Infrastructure,
Facilities and Equipment
Expenditure Plan
Funding Critical Priorities for
a Stronger, Safer Chula Vista

Infrastructure, Facilities and Equipment Expenditure Plan 2023

1 Amendment #11   Apr 2023
Introduction

The  City  of  Chula  Vista,  like  many  cities  throughout  the  country,  is  struggling  to  properly  fund  our infrastructure  needs.  The  City  of  Chula  Vista  (City)  has  been  developing  and  implementing  its  Asset Management  Program  to  operate  and  maintain  the  City’s  natural  and  built  infrastructure.   Staff  has provided several updates to the City Council on the Asset Management Program. The presentations and related publications can be found at www.chulavistaca.gov/infrastructure.

To address the City’s infrastructure needs and other City facilities and services, the City Council placed a funding  measure  on  the  November  2016  ballot  to  address  high  priority  infrastructure  projects.   On November  8,  2016,  Chula  Vista  voters  approved  Measure  P,  authorizing  a  temporary  ½  cent  sales  tax increase on retail sales within the City for a period of ten (10) years. Staff prepared the Infrastructure, Facilities and Equipment Expenditure Plan to identify the recommended allocation of the temporary ½ cent sales tax revenues which were originally estimated to generate $16 million per year. The updated 2023 revenue estimates are projected to generate $25+ million per year.  The recommended funding is based  on  the  criteria  established  through  the  Asset  Management  Program  which  identifies  the  major citywide infrastructure systems considered in critical need of repair or replacement.  Analysis conducted by  consultants  experienced  in  evaluating  infrastructure  system  conditions,  ranked  infrastructure  from lowest to highest probability of failure, identified a timeline for repair and replacement, and estimated associated  cost.   The  sales  tax  revenues  generated  over  the  10‐year  timeframe  could  address  all infrastructure  assets  designated  with  the  highest  probability  of  failure  which,  if  not  addressed,  could result  in  significant  impact  to  public  safety  response  or  availability  of  highly  used  community infrastructure.

Given  the  needs  and  limited  availability  of  funds,  the  items  proposed  for  funding  under  this  plan represent  one‐time  allocations  of  funds  and  not  ongoing  commitments.  Funding  of  ongoing commitments, such as salary and benefit increases, is not included in the Plan as they would result in continuing financial obligations beyond the ten‐year temporary tax period.  Therefore, this Plan focuses on  the  areas  where  one‐time  funds  could  be  used  to  address  critical  deferred  maintenance  or replacement of city infrastructure improving safety and reducing risk to the City as well as strengthening the  City’s  overall  financial  condition  by  avoiding  costly  emergency  repairs  or  further  deterioration  of existing failing infrastructure.

The following are the highest priority items for funding:
 Pave, maintain and repair neighborhood streets and fix potholes  Upgrade  or  replace  aging  police,  fire  and  9‐1‐1  emergency  response  facilities,  vehicles  and equipment
 Replace storm drains to prevent sinkholes
 Upgrade irrigation systems to conserve water and save energy  Make essential repairs to older libraries, senior center and recreation centers  Improve our Traffic Signal Systems
Infrastructure, Facilities and Equipment Expenditure Plan 2023

2 Amendment #11   Apr 2023
 Repair our Sports Fields and Courts and Park Infrastructure This  Infrastructure,  Facilities  and  Equipment  Expenditure  Plan  also  includes  long‐term  financing  of approximately $70.8 million in order to expedite the most critically needed repairs or replacements of citywide infrastructure.   City Council  approved the issuance bonds via Resolution 2017‐089 on June 6, 2017. This Plan also provides a component which identifies the potential annual allocations to projects which  could  be  included  in  the  annual  City  Manager  proposed  Capital  Improvement  Budget  for  City Council consideration and action.

Process for Creation of the Plan
Asset Management Program (AMP)
Since  March  2014,  the  City  has  been  working  to  enhance  its  asset  management  practices  to  promote effective  use  of  financial  and  physical  resources  and  to  develop  a  proactive  approach  to  managing infrastructure assets. As part of this effort, the City embarked on developing a comprehensive, citywide Asset Management Program that includes the following asset management systems:
 Wastewater Management System
 Urban Forestry Management System
 Building Management System
 Drainage Management System
 Parks Management System
 Roadway Management System
 Fleet Management System
AMP Goals
The  goal  of  the  City’s  Asset  Management  Program  is  to  shift  from  reactive  to  proactive  planning  and management of our infrastructure assets. The effort has helped the City to:
 Gain better understanding of the current state of the infrastructure and its future needs  Proactively  identify  the  asset  replacement  and  rehabilitation  needs  and  plan  the  budget  and resources accordingly
 Understand  the  probability  and  consequence  of  failure  of  each  asset  so  that  the  City  can manage high risk assets before failure and minimize the City’s overall risk profile  Minimize  the  life‐cycle  cost  by  incorporating  latest  technological  advances  in  infrastructure  to develop efficient and effective preservation and restoration strategies  Develop a consistent and defendable methodology for prioritizing work and budget expenditure  Focus on high benefit‐to‐cost ratio to ensure the budget is spent in the right place, for the right reason, at the right time, at the right cost
 Be  transparent  by  involving  the  City  Council  and  the  public  in  the  development  of  the  Asset Management Program and the associated decisions
Infrastructure, Facilities and Equipment Expenditure Plan 2023

3 Amendment #11   Apr 2023
It is important for the City to gain a better understanding and quantify current and future asset needs, asset  risk  profile,  appropriate  levels  of  service,  cost  to  provide  services,  and  financial  requirements  to sustain the delivery of services. City staff has worked to communicate this improved understanding of the infrastructure status with the public and decision makers. This analysis and information has enabled City  staff  to  develop  management  strategies  that  deliver  the  established  levels  of  service  while managing individual assets to minimize life‐cycle cost with an acceptable level of risk.

With this information, the City can better answer the following questions:
 Catch Up – What levels of work, resources, and budget are required to bring the asset back to required conditional state to meet the safety, regulatory, and level of service requirements?  Keep Up – Once the asset is caught up, what levels of work, resources, and budget are required to keep up the level of service?
 Moving Forward – What levels of work, resources, and budget are required to sustain the level of service?
Asset Management Program Advisory Committee
To  help  identify  the  needs  of  our  community  and  to  evaluate  the  state  of  our  infrastructure,  the  City formed the Asset Management Program Advisory Committee (AMPAC) in March 2014. The committee continues to provide input into setting priorities for the Asset Management Program.

Members of the AMPAC are residents, business owners, community leaders, and stakeholders.  AMPAC members visited various asset management systems and observed and discussed the issues associated with  each  system.   AMPAC  reviewed  the  City’s  overall  Asset  Management  Program  methodology  and helped to guide and reach consensus on how to address infrastructure deficits.

A technical committee was formed within AMPAC to further engage the public in the understanding and review of the asset management methodologies and logic used to define preservation and restoration costs and schedules.

A comprehensive inventory of assets took place for each asset management system. Where accessible, assets  were  visited  and  their  conditions  were  assessed.  Based  on  the  condition,  actions  required  to restore the asset were identified, and the cost and timing were estimated. Through assessment of risk (probability  and  consequence  of  failures),  activities  were  prioritized  and  communicated  regarding urgency and the financial and resource requirements.

Public Outreach and Public Opinion Surveys
In  July  and  August  2015,  the  City  of  Chula  Vista  engaged  a  research  firm  to  conduct  a  public  opinion survey to identify resident priorities and secure input on potential local funding mechanisms (bond or sales  tax)  to  upgrade,  repair  and  maintain  critical  infrastructure.  In  addition,  a  survey  mailer  was distributed to 54,000 households and an online version posted on the City website from January through Infrastructure, Facilities and Equipment Expenditure Plan 2023

4 Amendment #11   Apr 2023
May  2016  to  secure  broad  public  input  on  infrastructure  priorities.  More  than  3,000  responses  were received.

Public Opinion on Prioritizing Infrastructure Projects

Infrastructure, Facilities and Expenditure Plan
With  the  information  gathered  through  the  Asset  Management  process  and  community  input,  staff developed this Plan taking into account projected available funding, priorities and timing considerations.

The actual allocations will be dependent on updated engineering cost estimates, project specific criteria and available funding at the time the individual projects are proposed.

The following table presents the Infrastructure, Facilities and Expenditure Plan by Major Category.   On page 14 of this Plan is a 10‐year outlook by fiscal year which includes long‐term financing to expedite the most critically needed repairs/replacement of citywide infrastructure.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

5 Amendment #11   Apr 2023
Infrastructure, Facilities and Equipment Expenditure Plan (By Major Category)

Plan Implementation
The ballot measure approved by the voters is anticipated to generate an estimated $245 million over a 10‐year  period.   The  projected  revenues  from  the  sales  tax  measure  will  address  the  items  which  are considered  high  risk  and  in  critical  need  of  repair  or  replacement.   The  estimated  revenues  will  also address approximately 11% of the assets identified as having medium probability of failure.

The measure provides that any proposed expenditures of new sales tax revenues in the initial year will be presented in a form consistent with this Plan as budget amendments for City Council consideration.

For  each  subsequent  year,  the  spending  plan,  after  review  by  a  Citizen  Oversight  Committee,  will  be included in the City Manager’s proposed budget for Council consideration as part of the annual budget process.

The measure requires that expenditure of new sales tax revenues be tracked in a variety of ways.  First all  new  revenues  will  be  accounted  for  in  the  General  Fund  as  a  separate  line  item.   Second,  an independent audit of measure revenues and expenditures will be performed and presented for public review.   Finally,  a  Citizen’s  Oversight  Committee  will  review  all  proposed  expenditure  plans  and  all audits.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

6 Amendment #11   Apr 2023
Note:   This Plan is intended to guide City expenditures consistent with its terms.   It does not, however, constitute a binding legal commitment on the City Council to approve any of the expenditures proposed herein.   Provided that all proposed expenditures continue to be for City infrastructure, facilities and/or equipment, this Plan may also be updated or amended from time to time by City staff, or by action of the  City  Council,  in  order  to  address  changed  priorities,  standards  and/or  funding  availability.   There shall be no third‐party beneficiaries to the terms of this Plan.  This Plan does not modify the terms of the sales  tax  measure.   To  the  extent  of  any  conflict  between  the  terms  of  this  Plan  and  the  sales  tax measure, the terms of the sales tax measure shall govern.

Summary Description of Major Infrastructure Categories
To follow are descriptions of the major infrastructure categories within the Expenditure Plan. Included within  several  of  the  categories  described  below  is  an  emphasis  on  repairing  and  replacing  existing inefficient  systems  and  equipment  with  newer,  more  efficient  systems.   Funding  for  efficient  systems has been incorporated into the existing funding for police facility repairs, sports courts and fields, park infrastructure, recreation and senior centers, libraries, and other public buildings.   Specific projects will include:  citywide  lighting  upgrades;  citywide  irrigation  upgrades;  citywide  HVAC  equipment replacement; and other facility and park efficiency upgrades.   The projects will be consistent with the priorities laid out in the original Measure P Expenditure Plan as well as the City's Smart Cities Plans.  The projects  will  extend  the  life  of  the  City's  facilities  and  parks,  allow  for  easier  and  more  efficient maintenance, and provide flexibility to allocate proper maintenance funds are in place to "keep up" with ongoing maintenance on newly repaired facilities. Measure P funds will not be used to provide ongoing maintenance.

Street Pavement:

One  of  the  greatest  challenges  a  City  faces  is  maintaining,  preserving  and  restoring  its  paved  streets.

The City of Chula Vista utilizes the Streetsaver Pavement Management System to develop a multi‐year pavement  preservation  program.  The  program  has  primarily  been  focused  on  sustaining  more  heavily traveled  major  arterial  and  collector  streets  in  good  condition.   Through  the  Pavement  Management System,  city  streets  are  given  a  Pavement  Condition  Index  (PCI).   The  purpose  of  the  pavement management system is to enable the City to use its pavement dollars in the most cost‐effective manner so  that  the  overall  pavement  condition  is  as  good  as  possible.   The  pavement  preservation  approach significantly prolongs the life of existing pavements for a fraction of what it would cost to rehabilitate the street once it reached failure.  Unfortunately, local/residential streets have reached a failed state (0‐ 25  PCI)  and  the  typical  strategies  used  for  preventative  maintenance  would  be  inadequate.   These residential  streets  would  require  major  rehabilitation.   The  Measure  P  funding  for  Street  Pavement repair  is  intended  repair  these  failed  residential  streets.   Additional  information  is  available  in  the Roadway Assessment Plan located at www.chulavistaca.gov/infrastructure.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

7 Amendment #11   Apr 2023
Pavement Condition Index

PCI = 21 PCI = 40 PCI = 68 PCI = 75 PCI = 95

Other Infrastructure (Storm Drains, Sidewalks, Trees, Drainage Systems) Much of the City’s storm drain system is more than 50 years old.   There are approximately 13 miles of corrugated  metal  pipes  (CMP)  located  in  the  City  of  Chula  Vista.   Some  of  the  CMP  have  been deteriorating due to their age and corrodible nature of the material.   According to the 2005 condition assessment data, 1.8 miles of CMPs were recommended to be lined with CIPP liner and 0.4 miles of CMP were  recommended  to  be  replaced  immediately.   In  order  to  accelerate  the  replacement  of  CMP  and address infrastructure needs in Western Chula Vista, the City issued $10.5 million in debt but despite the City’s effort to reline and replace as much as possible of the problematic CMP based on the 2005 study, not all pipe failures could be predicted.   In February 2015, a CMP located near one of the elementary schools failed and  created a sinkhole.   In order to  prevent future failures and  to drive lower life‐cycle cost,  the  City  utilized  the  asset  management  strategies  to  identify  which  CMPs  have  a  greater  risk  of failing.   As  a  result,  the  City  repurposed  $1.2  million  from  streets  to  fund  CMP  replacement  or  lining.

Additional information on the City’s Drainage system is located in the Drainage Asset Management Plan located at www.chulavistaca.gov/infrastructure.

The  City  is  committed  to  the  goal  of  increasing  the  maintenance  and  number  of  trees  within  the  city.

Healthy trees provide many benefits to communities, such as reducing storm water runoff, removing air pollution, lowering summer temperatures, and reducing energy use in buildings.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

8 Amendment #11   Apr 2023
Traffic Signal System:

Proposed funding could advance traffic signal replacements and upgrades that focus on improving two major  objectives:  safety  and  performance.  Each  objective  listed  has  a  direct  correlation  to  enhancing safety at intersections or of City roadways while also improving efficiency and operability of the traffic signal  systems.   Tax  measure  funds  could  also  be  used  as  matching  funds  for  federal,  state  and  local grants.

Improvements could include:
 Replacement of aging or legacy traffic controllers and signal cabinet and equipment  Replacement of rusted, faded or missing traffic signal back‐plates or signal heads  Replacement of obsolete pedestal‐mounted traffic signals to overhead mounted traffic signals  Repair and/or replacement of broken inductive pavement loops and failing video cameras  Converting non‐actuated intersections to actuated
 Installation of pedestrian countdown indications and ADA compliant push buttons citywide  Replacement of obsolete 8” traffic signal lamps to standard 12” traffic signal lamps  Installation of Bicycle Detection System Citywide
 Replacement of legacy communications equipment and expansion of City Fiber Optics, Wireless, and/or Twisted Pair Communications
 Expansion of Adaptive Signal System
 Installation of Traffic Monitoring Devices:
o Closed‐Circuit  Television  (CCTV)  Cameras  at  intersection  along  Major  Trolley,  Freeway interchanges, or major cross streets in the City of Chula Vista o Expansion of Data Collection Systems to actively monitor Level‐of‐Service of City Streets o Changeable Message Sign System along Main Street to mitigate special event traffic for Sleep Train Amphitheater
o Installation of Traffic Calming Devices
 Comprehensive Coordination Retiming Project Citywide
Fire Response Vehicles (Apparatus):

The Fire Department’s fire apparatus fleet is currently experiencing excessive years of service.  This has led to increased downtime, decreased reliability, and obsolete safety features.  The Fire Department and Public Works Department are challenged on a daily basis with maintaining an adequate fire apparatus fleet  (frontline  and  reserve)  due  to  the  above  factors.   The  current  fleet  downtime  report  shows,  for every five days a fire apparatus is in service, it then requires one full day out of service for maintenance and repair.   Fire apparatus replacement standards call for 10 to 12 years for front line service with five years in reserve capacity.  Over half (10 of 17 fire apparatus) of the fire apparatus fleet exceeds 12 years of service, three of which are beyond 20 years of service.   Funds could be used to replace Fire Engines and  Fire  Trucks  that  are  overdue  for  replacement  by  excessive  maintenance  expenses  or  obsolete equipment improving response times.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

9 Amendment #11   Apr 2023
Fire Equipment:

Major  fire  equipment  needs  include  radio  communications  equipment,  mobile  data  computer  (MDC) communications equipment, and respiratory protection breathing apparatus.

The City of Chula Vista participates in the Regional Communication System (RCS), which provides public safety  and  public  service  radio  communications  to  the  San  Diego  County  area.   Federal  Regulations, require the upgrade of the RCS to become compliant.  This requires its users to upgrade their handheld, vehicle mounted, and dispatch radios to match the system backbone upgrade.

The  Fire  Department  also  uses  mobile  data  computers  (MDCs)  to  communicate  critical  emergency incident information between response units and dispatch.   These MDCs are ruggedized, military grade laptops  to  withstand  use  during  emergency  response.   These  MDCs  are  beyond  their  useful  life, exceeding  10  years  old  and  also  no  longer  meet  new  operating  system  requirements  to  properly communicate with dispatch.

The  Fire  Department  is  required  to  provide  and  maintain  proper  respiratory  protection  breathing apparatus equipment for firefighting activity.   The current fleet of breathing apparatus is between 13 to 15 years old and beyond the useful life.   This has led to increased downtime, decreased reliability and obsolete  safety  features.   Breathing  apparatus  are  utilized  when  fighting  fires  and  critical  to  the protection of firefighter personnel.

Police Equipment:

Major  equipment  needs  for  the  Police  Department  include  body  worn  cameras,  video  management system  and  replacement  of  network  servers.   Use  of  body  worn  cameras  has  helped  the  Police Department gather more evidence leading to successful prosecution of cases, as well as protecting both the  officer  and  citizens  from  allegations  of  excessive  force  or  misconduct.   The  video  management system will enable the Police Department to view recordings from different cameras when conducting investigations  and  responding  to  calls.   In  order  to  keep  up  with  technology,  network  servers  will  be updated in 5‐year increments.

Fire Station Repairs/Replacements:

The Fire Department currently operates nine fire stations to provide a network of emergency response service delivery.   Three of these fire stations are well beyond their service life.   Fire bay doors must be enlarged to accommodate new fire apparatus and extensive termite treatment and repair is needed. In addition, these fire stations are not compliant with seismic building codes.  Also, as emergency response volume increases beyond the current network of response capacity, existing Fire Station 4 will require expansion  to  accommodate  a  secondary  response  unit  in  order  to  meet  the  service  delivery  demand.

Funding  is  needed  in  order  for  the  expansion  to  move  forward  and  improve  response  times  to  the community.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

10 Amendment #11   Apr 2023
Police Vehicles:

There  are  128  police  vehicles  in  the  Police  Department.  The  vehicles  in  this  fleet  are  technologically complex and specially outfitted for law enforcement work. In addition to being very sophisticated pieces of  equipment  they  are  subjected  to  very  high  levels  of  utilization.  Approximately  41%  of  the  fleet  is identified as needing replacement due to excessive repairs from high mileage and heavy use. The failure of operating patrol vehicles would impact response times to the community.

Police Facility Repairs:

The  Police  facility  is  12  years  old  and  is  in  relatively  good  condition.   Although,  the  facility  is  in  good condition it is given the highest rating  possible for Consequence of Failure. This is because the facility operates 24  hours a day,  7 days a week.   The Asset Management Plan did identify a few items which need immediate attention to avoid operational impacts with the most immediate being the replacement of  the  heating  and  air  conditioning  system.   Failure  of  the  system  could  cause  disruption  to  critical service delivery and the ability to dispatch police personnel.

Public Safety Computer Aided Dispatch System (CAD):

The  Computer  Aided  Dispatch  (CAD)  system  is  a  critical  Information  and  Technology  (IT)  component, which serves as the lynchpin of the 911 emergency service frame work for the police department.  CAD is critical because it is used to dispatch police officers to citizens’ calls for service, and its efficiency and performance  directly  impact  response  times  and  officer  safety.  In  2015,  the  police  department processed 97,632 calls for service in the CAD system.   The department’s CAD system is also the central repository for all records and data related to calls for service. It is a key performance measurement tool used by supervisors and managers to make important tactical and strategic decisions.   Finally, the CAD system’s reliability and stability are critical because it must have continuous availability.  In short, CAD is the virtual and technical heart of all police department operations, especially pertaining to emergency service delivery.

Public Safety Regional Communications System (RCS):

The  Regional  Communications  System  (RCS)  provides  public  safety  and  public  service  radio communications service to San Diego County, Imperial County, 24 incorporated cities, and a multitude of other local, state, federal and  tribal government agencies in the San Diego County/Imperial County Region. The RCS infrastructure is approaching the end of its life cycle and must be replaced. The County of San Diego has been working with member RCS partner agencies to plan for the replacement of the RCS  system  with  a  “Next  Generation”  public  safety  interoperable  communications  system  which  will comply  with  Federal  Communications  System  (FCC)  and  the  national  Association  of  Public  Safety Communications  Officials  standards.  These  regulations  set  in  place  standards  for  communication systems which allow for interoperability between different cities, agencies, and various state and federal agencies.  This  has  been  done  to  ensure  that  during  emergency  events,  various  public  safety  and emergency response personnel can communicate with each other.  The City of Chula Vista currently has Infrastructure, Facilities and Equipment Expenditure Plan 2023

11 Amendment #11   Apr 2023
737 radios operating on the RCS. Based upon the radio count for the City, the approximate cost to the City for participating in the Next Gen RCS project would be $4.5 million, not including financing cost. This does not include the mandatory radio and equipment upgrades that would be needed at the City.

Other City Vehicles:

The “Other City Vehicles” comprises the remaining vehicles in the City’s inventory and supports all other City  provided  services  with  the  exception  of  those  supporting  the  wastewater  section.   These  vehicle replacements  have  been  deferred  for  many  years  resulting  in  excessive  repair  costs.   The  “out  of service” rates for many of these vehicles are at record highs impacting staff’s ability to provide services to the community.  Funding is needed to replace these vehicles (including lawnmowers, pick‐ups, dump trucks, forklifts, etc.) and help the City move toward a more environmentally friendly and economically efficient  fleet  composition  reducing  emissions,  fuel  and  related  operating  costs.   In  addition,  this category  includes  the  Fleet  Infrastructure  project  for  replacement  of  fuel  systems,  installation  of  EV charging stations, a heavy duty in‐ground lift and replacement of the City’s obsolete fleet information management system.

Sports Courts and Fields:

There is a high demand for use of the City’s various sports fields.  Most sports fields are reserved for City programs coordinated through the Youth Sports Council.  The Youth Sports Council, which represents 22 member organizations in the City of Chula Vista, was formed in 1989 to assist the City in coordinating youth sports programs and allocate field use in the City.  Due to the combination of budgetary cuts and water use restrictions, the City’s sports fields are overdue for renovation including re‐seeding, aeration, fertilizing,  and  in  some  cases  sod  replacement.   The  Public  Works  department  prepares  a  Field Management Report which identifies the condition of the various fields.  The current Field Management report, located at www.chulavistaca.gov/infrastructure identified four fields that are closed due to poor condition of the fields.   Another 20 were classified as fair condition but at risk of deteriorating further.

This significantly limits the number of fields available to the various organizations providing youth sports activities in the City of Chula Vista which includes participation of over 10,000 kids.

With additional funding, the sports fields could be brought back to good standings and available for field allocation.   In addition, funds could be allocated to upgrade the irrigations systems to a smart system allowing for efficient and effective water allocation which would assist in keeping the fields healthy even through the drought.

In addition to the sports fields, there are a total of 62 tennis courts and basketball courts.  Based on the most  recent  Court  Management  Report,  located  at  www.chulavistaca.gov/infrastructure  a  total  of  31 courts  are  considered  in  fair  condition  due  to  worn  surfaces,  visible  cracks  or  separation  and  lifting which will require replacement.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

12 Amendment #11   Apr 2023
Park Infrastructure:

The City owns and manages 56 parks that cover approximately 560 acres.   The largest park, Rohr Park, covers  nearly  60  acres.   The  asset  management  study  identified  several  assets  under  the  Park Infrastructure  category  which  included  items  such  as  barbeque  grills,  benches,  drinking  fountains, irrigation  controls,  lights,  picnic  tables,  play  structures,  playground  surfacing,  signage,  trash  bins,  etc.

This Infrastructure, Facilities and Equipment Expenditure Plan recommends funding assets identified in the AMP which are beyond their service life and in need of repair or replacement.  Additional details are available in the Parks Asset Management Plan located at www.chulavistaca.gov/infrastructure.

Recreation and Senior Centers:

In 2015, there were nearly 800,000 visits to our recreation facilities participating in sports, recreation, senior programs and other activities.   With nine recreation centers, two aquatic facilities and 56 parks, the  Recreation  Department  offers  a  myriad  of  opportunities  for  everyone  to  enjoy.  Due  to  the  high volume use of these facilities any interruption or reduction in their availability directly impacts the City’s residents.  Additional  funds  could  be  used  to  replace  roofs,  water  and  waste  water  plumbing,  heating and air conditioning elements that have all reached or exceeded your expected service life.

More specifically, at the Norman Park Senior Center the condition assessment indicates that there is a need  to  repair  the  perimeter  exterior  eaves,  paint  the  interior  and  exterior  of  the  building,  repair  the kitchen and the restroom.    At Loma Verde Recreation Center the pool pump system, decking, lighting and  shower  areas  are  also  in  need  of  repair.    The  City’s  newest  recreation  facilities,  Salt  Creek  and Montevalle,  are  now  over  10  years  old  and  are  beginning  to  experience  heating  and  air  conditioning failures and are in need of floor resurfacing throughout the gyms and classrooms.  Other facilities, such as the Women’s Club, are also in critical need of repair or replacement.

Civic Center Library and South Chula Vista Library:

The Chula Vista Civic Center Library opened its doors in 1976 and is celebrating its 40th Anniversary.  The Civic  Center  Library  and  South  Chula  Vista  Library  are  highly  valued  and  well  used  by  the  community.

Funding  for  the  Library  Department  has  been  focused  on  increasing  access  to  services  and  materials.

Over  the  years,  through  fundraising  efforts  by  the  Friends  of  the  Chula  Vista  Library  and  Chula  Vista Public Library Foundation as well as State grants, the City has been able to do some cosmetic upgrades to  the  interior  of  the  buildings.   At  this  point,  there  is  a  need  to  address  some  more  significant infrastructure repairs such as the roof, water and waste water plumbing, bathroom upgrades, heating and air conditioning systems that have all reached or exceeded their expected useful life.

Other Public Buildings: (Animal Care Facility, Living Coast Discovery Center, Ken Lee Building) In  addition  to  the  buildings  discussed  previously,  there  are  other  public  buildings  such  as  the  Animal Care Facility, Living Coast Discovery Center, and Ken Lee Building which are also in need of heating and air conditioning replacements, roof and plumbing repairs, flooring replacements, restroom renovations and upgrades to meet ADA standards.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

13 Amendment #11   Apr 2023
Citywide Network Replacement
The  overall  computer  network  which  provides  all  the  connectivity  between  PC’s,  servers,  phones  and other  network  attached  devices  throughout  the  City  is  outdated  with  20%  of  the  equipment  beyond end‐of‐life status, and a majority of the rest of the equipment within a year of end‐of‐life status. Due to advancements  in  technology  the  City  is  proposing  a  complete  restructuring  of  the  City’s  computer network in order to bring it up to industry standards in terms of: 1) Capability to handle high‐volumes of data traffic; 2) Provide industry standard reliability and redundancy to ensure near 100% up‐time across the  network;  and  3)  To  ensure  high  levels  of  security  and  resistance  to  modern  day  malware/hacking attacks. Measure P funds will be used to upgrade the network, which will directly benefit the community by allowing for Smart City functionality which will reduce traffic congestion on streets, reduce associated carbon  emissions,  enable  enhanced  energy  savings  in  City  buildings,  provide  advanced  citizen engagement through data sharing and capabilities of virtual City Hall, and enable enhanced security at City parks and other locations.

In  addition  to  updating  the  City’s  network,  the  Public  Works  Department  deploys  approximately  45 laptops in the field in order for crews to be able to receive work orders in the field, and then capture data regarding issues they see in the field back into our asset management systems. The current fleet of laptops is over 5 years old and only has 3G wireless modems which allow them to transmit data back to the  Public  Works  Department.  3G’s  data  footprint  in  Chula  Vista  is  shrinking  due  to  wireless  carriers focusing on 4G and 5G deployments. There are many areas in the eastern portion of Chula Vista, which do  not  have  3G  connectivity.  This  means  crews  must  return  back  to  the  Public  Works  Department  to enter data. Types of data transmitted include photos and videos which require high‐speed connections.

Additionally, older laptops are limited in terms of processing speed and memory, which affects overall productivity  of  the  laptop  in  a  data  rich  environment.  Measure  P  funds  will  be  used  to  replace  these laptops which will provide time savings and better work productivity allocating more time for the crews to be out in the field serving the public.

Citywide Telecommunications
Measure P funds will be  used to upgrade its telecommunications system which is nearly 20 years old.

Although functioning, the back‐end equipment required to keep the phone system working is no longer manufactured.  This  requires  the  City  to  find  replacement  parts  through  used  equipment  if  any equipment  fails.  Due  to  the  age  of  the  phone  system,  it  is  becoming  extremely  difficult  to  find  used equipment to keep the system working. The phone system is also very limited in terms of how it can be used in a modern business environment. New modern systems are run over a computer network (Voice Over I.P. – VOIP) rather than by an analogue system. Analogue systems have significant limitations on how a phone system can be used, while more modern systems allow for video conferencing, computer screen sharing, call following (“desk phone” can be accessed regardless of location), and other features which  increase  productivity  and  responsiveness  for  employees  to  the  public.  An  updated telecommunications system will also significantly reduce the risk of systematic failure.

Infrastructure, Facilities and Equipment Expenditure Plan 2023

14 Amendment #11   Apr 2023