Cities Index.
Attach 3 - Cost Estimates

Commerce City Council
January 23, 2024

Document
Attach 3 - Cost Estimates
Meeting
January 23, 2024
Body
Commerce City Council
Original file
47 KB
Text extracted from the city's file for reading and search. Open the original on cityofcommerce.legistar1.com. That file is the official record.

Wet Sandblast $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 $ 25,000.00 Slurry Seal on AC Pavement $ 134,000.00 $ 134,000.00 $ 134,000.00 $ 134,000.00 $ 134,000.00 Signing & Stirping $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 $ 50,000.00 TOTAL 'BASE' $ 209,000.00 $ 209,000.00 $ 209,000.00 $ 209,000.00 $ 209,000.00 Alternative 1 Alternative 2 Alternative 3 Alternative 3A Alternative 4 Bike Path Bus Tun Out Share the Road Sharrows No Bike Lanes Remove Curb & Gutter $ - $ 8,750.00 $ - $ - $ - Remove Sidewalk $ - $ 14,000.00 $ - $ - $ - Relocated Bus Benches/Kiosks $ - $ 7,500.00 $ - $ - $ - Relocate Fire Standpipe $ 12,500.00 $ 12,500.00 $ - $ - $ - Remove Landscaping $ 20,625.00 $ 17,000.00 $ - $ - $ - Modify Irrigation $ 3,000.00 $ 3,000.00 $ - $ - $ - Construct Bus Pad $ - $ 128,000.00 $ - $ - $ - Construct Curb & Gutter $ - $ 21,875.00 $ - $ - $ - Construct Sidewalk $ - $ 16,800.00 $ - $ - $ - Construct Bike Ramp $ 10,000.00 $ - $ - $ - $ - Construct Bike Path $ 24,750.00 $ - $ - $ - $ - Construct Retaining Curb $ 21,375.00 $ - $ - $ - $ - Signing & Striping $ 2,500.00 $ 5,000.00 $ 2,500.00 $ 3,500.00 $ (30,000.00) BUS HUB TOTAL $ 94,750.00 $ 234,425.00 $ 2,500.00 $ 3,500.00 $ (30,000.00) "BASE" + BUS HUB TOTAL $ 303,750.00 $ 443,425.00 $ 211,500.00 $ 212,500.00 $ 179,000.00 CONTIGENCIES @10% $ 30,375.00 $ 44,342.50 $ 21,150.00 $ 21,250.00 $ 17,900.00 TOTAL $ 334,125.00 $ 487,767.50 $ 232,650.00 $ 233,750.00 $ 196,900.00 DESIGN @10% $ 33,412.50 $ 48,776.75 $ 23,265.00 $ 23,375.00 $ 19,690.00 CONST. MANAGEMENT @15% $ 50,118.75 $ 73,165.13 $ 34,897.50 $ 35,062.50 $ 29,535.00 GRAND TOTAL $ 417,656.25 $ 609,709.38 $ 290,812.50 $ 292,187.50 $ 246,125.00 USE $ 418,000.00 $ 610,000.00 $ 291,000.00 $ 293,000.00 $ 247,000.00 Alternative 1 - ROW Dedication is Approx. 2,062.5 SF
Alternative 2 - ROW Dedication is Approx. 1,700 SF
Atlernative 3 - Estimated $30,000 reduction in costs by not re-installing bike lanes (Shiela Street to Harbor Street)

EASTERN AVENUE BETWEEM SHEILA STREET AND HARBOR STREET

EASTERN AVENUE BUS HUB MODIFICATION

← All documents from this meeting