Cities Index.
McKinley Street Grade Separation Update (002)

Corona City Council
March 16, 2022

Document
McKinley Street Grade Separation Update (002)
Meeting
March 16, 2022
Body
Corona City Council
Original file
9.7 MB
Text extracted from the city's file for reading and search. Open the original on corona.legistar1.com. That file is the official record.

McKinley Street
Grade Separation
Savat Khamphou
Public Works Director
Joshua Cosper
Project Manager
March 16, 2022
City Council
Update
Presentation
Outline
➝ Project Layout
➝ Utility Relocation Activities
➝ Construction Impacts
➝ Right of Way Requirements
➝ Public Outreach
➝ Next Steps
Project Layout
Project Layout | Overview (Looking NW’ly)
Project Layout | Overview (Looking W’ly)
Project Layout | Overview (Looking SE’ly)
Project Layout | Overview (Looking NE’ly)
Project Layout | Overview (Looking Southerly)
Utilities| Relocations
AT&T (Telecommunications)
Complete
Riverside Public Utilities (Water)
Complete
Southern California Gas (Gas)
Complete
Southern California Edison (Electric)
Completion May 2022
Construction Impacts | Stage 1
Duration: Approx. April, 2022 through Q1, 2023
Construction Impacts | Stage 2
Duration: Approx. Q1, 2023 through end of Q2, 2023
Construction Impacts | Stage 3
Duration: Approx. Q2, 2023 through end of 2023
Construction Impacts| Recommended Detour Plan
To / From West of
McKinley Street
Through Construction
W. 6th St
Radio Rd
Project
Limits
Freeways
Local Roads
Construction Impacts| Recommended Detour Plan
To / From East of
McKinley Street
Through Construction
Project
Limits
Freeways
Local Roads
Pierce St
Construction Impacts| Recommended Detour Plan
To / From North
and South of
McKinley Street
Through Construction
Project
Limits
Freeways
Local
Roads
Radio Rd
El Camino Rd
6th St
Construction Impacts| Recommended Detour Plan
Estelle Street
Through Construction Project
Limits
Local Roads
R/W Requirements| Acquisition Progress
Rail / Flood
• Private Properties (Complete)
• BNSF/RCFC (Complete)
Offers/Negotiations
• Possession secured – 10
properties
• Settlement reached – 5
properties
• Businesses Settled - 6
Relocation (None)
• City has secured possession of
Denny’s and Outback buildings
• Demolition of Buildings
Complete
Project Layout | R/W Requirements
Public Outreach
General Public
• Conducted Virtual Presentation – 11/12/2020
• Over 100 People Registered with 57 Community Members Attending • Conducted Virtual Presentation – 5/4/2021
• 67 Community Members Attended
• Conducted In-Person/Virtual Presentation – 12/7/2021
• 61 Community Members Attended Virtually, 8 in Person
Next Public Outreach
• Mid to End of April, 2022
• Virtual Meeting via Zoom
• Routine Outreach Efforts During Construction
• Met with Local Businesses on March 3
• Bi-monthly Public Notifications / Broadcasts
• Hot-Line Phone Number – (800) 546-3299
• Project Email – [email protected]
• Interactive Map for Upcoming Traffic Consideration / Project Pictures Currently Live on the Project Website: McKinley Grade Separation | City of Corona (coronaca.gov)
• Aerial Drone, Time Lapse, Ground Photography
Business Outreach
Outreach Meeting Completed
March 3, 2022
• Hand Delivered Flyers Mid
February
• Breakfast at Mimi’s Café
• 5 Local Business Attended
• 3 in the Los Arcos Plaza, 2 in the
former Food-4-Less shopping center
• Discussion Topics
• Project Impacts
• City Economic Development
Available Support
Next Steps
Continue Utility Relocation Efforts
• Complete Southern California Edison’s Relocation
Construction
• Contractor to Finish Securing Approvals/Permits and Provide Key Submittals Anticipated Early Q1, 2022
• Commence Early Stages of Construction Anticipated Late Q1 to Early Q2, 2022
Continue Public Outreach Efforts

← All documents from this meeting