RESOLUTION NO. __________
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROPRIATING $96,000 FROM THE
AVAILABLE BALANCE OF THE TRANSNET FUND TO THE
SIDEWALK REPLACEMENT FY 2020/21 (STL0448) PROJECT
FOR CONTRACT CHANGE ORDERS WITH JUST
CONSTRUCTION, INC.
WHEREAS, the Public Works Department replaces damaged sidewalk at various locations throughout the City through the “Sidewalk Replacement Program” on a yearly basis and CIP# STL0448 addresses the FY 2020/21 list of locations for the program; and
WHEREAS, on Wednesday, March 23, 2022, the Director of Engineering & Capital Projects received seven (7) sealed bids for the “Sidewalk Replacement Program FY2020/21 (CIP# STL0448)” project; and
WHEREAS, on April 6, 2022, the Director of Finance awarded a construction contract to Just Construction for CIP# STL0448; and
WHEREAS, due to differing quantities and additional items of work encountered in the field as compared to the construction contract, actual costs to the project will exceed the approved contingencies; and
WHEREAS, staff recommends appropriating an additional $96,000 above the originally approved amount for construction change orders with Just Construction, Inc., and associated staff costs.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Chula Vista that it appropriates $96,000 from the available balance of the TransNet Fund to CIP STL0448.
Presented by Approved as to form by
William S. Valle Glen R. Googins
Director of Engineering & Capital Projects City Attorney