Date: October 12, 2021

Page 1 of 2 ends

PROJECT DESCRIPTION:

PROJECT NO: 56-1203 Caltrans EA:08-0J6104 PURCHASE ORDER NO: P18879 CONTRACTOR: Jacobs Engineering Group, Inc
2600 Michelson Drive Suite 500
Irvine, CA 92612
DESCRIPTION OF CHANGES AND/OR EXTRA WORK:

The Contractor is hereby directed to make the herein described changes from the plans and specifications and/or perform the following described work not included in the Plans and Specifications for this project.

ITEM DESCRIPTION U/M QUANTITY UNIT PRICE TOTAL
7 LS 1.00 $32,731.00 $32,731.00
8 LS 1.00 $68,080.00 $68,080.00
9 LS 1.00 $52,242.00 $52,242.00
10 LS 1.00 $12,110.00 $12,110.00
TOTAL ESTIMATED PRICE FOR THIS CHANGE ORDER: $165,163.00 JUSTIFICATION: (Be specific on each item. Attach supporting documents as necessary) S-7 Update the Right of Way appraisal maps with new parcel numbers provided by Caltrans and revise all call-outs for the correct ownership.

Update ROW certification and coordinate with Crown Castle and AT&T on completion of relocation work. Update the ROW Certificate No. 3W
S-8 Prepare Record of Survey Map including the new monuments/property ties at the right of way lines. Submit to the County of Riverside Surveyors Office for review and final recordation of the map. After acceptance by the County Surveyor's Office submit a mylar version to the County Recorders for recordation.

S-9 Provide deed jackets for up to9 parcels, coordinate deed processing with Caltrans , Secure preliminary title reports if needed. Using PTR or Policy of Title Insurance, prepare Title Abstract Summary showing encumbrances on title, description of why not detrimental to State's use. If detrimental to State use coordinate to clear encumbrances from report/policy. (Assumption no cost clearing Title).

S-10 Prepare 9 deed jackets for conveyance of property from City to Caltrans, Preliminary Title Reports if needed for each parcel will be secured. Plans check fees / recording for Record of Survey This document shall become an amendment to the Contract and all provisions of the Contract will apply hereto. This Change Order constitutes a complete and final resolution of all claims of the Contract for additional time or additional compensation related to or affected by work that is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated.

Survey/Right of Way Engineering (DEA)
Right of Way Services (OPC)

CITY OF CORONA
Public Works Department
CONTRACT CHANGE ORDER NO. 6
Project Management and Roadway Design (Jacobs)
Other Direct Cost (ODC)
Cajalco Road/I15 Interchange Improvement - Engineering Design and Right of Way Services G:\CIP\CIP Master\Projects\56-1203 I-15 Cajalco Rd Interchg Improve\F- Financial\F-6 Change Orders (CCO) & Supporting Docs\Jacobs\PSA Amendment 7\Jacobs PSA Amendment 6 Date: Date: October 12, 2021

Page 2 of 2 ends

CONTRACT VARIANCE SUMMARY
CCO # % Date Approved
1 $146,889.00 3.85%
2 300,000.00 7.87%
3 866,783.00 22.73%
4 134,206.00 3.52%
5 0.00 0.00%
6 $165,163.00 4.33%
Total 42.30%
$5,426,433.26
Original Completion Date: November 12, 2019 Revised Completion Date: June 30, 2023 AUTHORIZATION BY CITY:

Recommended for approval by:

Date: __________ Date: __________
Peter Ramey, Project Manager Barry Ghaemi, P.E., Senior Civil Engineer Approved by:

Date: __________
Savat Kamphou, P.E., Public Works Director
ACCEPTANCE BY CONTRACTOR:

We, the undersigned Contractor, have given careful consideration to the above described changes and/or extra work and hereby agree that said work is a supplement to the contract and all provisions will apply hereto.

Accepted by: _____________________________________________________ Title: ____________________________ (Please print name and title)
Signature: _____________________________________________________ Date: ____________________________ 8/17/2015
12/3/2013
Amount Time
194
0 ____________________________________________ ____________________________________________ ________________________________________
Date Started: June 11, 2012
06/30/2020 - 09/30/2020
0 $1,613,041.00
Original Contract Amount
3/1/2017
8/5/2020
$3,813,392.26 Revised Contract Amount
0 0
11/12/2019 - 06/30/2020
G:\CIP\CIP Master\Projects\56-1203 I-15 Cajalco Rd Interchg Improve\F- Financial\F-6 Change Orders (CCO) & Supporting Docs\Jacobs\PSA Amendment 7\Jacobs PSA Amendment 6