3/27/2023
Contractor's Price Proposal - Detail
Subcontractor Listing
111841.00
Compton - Community Security Services
CA-R8-GB13-123021-MDJIQC Master Contract #:
Work Order #:
Owner PO #:
Title:
Re:
March 27, 2023Date:
Proposal Value:
Contractor: MDJ Management
$1,863,265.36
%DutiesName of Contractor Amount
Express Energy Services, Inc. 25.49$475,000.00
Horizons Construction Company
Intl. Inc
20.13$375,000.00
Refined Construction 32.20$600,000.00
6.00
3/27/2023
Subcontractor Listing
City of Compton
Community Security Services site improvements
404 N. Alameda Street, Compton, CA 90221
Who is Gordian?
Gordian is the leading provider of facility and construction cost data, software and expertise. 30+ year
history
delivering
procurement
solutions
$3.2 billion in
construction
volume
annually
$270 million
Job Order
Contracting
projects
healthcare
30,000
construction
projects each
year
Effectively
Manage the
Entire
Building
Lifecycle
• Governed by a board of directors
• Staff are public employees
• Have Legislative Authority to facilitate the
Competitive Bidding Process Competitively
Solicit & Award Contracts to Create Efficiency
Sourcewell is a leading, independent
government agency
www.sourcewell-mn.gov
Competitively
solicited
Awarded
contract
Membership
Legal
authority
Works with
How it works
Vendor
contractors
A legal contracting pathway between buyers & contractors And procures directly via ezIQC®
Sourcewell
Member
ezIQC
Contractor
Gordian
Team
Tamiko Gutierrez
Director of Operations, ezIQC CA
Maribel Olivares
Account Manager, ezIQC CA
Randy Horn
Director
Business Development, West
Michael Celesta
Account Executive,
Business Development
• Founded in 2017
• Local South Los Angeles contractor, located in El
Segundo
• CSLB B-License #1044711 (active)
• DIR Registration #1000061313 (active)
• High performing contractor within ezIQC JOC
program in California, since 2018
• Maintains a positive procurement and
construction record for projects performed within
ezIQC program in California
• Experienced in water damage/abatement,
demolition and removal, new construction,
interior remodels/modernizations, exterior site
and specialty work
MDJ
Management
MDJ Management – project resume
City of Pomona Transit Center beautification project
Scope of Work Details:
Security Wall
• Demolish existing exterior wall and
haul away
• Install 10-foot tall CMU wall
• Reinforce footings per
specifications
• CMU cells to be concrete filled
• Install 5-foot no climb fencing on top
of CMU wall
• Install four new K12 anti-ram and
anti-climb sliding gates
• Install one new 10-foot pedestrian
metal gate to match sliding gates
Exterior Security Wall
Interior Security Wall
• Demolish existing interior wall and
haul away
• Install 10-foot tall CMU wall
• Reinforce footings per
specifications
• CMU cells to be concrete filled
• Install 5-foot no climb fencing on top
of CMU wall
10 ft CMU
5 ft No Climb Fencing
New installation of CMU wall and No Climb Fence to be similar as above picture.
Scope of Work Details:
Building Demolition
Building Demolition
• Demolish existing 2,300 SF building
• Existing building to be considered
positive for lead paint and asbestos
containing material
• Demolition of building to be
completed by certified hazmat
demolition company
Scope of Work Details:
Lighting & Security Cameras
Exterior Lighting & Security Cameras
• Installation of new 400 amp main panel on wall of existing building. • Installation of new light poles to light up entire facility with insurance of no “dark” areas.
• Demolition of existing light poles and installation of 8 light poles with 24 LED fixtures.
• Installation of 4 Wall LED and 2 Canopy LED light fixtures mounted on existing building.
• All six exterior poles will have 2 HD Cameras installed and both entrance poles will have license plate readers.
• Both middle poles will have 3 HD Cameras installed
• Installation of new security cameras
• DVR recorder
• Camera types to include:
• License plate reader
• High definition cameras
Middle Poles: 3
HD Cameras
Exterior Poles: 2 HD
Cameras
Front Poles: License plate
readers & 2 HD Cameras
New
Lighting
Installation
Fixture
Schedule
LED Wall Pack Luminaire (WPE
Series): WPE-60-50K
LED Area Luminaire (AL XE G3 Series):
AL-200-50K
Round LED Parking Garage
Canopy (RPC Series): RPC-55-50K
New
Security
Cameras
Installation
Fixture
Schedule
WISENET X Series: XNP-6550RH
WISENET P Series: PNV-A9081RLP
WISENET WAVE Network Video
Recorder: WRR-Q-A200W
New Lighting Installation Footcandles
Scope of Work Details:
Asphalt
Asphalt
• Demo all existing asphalt and concrete
• Regrade entire site with proper drainage
• Installation of new asphalt for lot
• Install of new striping throughout
parking lot
Striping to be approved and
finalized by City.
Job Start
Security Wall
Completion
Building Demolition
Security Cameras
& Lighting
Asphalt
MAY
JUN
JUL
AUG
OCT
SEPT
NOV
DEC
Mid June
*Security cameras & lighting estimated to be completed in 4-6 weeks with lead times of four (4) weeks for cameras June – September
July
August – September
September - October
Mid October
*Security wall estimated to be completed in three (3) months *Building demolition estimated to be completed in two (2) weeks *Contractor to start work within 30 days after NTP is issued *Asphalt estimated to be complete in one (1) month
*Estimated timeline for project completion is 4 months with some parts of scope overlapping with one another. Detailedconstruction schedule to be provided upon project approval
Project Timeline
Thank you
Questions?