LAGOON DRIVE
BAY BOULEVARD
BAY BOULEVARDCONSTRUCT CLASS 1
SHARED USED PATH
PROTECT IN PLACE
EXISTING INACTIVE RAIL
SD&AERAIL R/W
SEE DETAIL BELOW
CONSTRUCT CLASS 1
SHARED USED PATH
A
A
CITY OF CHULA VISTA R/W
CITY OF
CHULA VISTA R/W
SEE DETAIL BELOW
CONSTRUCT ~200' OF BRIDGE
5' 5' 2'2' ±25'1'
MIN
14' CLASS 1 SHARED USE PATH
± 40' SD&AE R/W
PROTECT IN PLACE
EXISTING INACTIVE RAIL
8.5' MIN FROM CL OF RAIL
PROPOSED FENCING
PROPOSED FENCING
4"AC/8"AB
RAMP TO BE CONSTRUCTED (BY
OTHERS) BY FUTURE SWEETWATER
BICYCLE PATH PROJECT MID-2021
RAMP TO BE CONSTRUCTED (BY
OTHERS) BY FUTURE SWEETWATER
BICYCLE PATH PROJECT MID-2021
RAMP TO BE CONSTRUCTED (BY
OTHERS) BY FUTURE SWEETWATER
BICYCLE PATH PROJECT MID-2021
CLASS 1 SHARED USED
PATH TO BE CONSTRUCTED
(BY OTHERS) BY FUTURE
SWEETWATER BICYCLE
PATH PROJECT MID-2021
EXISTING BAYSHORE BIKEWAY
ROAD EXTENSION TO BE CONSTRUCTED
(BY OTHERS) BY FUTURE SWEETWATER
BICYCLE PATH PROJECT MID-2021
XING TO BE CONSTRUCTED (BY
OTHERS) BY FUTURE SWEETWATER
BICYCLE PATH PROJECT MID-2021
XING TO BE CONSTRUCTED (BY
OTHERS) BY FUTURE SWEETWATER
BICYCLE PATH PROJECT MID-2021
CONSTRUCT PED XING
CONNECT TO FUTRE
BAYSHORE BIKEWAY
SEGMENT
CONSTRUCT BIKE HAWK XING
CONSTRUCT PEDESTRIAN RAMP
CONSTRUCT PEDESTRIAN RAMP
CONSTRUCT PEDESTRIAN RAMP
CONSTRUCT HAWK TRAFFIC SIGNAL
(INCLUDING FOUNDATION, POLE, MAST
ARMS ,SIGNALS, LUMINAIRE)
CONSTRUCT HAWK TRAFFIC SIGNAL
(INCLUDING FOUNDATION, POLE, MAST
ARMS ,SIGNALS, LUMINAIRE)
Bayshore Bikeway - Chula Vista Segment
Proposed Project Plan and Cross Section
9/8/2020
Sheet 1 of 1
C:\CRA_SP\Chen Ryan\262-Chula_Vista_ATP - Files\CAD\Exhibits\262_Exh_Sheet 1.dwg Plot: Izzad J. Loh Date: 9/15/2020 8:44:00 N
0' 50' 100'
PROPOSED CONNECTION TO BAYSHORE BIKEWAY
AT BAY BLVD AND GUNPOWDER POINT DR
SCALE: 1" = 20'
PROPOSED LAGOON DR TRAIL CROSSING
SCALE: 1" = 20'
PROPOSED SECTION THROUGH SD&AE R/W
NOT TO SCALE
CONNECT TO FUTURE BAYSHORE BIKEWAY /
SWEETWATER BICYCLE PATH JUNCTION
PROPOSED BAYSHORE
BIKEWAY SEGMENT 6A
Attachment 2