Staff Report - Fiscal Year 2024 Congressionally Directed Spending funds El Camino Real Sustainable Streets Project Page 1 of 4

STAFF REPORT
TO: Mayor and Members of the City Council
FROM: Brad Donohue, Director of Public Works and Planning Abdulkader Hashem, Principal Project Manager
VIA: Daniel Barros, City Manager
MEETING DATE: February 11, 2026
SUBJECT: Fiscal Year 2024 Congressionally Directed Spending Funds For the El Camino Real Sustainable Streets Project

RECOMMENDATION
Staff recommends that the City Council adopt the following:

RESOLUTION APPROVING THE FISCAL YEAR 2024 CONGRESSIONALLY DIRECTED

SPENDING FUNDS ALLOCATED BY THE CITY/COUNTY ASSOCIATION OF

GOVERNMENTS OF SAN MATEO COUNTY (C/CAG) FOR THE EL CAMINO REAL SUSTAINABLE STREETS PROJECT PURSUANT TO CEQA GUIDELINE 15306 C

OUNCIL ADOPTED VALUES
The City Council approved a master plan that addresses bicycle and pedestrian safety and transportation deficiencies on El Camino Real (ECR) in Colma. This plan created a vision of how the highway could be reconstructed to accommodate all modes of transportation, a plan that endorses safety and promotes healthy modes of travel along ECR. The approval of the resolution is a continuation of the vision that ECR can be viable for all modes of travel.

BA

CKGROUND
In 2021, the City/County Association of Governments of San Mateo County (C/CAG) completed the San Mateo Countywide Sustainable Streets Master Plan. This Plan identified and prioritized hundreds of opportunities throughout San Mateo County, to integrate active transportation improvements with green stormwater infrastructure to provide water quality improvement and additional co-benefits, such as improving bicycle and pedestrian safety, enhancing urban greening, and reducing the impacts of climate change.

C/CAG, in coordination with five municipalities with high priority concept designs developed in the San Mateo Countywide Sustainable Streets Master Plan, including the City of Daly City, City of East Palo Alto, City of South San Francisco, County of San Mateo and Town of Colma, AGENDA ITEM #3
Staff Report - Fiscal Year 2024 Congressionally Directed Spending funds El Camino Real Sustainable Streets Project Page 2 of 4 submitted an application for $1,500,000 under the Fiscal Year 2024 Congressionally Directed Spending (CDS) program, through Congressmember Kevin Mullin’s Office and Senator Alex Padilla’s Office to fund planning and design for up to five high priority sustainable street projects, including the El Camino Real Sustainable Streets Project in Colma.

As requested by C/CAG and agreed upon by the selected local agencies recommended for funding, including the City of Daly City, City of East Palo Alto and Town of Colma, Caltrans approved a request to suballocate the $850,000 in total CDS funding designated for the San Mateo County Sustainable Streets Pilot Project to the three selected local agencies and to enter into funding agreements with the respective local agencies directly, without C/CAG acting as a passthrough for funding to the local agencies.

On April 22, 2025, the Town of Colma and the City/County Association of Governments of San Mateo County (C/CAG) formally entered into a Memorandum of Understanding (MOU). The purpose of this MOU is to define the roles, responsibilities, terms, and conditions for administering the $370,500 of the allocated $850,000 to the Town of Colma in Fiscal Year 2024.

CDS funds, which are allocated for the planning and design of the Colma El Camino Real Sustainable Streets Project “Segment A”, which is component of the larger El Camino Real Bicycle and Pedestrian Improvement project.

Detailed Description of the Project
The El Camino Real Bicycle and Pedestrian Improvement Project aims to enhance safety, provide multimodal accessibility, improve connectivity and access to public transportation, and support economic growth by providing continuous sidewalks and dedicated bicycle lanes along approximately 1.5 miles of El Camino Real/State Route (SR) 82 between Albert M Teglia Boulevard in the Town of Colma and Hickey Boulevard in the City of South San Francisco. The project is divided into three segments: Segment A from Albert M. Teglia Boulevard to Mission Road, Segment B from Mission Road to Arlington Drive in the Town of Colma, and Segment C from Arlington Drive to Hickey Boulevard in the City of South San Francisco.

The Project scope involves the design (Plans, Specifications and Estimates) for Green Landscaping/Infrastructure for the El Camino Real Sustainable Streets Project Segment A. This green landscaping feature will provide stormwater treatment along with detaining stormwater flow into the Town’s drainage system, enhancing urban greening, and improving overall community health, climate resiliency and an aesthetic pleasing landscape buffer between pedestrian sidewalks and bike paths.

ENVIRONMENTAL
City Council’s action in adopting the resolution is exempt from environmental review under the California Environmental Quality Act (CEQA) pursuant to CEQA Guideline 15306 as information collection, (Production of plans, specifications and estimates). The resolution will authorize information gathering for the Sustainable landscaping features that will parallel both the East and West side of Segment A of the Project. Approval of the resolution allows the Town to expense CDS funding for the development of the Plans, Specifications and Estimates for the Project. Approval of the design will come from both the Town of Colma and Caltrans. Once the Staff Report - Fiscal Year 2024 Congressionally Directed Spending funds El Camino Real Sustainable Streets Project Page 3 of 4 design has been approved, Staff will analyze the design to determine the appropriate level of CEQA review. CEQA will then be considered by the decision makers prior to approval of any construction of the project.

ANALYSIS
Since El Camino Real is a state-owned roadway, all improvements must be approved by Caltrans. The proposed improvements will require various levels of documentation, studies, and reviews to receive Caltrans’s approval at each stage, from project initiation to construction. The Project Study Report-Project Development Support (PSR-PDS) phase was completed and approved by Caltrans in February 2025. The next phase, Project Approval and Environmental Document (PA&ED), is currently in development and is expected to be finished in May 2026.

Following the PA&ED approval, the project will move into the Plan, Specifications and Estimate (PS&E) and Right of Way (ROW) stage of the project.

C/CAG and the Town have agreed to allocate $370,500 of the total amount of $850,000 provided by the Fiscal Year 2024 Congressionally Directed Spending program under the San Mateo County Sustainable Streets Design Pilot Project for the El Camino Real Sustainable Streets Project Segment A (Project).

The Fiscal Year 2024 Congressionally Directed Spending program, administered by the Federal Highway Administration, requires an 11.47% non-federal local match from Colma, totaling $48,002. The local match corresponds to the full grant amount of $370,500 allocated to the El Camino Real Sustainable Streets Project (Segment A).

A City Council resolution is required to approve the acceptance and use of the Fiscal Year 2024 CDS funds allocated by C/CAG. These funds are designated for the design of the Colma El Camino Real Sustainable Streets project, which is part of the larger El Camino Real Bicycle and Pedestrian Improvement project.

FISCAL IMPACT
The Town’s estimated funding plan for the PS&E of the El Camino Real Sustainable Streets Project is as follows:

• Fiscal Year 2024 Congressionally Directed Spending (CDS) funds $ 370,500 • Proposed CIP Allocation for FY 25-26 (Local Match 11.47%) $ 48,002

Estimated Project Total: $ 418,502

The $48,002 required for local match funding will be appropriated with the FY 2026-27 budget using a transfer of General Fund unassigned fund balance.

The Town of Colma is the project's sponsor and implementing agency. The Project must be completed by the CDS program deadline of September 30, 2032.

Staff Report - Fiscal Year 2024 Congressionally Directed Spending funds El Camino Real Sustainable Streets Project Page 4 of 4

SUSTAINABLE IMPACT
This resolution in support of Green Landscaping/Infrastructure of the El Camino Real Sustainable Streets Project is consistent with the Town’s sustainability goals and Complete Streets and Green Streets Program goals.

AL

TERNATIVES
The City Council could choose not to accept the Fiscal Year 2024 Congressionally Directed Spending funds. Doing so is not recommended, the Town would lose this funding opportunity to assist with the development of the PS&E’s for the Green Landscaping/Infrastructure portion of Segment A of El Camino Real Sustainable Streets Project.

CO

NCLUSION
St
aff is requesting that City Council adopt a resolution to accept and authorize the use of the allocated Fiscal Year 2024 Congressionally Directed Spending funds. The funding will be used exclusively for the design of the Green Landscaping/Infrastructure in Segment A of the El Camino Real Sustainable Streets project.

A

TTACHMENTS
A. Re
solution
B. Memorandum of Understanding between C/CAG and Colma
R
ESOLUTION NO. 2026-XX

OF THE CITY COUNCIL OF THE TOWN OF COLMA
RES
OLUTION APPROVING THE FISCAL YEAR 2024 CONGRESSIONALLY DIRECTED

SPENDING FUNDS ALLOCATED BY THE CITY/COUNTY ASSOCIATION OF

GOVERNMENTS OF SAN MATEO COUNTY (C/CAG) FOR THE EL CAMINO REAL SUSTAINABLE STREETS PROJECT PURSUANT TO CEQA GUIDELINE 15306 T
he City Council of the Town of Colma does resolve as follows:
1 . Background
(a) Th
e City/County Association of Governments of San Mateo County (C/CAG) manages the San Mateo Countywide Water Pollution Prevention Program to support its member agencies in meeting state and federal mandates to reduce pollution discharging from municipal storm drainage systems.
(b) In 2021, C/CAG completed the San Mateo Countywide Sustainable Streets Master Plan, which identified and prioritized hundreds of opportunities throughout San Mateo County to integrate active transportation improvements with green stormwater infrastructure to provide water quality improvement and additional co-benefits, such as improving bicycle and pedestrian safety, enhancing urban greening, and reducing the impacts of climate change. (c) C/CAG, in coordination with five municipalities with high priority concept designs developed in the San Mateo Countywide Sustainable Streets Master Plan, including the City of Daly City, City of East Palo Alto, City of South San Francisco, County of San Mateo and Town of Colma, submitted an application for $1,500,000 under the Fiscal Year 2024 Congressionally Directed Spending program, herein referred to as “CDS”, through Congressmember Kevin Mullin’s Office and Senator Alex Padilla’s Office to fund planning and design for up to five high priority sustainable street projects, under the CDS project title “San Mateo County Sustainable Streets Pilot Project”. (d) The Consolidated Appropriations Act of 2024 included an appropriation of $850,000 under the CDS program for Fiscal Year 2024 and lists C/CAG as the recipient of said funds to implement the San Mateo County Sustainable Streets Pilot Project. (e) The Federal Highway Administration is authorized to allocate the CDS funding via the California Department of Transportation, herein referred to as “Caltrans,” through the Caltrans Local Assistance Program to implement the San Mateo County Sustainable Streets Pilot Project. (f) C/CAG, in coordination with the local agencies included in C/CAG’s San Mateo County Sustainable Streets Pilot Project application, went through a process of recommending funding three of the five sustainable streets projects, based on project readiness and local buy in. (g) As requested by C/CAG and agreed upon by the selected local agencies recommended for funding, including the City of Daly City, City of East Palo Alto and Town of Colma, Caltrans approved a request to suballocate the $850,000 in total CDS funding designated for the San Mateo County Sustainable Streets Pilot Project to the three selected local agencies and to enter into funding agreements with the respective local agencies directly.

ATTACHMENT A
2 . Approval and Authorization
(a) The City Council hereby approves the Fiscal Year 2024 Congressionally directed spending funds allocated by C/CAG for the El Camino Real Sustainable Streets Project “Segment A”. (b) The Town of Colma have agreed to allocate $370,500 of the total amount of $850,000 provided by the Fiscal Year 2024 CDS program for the planning and design of the Colma El Camino Real Sustainable Streets Project “Segment A” (Project), which is component of the larger El Camino Real Bicycle and Pedestrian Improvement project.
(c) On April 22, 2025, the Town of Colma and C/CAG formally entered into a Memorandum o
f Understanding (MOU) for outlining and defining roles, responsibilities, terms, and conditions for administering the allocated $370,500 CDS funds to the Town. (d) The T own has agreed to provide the associated 11.47% (percent) local match requirement of $48,002.
(e) The Town will ensure timely obligation of the CDS funding for the Project, consistent with the Fiscal Year 2024 CDS program Caltrans E-76 deadline of September 30, 2027. (f) The Town agrees to complete the Project scope by the Fiscal Year 2024 CDS program deadline of September 30, 2032.

C
ertification of Adoption
I certify that the foregoing Resolution 2026- __ was duly adopted at a regular meeting of said City Council held on February 11, 2026, by the following vote:

N
ame Voting Present, Not Voting Absent
Ay e No Abstain Not Participating
Carrie Slaughter, Mayor
Helen Fisicaro
Ken Gonzalez
Joanne F. del Rosario
Thomas Walsh
Voting Tally
D
ated ______________________ ___________________________________ Carrie Slaughter, Mayor
At
test: ____________________________
Michelle Estabillo, City Clerk

MEMORANUM OF UNDERSTANDING

BETWEEN

THE CITY/COUNTY ASSOCIATION OF GOVERNMENTS OF SAN MATEO COUNTY AND THE TOWN OF COLMA FOR ADMINISTERING $370,500 IN FISCAL YEAR 2024 CONGRESSIONALLY DIRECTED SPENDING FUNDS FOR PLANNING

AND DESIGN OF THE COLMA EL CAMINO REAL SUSTAINABLE STREETS PROJECT.

This Memorandum of Understanding (MOU) entered into as of the _22nd day of_April_, 2025, by and between the City/County Association of Governments of San Mateo County, herein referred to as “C/CAG,” and the Town of Colma, herein referred to as "TOWN,” collectively referred to as “PARTIES,” is for the purpose of outlining and defining the roles, responsibilities, terms and conditions for administering $370,500 in Fiscal Year 2024 Congressionally Directed Spending funds for planning and design of the Colma El Camino Real Sustainable Streets Project, hereinafter referred to as “PROJECT”.

RECITALS
WHEREAS, C/CAG manages the San Mateo Countywide Water Pollution Prevention Program to support its member agencies in meeting state and federal mandates to reduce pollution discharging from municipal storm drainage systems; and WHEREAS, in 2021, C/CAG completed the San Mateo Countywide Sustainable Streets Master Plan, which identified and prioritized hundreds of opportunities throughout San Mateo County to integrate active transportation improvements with green stormwater infrastructure to provide water quality improvement and additional co-benefits, such as improving bicycle and pedestrian safety, enhancing urban greening, and reducing the impacts of climate change; and
WHEREAS, the San Mateo Countywide Sustainable Streets Master Plan included 12 project concepts for high priority sustainable streets projects focusing in areas of underserved and vulnerable communities, with the intention of supporting future funding for implementation; and
WHEREAS, C/CAG, in coordination with five municipalities with high priority concept designs developed in the San Mateo Countywide Sustainable Streets Master Plan, including the City of Daly City, City of East Palo Alto, City of South San Francisco, County of San Mateo and Town of Colma, submitted an application for $1,500,000 under the Fiscal Year 2024 Congressionally Directed Spending program, herein referred to as “CDS”, through Congressmember Kevin Mullin’s Office and Senator Alex Padilla’s Office to fund planning and design for up to five high priority sustainable street projects, including the PROJECT, under the CDS project title “San Mateo County Sustainable Streets Pilot Project”; and WHEREAS, the Consolidated Appropriations Act of 2024 included an appropriation of $850,000 under the CDS program for Fiscal Year 2024 and lists C/CAG as the recipient of said funds to implement the San Mateo County Sustainable Streets Pilot Project; and Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D

ATTACHMENT B
WHEREAS, there is an 11.47% (percent) non-federal local match requirement for the Fiscal Year 2024 CDS program administered by the Federal Highway Administration, totaling $110,127 for the entire grant amount of $850,000 allocated to the San Mateo County Sustainable Streets Pilot Project; and
WHEREAS, the Federal Highway Administration is authorized to allocate the CDS funding via the California Department of Transportation, herein referred to as “Caltrans,” through the Caltrans Local Assistance Program to implement the San Mateo County Sustainable Streets Pilot Project, including the PROJECT; and
WHEREAS, to best utilize the available CDS funding, C/CAG, in coordination with the local agencies included in C/CAG’s San Mateo County Sustainable Streets Pilot Project application, went through a process of recommending funding three of the five sustainable streets projects, including the PROJECT, based on project readiness and local buy in; and WHEREAS, as requested by C/CAG and agreed upon by the selected local agencies recommended for funding, including the City of Daly City, City of East Palo Alto and Town of Colma, Caltrans approved a request to suballocate the $850,000 in total CDS funding designated for the San Mateo County Sustainable Streets Pilot Project to the three selected local agencies and to enter into funding agreements with the respective local agencies directly, without C/CAG acting as a passthrough for funding to the local agencies; and WHEREAS, C/CAG and the TOWN wish to document the general expectations and roles and responsibilities for implementing the PROJECT under the San Mateo County Sustainable Streets Pilot Project.

Now, THEREFORE, the PARTIES to this MOU agree as follows:

1. SCOPE OF WORK
The PROJECT Scope of Work pursuant to this MOU includes planning, design and permitting only for the PROJECT, as originally envisioned through the project concept developed in C/CAG’s San Mateo Countywide Sustainable Streets Master Plan (see Exhibit A). It is expected that the PROJECT plans and designs under this Scope of Work shall be substantially consistent with the concept plan for the PROJECT (Exhibit A), recognizing plans and designs may need to be modified to accommodate site constraints, utility conflicts, and funding availability, among other considerations as the PROJECT develops. This MOU only pertains to the Scope of Work as defined herein. The main components of the PROJECT, as originally envisioned in the San Mateo Countywide Sustainable Streets Master Plan, are summarized as follows:

Colma El Camino Real Sustainable Streets Project:
• The El Camino Real Sustainable Streets Project Segment A (PROJECT) is a component of a larger El Camino Real (State Route 82) Improvement Project. Segment A extends Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D

from El Camino Real between Albert M. Teglia Boulevard and Mission Road intersection within the Town of Colma.

• The proposed improvements on Segment A include construction of new accessible sidewalks, protected bicycle facilities, ADA curb ramps, high-visibility crosswalks, energy efficient street lighting, landscaping, bioretention planters, and safe harbor bus stops.

The PARTIES further recognize that the full scope and scale of the PROJECT, as originally conceptualized in the San Mate Countywide Sustainable Streets Master Plan, would require additional funding to complete 100% (percent) engineering plans and specifications and cost estimates, and may require additional funding for permitting beyond the amount provided for the PROJECT through the CDS funding. As such, the PARTIES agree that the TOWN will advance the PROJECT planning, design and permitting to the greatest extent feasible as defined within this Scope of Work with the funds made available through the Fiscal Year 2024 CDS program.

2. FUNDING ALLOCATION
a. Funding Commitment. C/CAG and the TOWN have agreed to allocate $370,500 of the total amount of $850,000 provided by the Fiscal Year 2024 CDS program under the San Mateo County Sustainable Streets Design Pilot Project for the PROJECT.

The TOWN has agreed to provide the associated 11.47% (percent) local match requirement of $48,002.

3. TERM OF MOU
a. This MOU is effective upon execution and will terminate upon the earliest of: (a) six months after written acceptance of C/CAG of the completion of the Scope of Work, (b) termination by C/CAG pursuant to Section 2.c. of this MOU, or (c) September 30, 2027.

4. GENERAL RESPONSIBILITIES
a. C/CAG.
• As the named funding recipient for the Fiscal Year 2024 CDS funding allocated to the San Mateo County Sustainable Streets Design Pilot Project pursuant to the authorizing legislation (Consolidated Appropriations Act of 2024), C/CAG is committed to the success of the PROJECT Scope of Work and will provide in- kind staff and consultant support to the TOWN in preparing the PROJECT for inclusion in the Federal Transportation Improvements Program (FTIP) 2025 Amendment and to support the TOWN in submitting its E-76 federal obligation request through Caltrans.

• C/CAG reserves the right to request review of the funding agreement between the TOWN and Caltrans prior to execution to ensure substantial consistency with the San Mateo County Sustainable Streets Pilot Project.

Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D

• As needed, C/CAG will continue to seek additional funding to complete planning, design, and permitting for the PROJECT.

• As needed, C/CAG will continue to seek state and federal funding for the construction of the PROJECT.

b. TOWN.
• As the PROJECT sponsor, the TOWN will ensure timely obligation of the CDS funding for the PROJECT, consistent with the Fiscal Year 2024 CDS program Caltrans E-76 deadline of September 30, 2027.

• The TOWN agrees to complete the Scope of Work as detailed in Section 1 by the Fiscal Year 2024 CDS program deadline of September 30, 2032.

• As needed, the TOWN will continue to seek additional funding to complete planning, design, and permitting for the PROJECT.

• As needed, the TOWN will continue to seek state and federal funding for the construction of the PROJECT.

5. HOLD HARMLESS/ INDEMNITY
The PARTIES agree to fully indemnify, defend, and hold each other (including their appointed and elected officials, officers, employees, and agents) harmless and free from any damage or liability imposed for injury occurring by reason of the negligent acts or omissions or willful misconduct of the indemnifying PARTY, its appointed or elected officials, officers, employees, or agents, under or in connection with any work, authority, or jurisdiction delegated to such PARTY under this MOU. No PARTY, nor any appointed or elected official, officer, employee, or agent thereof, shall be responsible for any damage or liability occurring by reason of the negligent acts or omissions or willful misconduct of any other PARTY, its appointed or elected officials, officers, employees, or agents, under or in connection, with any work, authority, or jurisdiction delegated to such other party under this MOU.

6. NOTICES
All notices affecting any of the clauses of this MOU must be in writing via email to the appropriate address indicated below.

To C/CAG:

City/County Association of Governments of San Mateo County Attn: Reid Bogert, C/CAG Stormwater Program Director
Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D

Email: [email protected]

To TOWN:

Town of Colma
Attn: Abdulkader Hashem, Principal Project Manager
Email: [email protected]
IN WITNESS WHEREOF, the PARTIES have executed this MOU on the date set forth above.

AGREED AND EXECUTED BY:

CITY/COUNTY ASSOCIATION OF GOVERNMENTS OF SAN MATEO COUNTY

By: Date: , 2025

Title:

TOWN OF COLMA

By: Date: , 2025

Title:

Approved as to Form:

By:

Name:

Legal Counsel for C/CAG

Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D City Manager
4/22/2025
Melissa Andrikopoulos
4/22/2025
Executive Director, C/CAG

EXHIBIT A

PROJECT CONCEPT FOR THE COLMA EL CAMINO REAL SUSTAINABLE STREETS PROJECT

FROM THE SAN MATEO COUNTYWIDE SUSTAINABLE STREETS MASTER PLAN Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D

PROJECT SITE
COLMA

SOUTH SAN

FRANCISCO

DALY CIT Y
I-280
CA-1
I-280
E-8
San Mateo Countywide Sustainable Streets Master Plan
El Camino Real Colma
El Camino Real (State Highway 82) through the T own of
Colma is being redesigned with pedestrian and bicycle
improvements. The design includes new landscaping,
the addition of a protected bike lane in both directions, new signaling, and a lane reduction from C Street to
Mission Street. This concept proposed to integrate green stormwater infrastructure in the planned transportation improvements.

The proposed vegetated median separating the
bike lanes from vehicular traffic is 5 to 6 feet wide. At T-intersections and at intersection approaches the
proposed median widens to 10 to 13 feet. Portions of the vegetated median on the northeast side of El Camino Real can be installed as bioretention facilities that collect and manage stormwater runoff from the roadway, bike lanes,
and sidewalks. The remaining portions of the median
can be landscaped with trees and graded to direct flow
towards the bioretention areas. The proposed median on
the southwest side of El Camino Real is located above a water main making bioretention facilities infeasible.

The bioretention facilities are shown for the block
extending north of Collins Road representing a typical
block within the corridor. The same design can be applied to the full extent of improvement from C Street through Mission Street. The proposed bioretention facilities
shown on the typical block represent 3,300 square feet
of facilities. This project will manage stormwater from

1.9 acres of roadway and provide capture of 3.5 acre-
feet of runoff per year. The project is expected to retain approximately 68.6% of runoff.

Concept Description
Site Characteristics
In Priority Development Area
Yes
Pavement Condition Index
Not Available
Watershed
Colma Creek
Green Infrastructure
Performance
Drainage Management Area

1.9 ac
Annual Runoff Captured

3.5 ac-ft
Bioretention Area / Storage Volume
3,300 sf / 0.10 ac-sf
Active Transportation
Performance
Change in Bicycle Level of Traffic
Stress (LTS)

LTS 4 to LTS 1
Increase in % Likely Bicyclist Usage
99%
Key Transportation Benefits
» Reduced pedestrian crossing
distance
» Protected bike space
» Road diet
[ ]
Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D 0 100’25’ 50’ 75’
E-9
Typical Concept Site Plan Detail: El Camino Real, Colma 22’
El Camino Real
Northbound
6’
Sidewalk
5’
Bike
Lane
6’
Planter
5’
Bio-
retention
5’
Bike
Lane
6’
Side-
walk
9’
Parking
Lane
8’
Parking
Lane
33’
El Camino Real
Southbound
15’
Planter Median

EL CAMINO REAL

COLLINS RD
Typical Cross Section Detail: El Camino Real
Proposed bioretention planter
Proposed planter buffer
Proposed protected bike lane
Existing planter median

KEY SITE IMPROVEMENTS
A

A A A A
D D D
C
C
CB
B
B B
B B
Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D E-10
Existing condition, El Camino Real Proposed condition
Site Elements
Concept Perspectives
El Camino Real Colma
Bioretention planter buffer, Portland Landscaped raised planter median, Farragut TN Class IV bike lane and parking lane, Sacramento Cannon & Cannon Engineers
Sacramento Area Council of Governments
Sergio Ruiz, NACTO
City of Portland Environmental Services
Class IV bike lane with planter buffer, Oak St, San Francisco CA Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D E-11
Increased Trees
Shade for walking comfort
Heat and carbon emission reduction
Neighborhood Beautification
Increased vegetation
Provide engaging streets to walk on
Groundwater Recharge
Recharge of the Westside Groundwater
Basin
Reestablishes Natural Hydrology
Bioretention planters capture and infiltrate
stormwater
Project Benefits
Bikeability & Safety
Increased protected bike lanes
Increased bike-share roads
Walkability & Safety
Curb extensions for safer street crossing
Connection to commercial areas
Bike Network
Part of larger network for connectivity
Promote biking with more connectivity
Prioritize Non-Motorized Users
Convert car lanes for biking & walking
Promote more active transportation
Planning-Level Cost Estimate

DESCRIPTION UNIT COST UNIT COST QUANTITY SUBTOTAL
Utilities Protection/Relocation $100,000 LS 1 $100,000
Sawcutting Pavement $12 LF 4,100 $49,200
Concrete Demo, Excavation & Offhaul $11 SF 10,900 $119,900 Planter Excavation & Offhaul $70 CY 5,750 $402,500
Planter Curb & 36" Sidewalls $160 LF 500 $80,000
Planter Curb & Gutter & 36" Sidewalls $180 LF 560 $100,800 Curb and Gutter $40 LF 4,780 $191,200
Bio-soil Media $250 CY 170 $42,500
Bioretention Plantings & Mulch $25 SF 3,100 $77,500
Trees $1,500 EA 35 $52,500
Landscaping Soil $125 CY 410 $51,250
Landscaping Plantings & Mulch $20 SF 5,430 $108,600
Underdrains $6 SF 1,600 $9,600
Drain Rock Subbase $160 CY 110 $17,600
Storm Drain Connections $7,500 EA 6 $45,000
Curb Ramps $6,000 EA 4 $24,000
Crosswalk Striping $6,000 EA 2 $12,000
Bike Lane Striping $12 SF 9,850 $118,200
Irrigation System $22,300 EA 3 $66,900
Asphalt and Subbase for Turn Lanes $15 SF 1,600 $24,000 Traffic Sign Relocation $900 EA 13 $11,700
CONSTRUCTION SUBTOTAL $1,705,000
Traffic Control $170,500
Mobilization (10% construction) $171,000
Contingency (30% construction) $512,000
Design Fees (15% total) $384,000
TOTAL PROJECT COST (DESIGN + CONSTRUCTION) $2,943,000
This is a planning-level cost estimate ($2020) for design and construction. Soft costs for City administration and project management and post-construction operations and maintenance are not included.

Other factors that may affect the cost of future construction include escalation and market conditions.

Docusign Envelope ID: C91F3B8E-10FD-466F-B04E-82281053DC2D E-12
This project concept is presented for discussion only. This project concept is planning-level and subject to revision as additional information becomes available. Factors to be considered during design of this project include but are not limited to the following:
» Infiltration Potential. Soils around El Camino Real in Colma are classified as hydrologic soil group (HSG) B which indicates potentially good soils for infiltrating. A geotechnical investigation will be conducted during design development, including site-specific borings and infiltration tests, to ensure facilities are designed appropriately.

Proposed green infrastructure improvements may be lined with impermeable geotextile and fitted with underdrain pipes to connect treated flows to existing storm drain line if infiltration is deemed infeasible. » Utility Conflict. An initial utility assessment was conducted for sanitary sewer, storm sewer, water, electrical, and telecom. Bioretention facilities are proposed in configurations that minimize disruption of water and sewer lines. » Regional Stormwater Management. The existing water main precludes locating a bioretention planter within the median on the southwest side of El Camino Real. There is potential to route runoff from this side of the street towards the open space on the northeast side of El Camino near the intersection with Mission Street. Within the available space a regional stormwater facility could provide storage and infiltration of runoff from the large portion of El Camino Real.
» Irrigation. Green infrastructure planters should be irrigated to ensure establishment and maintenance of healthy plants during periods with no rain. The planning-level cost estimate includes an irrigation system for the bioretention planters.

Additional Considerations
El Camino Real Colma