RESOLUTION NO. __________

RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CHULA VISTA (1) ACCEPTING BIDS AND AWARDING A
CONTRACT FOR “TELEGRAPH CANYON ROAD RAISED
MEDIAN IMPROVEMENTS (TRF0415) AND PEDESTRIAN

IMPROVEMENTS AT UNCONTROLLED MID -BLOCK

CROSSWALK AT CASTLE PARK MIDDLE SCHOOL
(TRF0411)” PROJECT TO TRI -GROUP CONSTRUCTION &
DEVELOPMENT, INC. IN THE AMOU NT OF $636,181; AND
(2) AMENDING THE FISCAL YEAR 2025 -26 CAPITAL

IMPROVEMENT PROGRAM BUDGET BY TRANSFERING
$150,000 IN TRANSNET FUND S FROM CIP PROJECT
“PAVEMENT MAJOR REHAB PROGRAM FY25 (STM0404)”
TO CIP PROJECT “ TELEGRAPH CANYON ROAD RAISED
MEDIAN IMPROVEMENTS (TRF0415)”

WHEREAS, Chapter 2.56 of Chula Vista Municipal code authorizes the City to contract for Public works; and

WHEREAS, on May 16, 2025, the Department of Engineering and Capital Projects solicited bids for the “Telegraph Canyon Road Raised Median Improvements (TRF0415) and Pedestrian Improvements at Uncontrolled Mid -Block Crosswalk at Castle Park Middle School (TRF011)” project in accordance with Chula Vista Municipal Code section 2.56.160(A); and

WHEREAS, on June 18, 2025, the Assistant Director of Engineering and Capital Projects received nine (9) sealed bids for the “Telegraph Canyon Road Raised Median Improvements (TRF0415) and Pedestrian Improvements at Uncontrolled Mid -Block Crosswalk at Castle Park Middle School (TRF011)” project; and

WHEREAS, the apparent low bid for the project was submitted by Tri-Group Construction and Development, Inc. (“Tri -Group”) in the amount of $636,181, which is approximately 9.9% below the Engineer’s estimate of $706,389; and

WHEREAS, staff has determined that the bid submitted by Tri-Group is responsive in all material respects to the bid specifications/requirements, and that Tri -Group is the lowest responsive and responsible bidder; and

WHEREAS, staff recommends awarding the contract to Tri -Group in the amount of $636,181; and

WHEREAS, staff recommends amending the fiscal year 2025-26 CIP Program budget by transferring $150,000 in TransNet funds from” Pavement Major Rehab Program FY25 (STM0404)” to “Telegraph Canyon Road Raised Median Improvements (TRF0 415)” for completion of the project.

Resolution No.

Page 2 ends

NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Chula Vista, that it:
1) Accepts bids and awards the public works contract for the “Telegraph Canyon Road Raised Median Improvements (TRF0415) and Pedestrian Improvements at Uncontrolled Mid-Block Crosswalk at Castle Park Middle School (TRF0411)” project to Tri-Group Construction & Development, Inc. in the amount of $636,181.’ 2) Amends the fiscal year 2025-26 Capital Improvement Program budget by transferring $150,000 in TransNet funds from “Pavement Major Rehab Program FY25 (STM0404)” to “Telegraph Canyon Road Raised Median Improvements (TRF0415) ” for completion of the project.

Presented by Approved as to form by

Matthew Little, PE Marco A. Verdugo
Deputy City Manager/ City Attorney
Director of Engineering & Capital Projects