1 Julianna Zaleski
Associate Engineer
Public Works Department
City Council, September 21, 2022
ONTARIO AVENUE
WIDENING AT
LINCOLN AVENUE
The Ask
That City Council authorize the creation of
the Capital Improvement Project, “Ontario
Avenue Widening at Lincoln Avenue.”
3 ▷ Reduce congestion by improving traffic capacity on Ontario Avenue ▷ Improve pedestrian mobility by installing ADA compliant sidewalks and curb ramps ▷ Improve safety at the intersections of Lincoln/Ontario and Lincoln/Othello ▷ Complete the missing and/or deficient civil improvements (curb and gutter, sidewalks, raised medians, roadway, street lighting, etc.)
▷ Complete the missing or deficient traffic improvements (traffic signals, pedestrian push buttons, etc.)
▷ Comply with the City of Corona Strategic Plan, Strategic Goals: Sound Infrastructure and Safe Community
Purpose and Need
Project
Vicinity
NTS
Project
Location
Ontario Avenue from Oak Avenue to S. Vicentia Avenue
&
Lincoln Avenue from Ontario Avenue to Othello Lane
NTS
6 Ultimate curb and cutter matching adjacent improved areas Existing Right of Way
45 mph
28 FT
NTS
Existing Right of Way 7
45 mph
28 FT
8 45 mph
Looking East from the Intersection
of Ontario and Lincoln
Looking West from the Intersection
of Ontario and Conejo
Proposed Improvements
• Widen Ontario Avenue from 4 to 6 through lanes and include left turn pockets at intersections • Construct curb & gutter, catch basins, parkways, sidewalks, street lighting, and modify driveways • Construct landscaped raised median islands on Ontario between Lincoln and S. Vicentia • Construct ADA compliant curb ramps at intersections
• Modify the existing signalized intersections to accommodate improvements • Install a new traffic signal at Lincoln and Othello
• Relocate existing utilities as necessary
9 $796,166
$404,560
$394,133
$1,023,276
$1,081,865
$2,300,000
$6,000,000
Landscape Project 80080274 Fund
Development Impact Fees Fund 274 (Landscape)
Development Impact Fees Fund 212 (Drainage)
Development Impact Fees Fund 211 (Streets & Traffic)
Measure A Fund 227*
TUMF Allocation from WRCOG
Preliminary Engineer’s Estimate
*Currently pursuing grant opportunities to offset allocation. 10 Preliminary Engineer’s Estimate and Funding Sources
Proposed Project Duration
11 Planning, Design &
Environmental Construction
Right of Way & Temporary
Construction Easements
12 MONTHS 6 MONTHS 18 MONTHS
Staff’s Recommendation
That the City Council authorize the creation of
Capital Improvement Project No. 2022-12 “Ontario
Avenue Widening at Lincoln Avenue,” and approve
the associated actions to create the project.
Questions?
951-736-2264
[email protected]