ID Task Name Duration Start Finish
1 City of Commerce - Energy Project 332 days Fri 3/1/24 Mon 6/9/25 5 Bandini Park 156 days Fri 3/1/24 Fri 10/4/246 Interior Lighting 3 days Fri 3/1/24 Tue 3/5/247 Exterior Lighting 21 days Wed 3/6/24 Wed 4/3/24 10 Transformers 12 days Mon 5/20/24 Tue 6/4/24
8 HVAC 28 days Mon 8/12/24 Wed 9/18/249 HVAC Controls 12 days Thu 9/19/24 Fri 10/4/24 11 City Hall Complex 299 days Thu 4/4/24 Tue 5/27/2514 Interior Lighting 14 days Thu 4/4/24 Tue 4/23/2413 Roofing 45 days Mon 6/17/24 Fri 8/16/2415 Solar 72 days Mon 11/25/24 Tue 3/4/2512 HVAC 42 days Wed 3/5/25 Thu 5/1/2516 HVAC Controls 18 days Fri 5/2/25 Tue 5/27/2521 Rosewood Park 20 days Wed 4/24/24 Tue 5/21/2422 Interior Lighting 8 days Wed 4/24/24 Fri 5/3/2423 Exterior Lighting 12 days Mon 5/6/24 Tue 5/21/24 2 Senior Center 12 days Wed 5/22/24 Thu 6/6/244 Interior Lighting 8 days Wed 5/22/24 Fri 5/31/243 Exterior Lighting 4 days Mon 6/3/24 Thu 6/6/24 17 Teen Center 279 days Fri 6/7/24 Wed 7/2/2518 Interior Lighting 15 days Fri 6/7/24 Thu 6/27/2419 Exterior Lighting 2 days Fri 6/28/24 Mon 7/1/2420 HVAC Controls 26 days Wed 5/28/25 Wed 7/2/25 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul 24 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025 Qtr 3, 202 TaskSplitMilestoneSummary
Project SummaryInactive TaskInactive MilestoneInactive Summary Manual TaskDuration-onlyManual Summary RollupManual Summary Start-onlyFinish-onlyExternal TasksExternal Milestone
DeadlineProgressManual Progress
Project: chaseDate: Thu 2/8/24