Erickson Hall Construction Co.
Guaranteed Maximum Price
June 12, 2026
Chula Vista Fire Station 11 Budget
DBE Allowances
50,000
250,000
City Allowances
200,000
Construction Cost Subtotal 13,269,991
Subtotal 15,674,415
Subtotal 17,013,651
Guaranteed Maximum Price 17,183,788
1 Final Clean 40,930
2 Surveying 67,890
3 Materials Testing & Geotechnical Engineering 134,542
4 Concrete 1,331,087
5 Masonry 38,500
6 Structural Steel & Misc Metals 145,327
7 Rough Carpentry 818,436
8 Casework 480,388
9 Roofing 281,695
10 Sheet Metal 318,971
11 Building Insulation 48,490
12 Glass & Glazing 71,200
13 Doors, Frames & Hardware 227,684
14 Coiling Doors 331,686
15 Plaster & Drywall 794,786
16 Acoustical Ceilings 65,950
17 Flooring 239,755
18 Painting 96,124
19 Specialties 353,135
20 Signage 44,681
21 Window Treatment 14,200
22 Fire Protection 109,065
23 Plumbing 463,736
24 HVAC 861,283
25 Electrical 2,933,807
26 Earthwork 486,951
27 AC Paving & Striping 203,133
28 Landscape & Irrigation 484,093
29 Fences & Gates 262,305
30 Site Utilities 1,020,163
Testing & Inspections
Permit & Utility Fees
FF&E Allowance
DBE Construction Contingency- 5% 663,500
DBE General Requirements 1,560,924
Construction Administration (CA) 180,000
Fee - 6% 940,465
Insurance - 2% 313,488
COC Insurance 85,282
Bonds - 1% 170,137