Capital Improvement Program Overview
Fiscal Year 2023/2024
Completed Projects
Camp Commerce pool re-plastering and new equipment installation Pavement Rehab – FY 22/23
Bandini Blvd. at I-5 Freeway restriping
Mixmaster Phase 1 – striping, pavement markings and signal timing Highway Safety Improvement Program (HSIP) Cycle 7 Program for Eastern, Telegraph, Slauson, Atlantic, and Garfield – 27 new traffic signal cabinets, foundations, controllers, timing updates, and battery back-up system Commerce Way Street Improvements - 2 new street lights to be installed in July 2023 Fiscal Year 2022/2023
Projects In Progress
Eastern Median Improvements (city limits) – completion in August 2023 Basketball/volleyball outdoor courts resurfacing at 3 parks –completion in August 2023 I-5 Freeway SB Eastern exit beautification with lighted monument sign and landscaping - In Design Randolph Corridor Improvements - In Design
Pathways for Hope Connectivity Improvements - In Design Ferguson Sidewalk Installation – Design Completed, Out to bid Mixmaster Ph. 2 NB Atlantic Right Turn Pocket – In Design Citywide Lighting Assessment – In Design
Telegraph Rd. from Atlantic to Mariana Concept Plan Approved – next step is Design Services bid release Civic Center Turf Replacement and Library Learning Garden Improvements – Award of contract planned for June 27th Wayfinding award of contract planned for June 27th
Camp Commerce Retaining Wall Replacement – construction to start July 31st with completion by mid September 2023 BVAC pool filtration replacement – awarded contract - completion in fall/winter 2023 per pool activity schedule Fiscal Year 2022/2023
City of Commerce Capital Improvement Program
Measure AA Advisory Committee Project Update and Funding Requests Fiscal Year 2023/2024
Bandini Library Learning Center
$2,500,000 project cost requested for design and construction Improvements to include environmental abatement, a new roof, and redesign of interior spaces Concept Plan approved
4 Proposals for Design Services received
City Council awarded agreement on May 30, 2023 for Design for $3.00 Library Improvements
Senior Center Roof Condition
City needs a proactive schedule for roof repairs and replacements for all its buildings First priority is Senior Center and Bristow Park
Senior Center Food Program requires an LA County Health Department Permit and inspections Senior Center sustained water intrusion in the kitchen and dining area causing the food program to be temporarily relocated to Rosewood Park Roofing companies are currently inspecting the roof and providing estimates Roof Conditions
Park and Open Space Master Plan
Completed Park and Open Space Master Plan
Stakeholder survey results shown here for programs and facilities Presentations in May 2023 to Parks and Recreation Commission and City Council Planning document to help prioritize needs and future capital improvements $9.4 in park and facility recommendations including repairing roofs, modernizing buildings, improving restrooms, repairing or replacing fitness stations at parks, repairing and renovating the boxing gym at Bristow Park, and repairing and renovating the swimming and spray pools Park and Facility Improvements
Bristow Park Redesign Options
Design services to determine options and costs for retrofitting existing building with potential removal of atrium to expand usable space with new roof and HVAC vs. new build Roundabout speeding issue at shared driveway with County facilities Overnight parking issues on public property at roundabout Delivery trucks regularly strike roundabout and damage lighting Design services needed to reconfigure this location to enhance safety for pedestrians and motorists Opportunity to enhance Bristow Park and Library with a Learning Garden Implementing the Park Master Plan and Improving Safety
Digital Public Notice Kiosk
Commerce continues to modernize its ways of communicating with the community and would like to install a digital kiosk in front of City Hall for all public meeting postings and other information that can be easily updated from any computer
Central Library Learning Garden Reading Patio
Two temporary white painted plywood square wall areas would be replaced with a glass door and windows, benches, fabric awning over patio, and outdoor lighting to follow the Library Learning Garden Installation Project starting in Summer 2023 Learning Outdoors
Telegraph Corridor Improvements
$600,000 project cost requested for design and construction Atlantic Blvd. to Marianna Ave. (City limit)
Feasibility Study completed
Council approved Concept Plan
Removed uncontrolled crosswalks and relocated closer to bus stops Design Services need to be released for bidding
Improvements may include restriping for dedicated left turn lanes, bulb-outs at intersections for pedestrian safety, sidewalk repairs, trees, curb painting, centerline adjustments, and repurposing of historic light poles.
Active Mobility Enhancements
1. Bristow Park Basketball Courts Resurfacing Project - Additional Work New Requests for Funding
2. Wayfinding Signs Project
Requesting $87, 811 for:
Removal of top 10' of existing 20' fence and entire fence between double courts.
Provide and install new 10' galvanized chain link fabric to all fence.
Remove two existing gooseneck posts, backboards and footings and install two new Bison equipment Project underway and previously allocated $200,000 of Measure AA Funds for three parks: Bristow, Bandini and Rosewood Requesting $184, 377.94 to:
Award a contract to the lowest responsible bidder for the Citywide Wayfinding Vehicular Directional Signs Project (7 bids received).
In 2019, the City received only one bid in the amount of $255,100.
New contract will Install 46 signs at gateways, major intersections and major roadways.
Measure AACIP Project Prioritizing
Discussion