U.S. Army Corps of Engineers
April 6, 2022

SANTA ANA RIVER MAINSTEM
PROJECT – ALCOA DIKE PHASE 2
UPDATE FOR: CITY OF CORONA, CA
UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 2

PRADO BASIN PROJECT FEATURES
Prado Basin will contain the Standard
Project Flood event (approx. 190-year)
Dike features will provide protection up
to the 566-ft elevation around the
perimeter of the basin
UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 3 ALCOA DIKE PHASE 2 PROJECT
Status:
• Awarded 3-Sep-2021 to Empire
Equipment Service for $24,495,408
• Information flyers were mailed to
nearby residents and businesses.
• Earthwork and road relocations -
December 2021 - December 2023.
• Hydroseed application and 12-
month maintenance period -
December 2023 - December 2024.
• Project will be turned over to
Orange County Public Works for
long term maintenance in January
2025.

UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 4

TEMPORARY AUBURNDALE STREET CLOSURE
UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 5

AUBURNDALE FLOODGATE
Auburndale Floodgate:
• Connects Alcoa Dike across Auburndale St.
• 19-ft high x 36-ft wide swing gate
• Swing gate is normally open, only closed when
water is impounded to Auburndale St.
• 19-ft high concrete floodwalls transition from
floodgate to dike embankment.
• Gate will swing 180 degrees.
• Will include a push/pull bar to facilitate manual
operation of the gate. It is anticipated that a
small tractor can be used to operate the gate.

UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 6

TEMPORARY RINCON STREET CLOSURE
UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 7 BUTTERFIELD PARK CLOSURE Butterfield Connector Road
2 1
3 4
Butterfield Park Schedule:

Close (partial): 07 April 2022
Open: * January 2023
*Field 1 and adjacent parking lot (Smith Ave) permanently closed UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 8

FINAL ROAD RE-ALIGNMENT LAYOUT
Road Relocation Plan at Rincon
and Butterfield:
• New Butterfield Connector
Road will connect Rincon Street
to Butterfield Drive and will be
the new access to Corona
Municipal Airport and Butterfield
Park. (Scheduled completion
October 2022)
• Existing Rincon St. will be
raised to cross over the Alcoa
Dike (Scheduled completion
April 2023)
• Existing Butterfield Rd. will be
removed between Smith Ave.
and new connector road
(Scheduled completion May
2023)
Permanent Road Closure
May 2023
Butterfield Connector
Road
Rincon Street Re-alignment
To Airport & Butterfield Park
UNCLASSIFIED/FOUO/PRE-DECISIONAL/NOT FOR DISTRIBUTION 9

QUESTIONS