LOMA VERDE RECREATION CENTER1420 Loma Lane
Patricia Fermán, Principal Landscape Architect, DSDJonathan Salsman, Senior Civil Engineer, Engineering and Capital ProjectsTim Farmer, Parks & Recreation Administrator, Community Services
Hilltop DriveRienstraSports Complex
LOMA VERDE RECREATION CENTERProject Location: 1420 Loma Lane Loma VerdeElementary SchoolLoma Lane
LOMA VERDE RECREATION CENTER2019 and 2020 - PUBLIC OUTREACH
Subsequently, the City issued a Request for Proposals (RFP) to a list of prequalified Design-Build firms.After evaluation, the contract to design the Center was awarded to EC Constructors Inc. and Jeff Katz Architecture
LOMA VERDE RECREATION CENTERPLAN VIEW
SEGMENTS 1 AND 2SEGMENT 3
Looking north-east from the parking lot
Looking north-west from the parking lot
LOMA VERDE RECREATION CENTERSINGLE POINT OF ENTRY
Single point of entry
LOMA VERDE RECREATION CENTERLOBBY
LOMA VERDE RECREATION CENTERConstruction of Segments 1 and 2 Main Lobby and game room
LOMA VERDE RECREATION CENTERConstruction of Segments 1 and 2 Dance Room withaccordion wall track
LOMA VERDE RECREATION CENTERMUL TI-PURPOSE ROOM
Multi-purpose Gymnasium
LOMA VERDE RECREATION CENTERSEGMENT 3
COMPETITION POOL
CLASSROOMSPOOL EQUIPMENT AND STORAGE
SPLASH PAD
RECREATIONAL POOL
OUTDOORMULTI-PURPOSE AREA
LOMA VERDE RECREATION CENTERSEGMENT 3 – POOL AND BUILDINGS
LOMA VERDE RECREATION CENTERPOOL DECK
FUNDING
MEASURE Pand other funding sources
MEASURE Pand other funding sources
Segment 3 GMP: $14.2 millionOther project costs (approx.) $900,000 Segment 3 GMP: $14.2 millionOther project costs (approx.) $900,000CONSTRUCTION COST SEGMENT 3
CONSTRUCTION COMPLETION
Segments 1 and 2: FALL 2022Segment 3: SUMMER 2023
Segments 1 and 2: FALL 2022Segment 3: SUMMER 2023
LOMA VERDE RECREATION CENTERSegment 3RECOMMENDED ACTIONAdopt a resolution authorizing construction of Segment 3 of the Loma Verde Recreation Center and authorizing the City Engineer to execute change orders necessary for the project.