McKinley Street
Grade Separation
Savat Khamphou
Public Works Director
Joshua Cosper
Project Manager
March 16, 2022
City Council
Update
Presentation
Outline
➝ Project Layout
➝ Utility Relocation Activities
➝ Construction Impacts
➝ Right of Way Requirements
➝ Public Outreach
➝ Next Steps
Project Layout
Project Layout | Overview (Looking NW’ly)
Project Layout | Overview (Looking W’ly)
Project Layout | Overview (Looking SE’ly)
Project Layout | Overview (Looking NE’ly)
Project Layout | Overview (Looking Southerly)
Utilities| Relocations
AT&T (Telecommunications)
Complete
Riverside Public Utilities (Water)
Complete
Southern California Gas (Gas)
Complete
Southern California Edison (Electric)
Completion May 2022
Construction Impacts | Stage 1
Duration: Approx. April, 2022 through Q1, 2023
Construction Impacts | Stage 2
Duration: Approx. Q1, 2023 through end of Q2, 2023
Construction Impacts | Stage 3
Duration: Approx. Q2, 2023 through end of 2023
Construction Impacts| Recommended Detour Plan
To / From West of
McKinley Street
Through Construction
W. 6th St
Radio Rd
Project
Limits
Freeways
Local Roads
Construction Impacts| Recommended Detour Plan
To / From East of
McKinley Street
Through Construction
Project
Limits
Freeways
Local Roads
Pierce St
Construction Impacts| Recommended Detour Plan
To / From North
and South of
McKinley Street
Through Construction
Project
Limits
Freeways
Local
Roads
Radio Rd
El Camino Rd
6th St
Construction Impacts| Recommended Detour Plan
Estelle Street
Through Construction Project
Limits
Local Roads
R/W Requirements| Acquisition Progress
Rail / Flood
• Private Properties (Complete)
• BNSF/RCFC (Complete)
Offers/Negotiations
• Possession secured – 10
properties
• Settlement reached – 5
properties
• Businesses Settled - 6
Relocation (None)
• City has secured possession of
Denny’s and Outback buildings
• Demolition of Buildings
Complete
Project Layout | R/W Requirements
Public Outreach
General Public
• Conducted Virtual Presentation – 11/12/2020
• Over 100 People Registered with 57 Community Members Attending • Conducted Virtual Presentation – 5/4/2021
• 67 Community Members Attended
• Conducted In-Person/Virtual Presentation – 12/7/2021
• 61 Community Members Attended Virtually, 8 in Person
Next Public Outreach
• Mid to End of April, 2022
• Virtual Meeting via Zoom
• Routine Outreach Efforts During Construction
• Met with Local Businesses on March 3
• Bi-monthly Public Notifications / Broadcasts
• Hot-Line Phone Number – (800) 546-3299
• Project Email – [email protected]
• Interactive Map for Upcoming Traffic Consideration / Project Pictures Currently Live on the Project Website: McKinley Grade Separation | City of Corona (coronaca.gov)
• Aerial Drone, Time Lapse, Ground Photography
Business Outreach
Outreach Meeting Completed
March 3, 2022
• Hand Delivered Flyers Mid
February
• Breakfast at Mimi’s Café
• 5 Local Business Attended
• 3 in the Los Arcos Plaza, 2 in the
former Food-4-Less shopping center
• Discussion Topics
• Project Impacts
• City Economic Development
Available Support
Next Steps
Continue Utility Relocation Efforts
• Complete Southern California Edison’s Relocation
Construction
• Contractor to Finish Securing Approvals/Permits and Provide Key Submittals Anticipated Early Q1, 2022
• Commence Early Stages of Construction Anticipated Late Q1 to Early Q2, 2022
Continue Public Outreach Efforts
McKinley Street Grade Separation Update (002)
Corona City Council
March 16, 2022
- Document
- McKinley Street Grade Separation Update (002)
- Meeting
- March 16, 2022
- Body
- Corona City Council
- Original file
- 9.7 MB
Text extracted from the city's file for reading and search. Open the original on corona.legistar1.com. That file is the official record.