Form Rev 3/6/2023
RESOLUTION NO. __________
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA APPROPRIATING HIGHWAY BRIDGE
PROGRAM FUNDS BASED ON UNANTICIPATED REVENUE
TO THE HERITAGE BRIDGE REPLACEMENT PROJECT
(STM0386)
WHEREAS, Caltrans has previously awarded the City grant funding under the Highway Bridge Program (HBP) for the Heritage Bridge Replacement Project (STM0386); and
WHEREAS, Environmental resource agencies have identified project mitigation measures required for the project; and
WHEREAS, the City has identified off -site mitigation bank credits for purchase to meet environmental compliance requirements; and
WHEREAS, additional funds were required to finalize design plans and specifications for STM0386; and
WHEREAS, the Federal Highway Bridge Program (HBP) will continue to reimburse the City for 88.53% for all participating costs.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Chula Vista, that it appropriates $3,045,432 of Highway Bridge Program (HBP) funds based on unanticipated revenue to STM0386.
Presented by Approved as to form
By:
William Valle Jill D.S. Maland
Director of Engineering and Capital Projects Lounsbery Ferguson Altona & Peak Acting City Attorney