RESOLUTION NO.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF COMMERCE, CALIFORNIA, AWARDING A CONSTRUCTION CONTRACT TRUELINE CONSTRUCTION & SURFACING, INC. FOR THE BASKETBALL/VOLLEYBALL COURTS RESURFACING AT VARIOUS CITY PARKS PROJECT AND AUTHORIZING CONSTRUCTION MANAGEMENT AND INSPECTION SERVICES BY TRANSTECH ENGINEERS, INC., PURSUANT TO THEIR ON-CALL PROFESSIONAL SERVICES CONSULTING AGREEMENTS WHEREAS, on August 23, 2022, City Council approved the Annual Operating and Capital Improvement Program (CIP) for Fiscal Year 2022/2023 which included the Basketball/Volleyball Courts Resurfacing at Various City Parks Project and an appropriation of $200,000; and WHEREAS, on November 29, 2022, staff advertised the construction bid package for the Basketball/Volleyball Courts Resurfacing at Various City Parks Project with one (1) bid submitted to the City at the Bid Opening held on December 21, 2022; and WHEREAS, the lowest responsible bidder for the base bid for the construction contract is Trueline Construction & Surfacing, Inc.; and WHEREAS, staff is recommending award of a contract based to Trueline Construction & Surfacing, Inc. in the amount of $243,686.40 reflecting total of base bid and additive bid item in their bid schedule.
WHEREAS, the total estimated cost of this project including the construction contract, contingencies, construction management and inspection services is $304,608, and WHEREAS, sufficient Measure AA funds are available to cover the total project cost; and WHEREAS, the project is Categorically Exempt pursuant to section 15301 Class 1 of CEQA due to repair and resurfacing of existing basketball and volleyball courts.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF COMMERCE DOES HEREBY RESOLVE, DECLARE AND DETERMINE AS FOLLOWS:
Section 1. The City Council of the City of Commerce hereby finds and declares that the foregoing recitals are true and correct, and incorporates them herein as findings and as a substantive part of this Resolution.
Section 2. Approve Plans and Specifications for the Basketball/Volleyball Courts Resurfacing at Various City Parks Project.
Section 3. Award a construction contract to Trueline Construction & Surfacing, Inc., the lowest responsible bidder, for the Basketball/Volleyball Courts Resurfacing at Various City Parks Project, in the amount of $243,686.40 and authorize the Mayor to execute the contract in a form approved by City Attorney.
Section 4 Authorize construction contingencies in the amount of $36,552.96 (15%) for unforeseen conditions.
Section 5. Authorize Transtech Engineers, Inc. to proceed with Construction Management and Inspection Services, in the amount of $24,368.64 (10% of total construction cost), pursuant to their existing On-Call Professional Service Agreement.
Section 6. Approve a supplemental appropriation of $104,608 from Measure AA funds to cover the total project cost as recommended by the Measure AA Advisory Committee on January 17, 2023.
Section 7. All procedures of the California Environmental Quality Act (“CEQA”), California Public Resources Code §21000 et seq., and the CEQA guidelines, title 14 of the California Code of Regulations, chapter 3, §15000 et seq. have been satisfied and the City Council has found that the proposed Project is Categorically Exempt from California Environmental Quality Act (CEQA) requirements under provisions of CEQA Guidelines Section 15301 – Existing Facilities. This exemption applies to projects characterized as repairs to existing facilities meeting the conditions described in Section 15301.
Pursuant to CEQA, the City Council finds and determines there is no substantial evidence that the Project could have a significant effect on the environment. The City Council in its independent judgment finds that there is no possible significant effect directly related to the Project because the Project consists of the repair and resurfacing of existing public facilities; basketball and volleyball courts where there is negligible or no expansion of the use. The City Council finds that the Project will not cause any physical change in the environment, that the Project is categorically exempt from CEQA under Administrative Code, Title 14, Chapter 3, § 15301, Class 1, Existing Facilities, and therefore no further action is required under CEQA.
Section 8. Authorize the Mayor to execute the Resolution for and on behalf of the City of Commerce.
Section 9. This Resolution shall take full force and effect immediately upon adoption by the City Council.
PASSED, APPROVED and ADOPTED this 21st day of February 2023.
Oralia Y. Rebollo, Mayor