1 PROJECT OVERVIEW
The Los Angeles County Metropolitan Transportation Authority (Metro) Countywide Signal Priority (CSP) Upgrade and Expansion NextGen Project (NextGen) will deploy Bus Signal Priority (BSP) systems along several corridors throughout Los Angeles County. The CSP systems to be deployed will be based on the technologies, hardware, and software developed, tested, and placed into “on the street” operation as defined by Metro’s CSP Standard.
CSP Compliant Systems have been deployed throughout Los Angeles County along several major corridors.
This project seeks to commission new BSP systems along some corridors and modernize existing systems for others.
The project includes the design, procurement, installation, and testing of a bus signal priority (BSP) system to support Metro’s Bus service. Traffic signal improvements other than controller and controller software upgrades, such as cabinet change-outs and installation of new traffic signal cables, and street improvements, such as ADA improvements, curb replacements, median modifications, and access ramps are not included in the scope of work.
As part of the project, the design team will conduct meetings with each of the affected local agencies responsible for traffic signal operations and maintenance to discuss the placement of the WLAN equipment including antennas, enclosures, and hardware mounted in the intersection controller cabinets as well as the use of existing conduits, the possible use of existing signal interconnect, communication, traffic controller and controller cabinet upgrades, and equipment installation requirements in the following corridors:
Line 260 Atlantic Blvd
Line 180 Colorado Blvd
Line 210: Crenshaw Blvd
Line 70 Garvey Ave/Cesar Chavez Ave
Line 212: Hawthorne Blvd
Line 60: Long Beach Blvd
Line 111: Florence Ave
Line 115: Manchester Blvd
Line 4: Santa Monica Blvd
Line 78: Main St
Line 108: Slauson Ave
Line 180: Los Feliz Rd-Brand Ave-Broadway
2 PROJECT MAP
3 CITY OF COMMERCE MAP
4 LIST OF INTERSECTIONS IN CITY OF COMMERCE
1. Everington St & Atlantic Blvd
2. Harbor St & Atlantic Blvd
3. Jardine St & Atlantic Blvd
4. Jillson St & Atlantic Blvd
5. Washington Blvd & Atlantic Blvd
6. Sheila Street & Atlantic Blvd
7. E Slauson Ave & S Eastern Ave
8. E Slauson Ave & Zambrano St
9. E Slauson Ave & Alexander St
10. E Slauson Ave & Boxford Ave
11. E Slauson Ave & S Malt Ave
12. E Gage Ave & I-5 SB On/Off Ramp
13. E Slauson Ave & Triangle Dr
14. Slauson Ave & Greenwood Ave
15. E Slauson Ave & Garfield Ave
5 PROJECT CONTACT INFORMATION
LOS ANGELES METROPOLITAN TRANSPORTATION AUTHORITY - METRO Eva Moon
Senior Manager, Transportation Planning
[email protected]
(213) 418-3285
CONSULTANT PROJECT TEAM – PARSONS
Christine Simonton
[email protected]
(470) 898-2140
CONSULTANT PROJECT TEAM – ITERIS
Alek Hovsepian
[email protected]
(818) 621-4208