SN240

Chino City Council
April 1, 2025

Document
Exhibit I Substantial Amendment - 2024-2025 Alley Improvement SN240
Meeting
April 1, 2025
Body
Chino City Council
Original file
16 KB
Text extracted from the city's file for reading and search. Open the original on chino.legistar1.com. That file is the official record.

Exhibit 1:

CDBG 2024-2025 Action Plan-Substantial Amendment
The proposed amendment will reallocate funding within the City’s CDBG program to enable sufficient funding for the completion of the project as described below.

Alley Improvement Project SN240:

The proposed project expands the limits of work for Alley Improvements Project (SN240) CDBG FY23-24 to fully capture the east-west alley between D Street and Chino Avenue (from Monte Vista Avenue to 5th Street). This area is primarily residential and entirely within CDBG LMI areas.

The scope of work includes pavement rehabilitation of the asphalt alley, installation of a concrete ribbon gutter to facilitate drainage and improved ADA access at alley driveway approaches. This project will enhance pedestrian access and remove barriers, allowing increased access to the western-adjacent Monte Vista Park.

The program performance categories for this project promote Availability/Accessibility and Livable or Viable Communities. The project targets the older part of the community, Census Tract 605, Block Group 1. Improvement of both the motorist and pedestrian travel ways will enhance the overall appearance of the neighborhood and will directly benefit 12 households that immediately abut the alleyway.

The City’s Public Works Department will administer and monitor the project design and construction. The estimated cost of design and construction to complete the project scope is $588,000.

Proposed Project Budget Increase over 25%
CDBG Allocation
FY 2023-24 Alley Improvement Project SN240 Original Budget Allocation $219,256.00
Proposed Action Plan Reallocation of Funds
FY 2024-25 Community Garden Pumpkin Patch Project- (cancel and reallocate) $298,868.65
FY 2023-2024 Alley Improvement Project SN240 New Allocation Total $298,868.65
FY 2023-24 Alley Improvement Project SN240 Total Budget Allocation $518,124.65