1 Savat Khamphou &
Joshua Cosper
Quarterly Update
April 5, 2023

MCKINLEY STREET

GRADE SEPARATION
Presentation Outline
2 • Project Status • Utility Relocation Activities • Construction Activities • Traffic Control / Detours • Construction Look Ahead • Right of Way Status • Economic Development • Public Outreach • Next Steps Project Status
Utilities – Relocation Activities
4 AT&T (Telecommunications)
Complete
Riverside Public Utilities (Water)
Complete
Southern California Gas (Gas)
Complete
Southern California Edison (Electric)
Complete
Utilities – Relocation Activities
5 • Utility Relocation
Summary
• Pending Activities
• Miscellaneous
Adjustments
• WMWD & City of
Corona DWP
• Close out for the RPU &
WMWD Agreements
Construction – Recent Activities
6 • Piles and Columns
• East Side
• West Side
• Miscellaneous
• Sign Removals
• Preparation for Sewer and
Water
• Preparation for West Side
Retaining Walls
Construction – Steel Fabrication
7 Construction – Steel Fabrication
8 Construction – Steel Fabrication
9 Construction – Steel Fabrication
10 Construction – Traffic Control
11 • Temporary Traffic Control
• South of Sampson
• Thru Lanes
• Shopping Center Access
• Pedestrian Access
• North of Sampson
• Thru Lanes
• Business Center Access
• Pedestrian Access
Construction – Detour
12 Construction
– Detour
13 • Additional Signage • Advanced Warning
Signs
• Changeable
Message Signs
• Trucks • Avoid McKinley
between Magnolia
and SR-91
• Outreach Efforts • Truck Detour Plan • Detour Notification • Businesses North of SR -
91 Construction Look Ahead
Construction – Look Ahead
15 • Miscellaneous Storm
Drain, WMWD, and City
DWP Work
• Retaining Walls &
Abutments
• Permanent Along West
Side
• Temporary Retaining Walls
• Steel Bridge Fabrications
• Continued Fabrication
• On-Site Mobilization /
Bridge Move
• Delays in the Process
Right of Way Status
R/W Requirements – Acquisition Progress
17 • Rail / Flood
• Private Properties (Complete)
• BNSF/RCFC (Complete)
• Offers/Negotiations
• Possession secured – All
properties
• Settlement reached – 9
properties
• Businesses Settled - 21
• Remaining
• 3 Properties
• 6 Businesses
https://www.coronaca.gov/home/showpublish
eddocument/20374/637750798403470000
Economic Development
Economic Development Outreach
19 78
Businesses
connected with
via phone calls, inperson visits, and
email
Business
Spotlights
3 completed
5 underway
Economic Development Support
20 • Targeted Business Promotion
• Monthly Newsletter
• Business/Shopping Center Spotlight
• Social Media
• Workforce Support
• Subsidized training (On-the-Job training)
• Live Work Corona (Spring Job Fair)
• Funding opportunties
• Grants for small businesses
• Focused on business resiliency, education and
support
• Launching in 2023
• External Grants and Funding
• Business Assistance Now Program
Public Outreach
Public Outreach
22 • General Public • Virtual Presentations • 11/12/2020 • 5/4/2021 • 8/11/2022 • In-Person/Virtual Presentation • 12/7/2021 • 1/24/2023 • Next Public Outreach – April/May, 2023 (Virtual) • Routine Outreach Efforts During Construction • Economic Development • Text Program - Text MCKINLEY to 844-518-1409 to stay in the loop!
• Bi-monthly Public Notifications / Broadcasts
• Hot-Line Phone Number – (800) 546-3299
• Project Email – [email protected]
• Interactive Map on the Project Website: McKinley Grade Separation | City of Corona (coronaca.gov)
• Aerial Drone, Time Lapse, Ground Photography
Next Steps
Next Steps
24 • Construction
• Underground Water, Sewer and Storm Drain Facilities
• Retaining Walls and Fill Operations Along West of
McKinley
• Continue Steel Fabrication and Prepare for Bridge Move • Next Traffic Control Operations
• Continue Partnering with Walsh Construction of Value
Engineering Ideas
• Continue Public Outreach Efforts
Questions?