Option A – Complete streets with bike lanes as recommended Slauson Corridor Improvements Project Concept Plan Options Option B –
No bike lanes, include all other improvements
Metro I-710 Measure R and ATP Cycle 6 Grant funded
Next Steps: proceed with design, seek construction funds and bid out Fiscal Impact: No Change
Potential loss of $2.3M I-710 Measure R & $2.1 M ATP resulting in payment of design phase(KOA and Project Management) costs of $1,551,867 through local funds Next Steps: contact Metro and Caltrans to request change in scope Fiscal Impact: TBD by funding sources
Loss of I-710 Measure R funds and ATP Cycle 6 Grant, Cancellation of KOA Design Contract and Reconciliation of funds owed Next Steps: inform funding agencies of no project and cancel KOA contract and reconcile money owed to KOA for design services with local funds Fiscal Impact: $2.3 M + $2.1 M
Fiscal Impact: Unknown
Option C – Cancel project, make no improvements
Option D – Council provided alternative
Slauson PP Pres Options
Commerce City Council
November 14, 2023
- Document
- Slauson PP Pres Options
- Meeting
- November 14, 2023
- Body
- Commerce City Council
- Original file
- 91 KB
Text extracted from the city's file for reading and search. Open the original on cityofcommerce.legistar1.com. That file is the official record.